2020-197-DM
- Let date
- Friday, March 5, 2021
- Contract
- 62M70 · job page
- District
- District 1
- County
- Lake
- Highway
- Limits
- This is a building demolition project for gas station. Work includes removing of all existing improvements: one-story building, canopy with gas pumps and storage tanks. Location: 491 South IL. Route 83, Village of Grayslake.
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lima Contractors Low bidder | $367,612 | ||
| 2 | Berger Excavating Contractors, Inc. | $393,262 | +7.0% | |
| 3 | Campanella and Sons, Inc. | $401,210 | +9.1% | |
| 4 | Lake County Grading Company, LLC | $420,000 | +14.3% | |
| 5 | Copenhaver Construction, Inc. | $461,740 | +25.6% | |
| 6 | Scanlon Excavating & Concrete, Inc. | $493,356 | +34.2% | |
| 7 | MYS, Incorporated | $712,937 | +93.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lima Contractors | #2 Berger Excavati… | #3 Campanella and … | #4 Lake County Gra… | #5 Copenhaver Cons… | #6 Scanlon Excavat… | #7 MYS, Incorporat… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0300249 | REMOV EX GATE | 1 | EACH | $300.00 | $250.00 | $232.50 | $350.00 | $500.00 | $500.00 | $500.00 | |
| 2 | X0321690 | BRICK WALL REMOV | 36 | FOOT | $28.00 | $20.00 | $17.23 | $20.00 | $100.00 | $20.00 | $30.00 | |
| 3 | X0322791 | FILL EXIST SAN SEWER | 2 | CU YD | $380.00 | $566.38 | $940.00 | $300.00 | $600.00 | $1,500.00 | $3,500.00 | |
| 4 | X0325815 | REMOVE EXISTING CABLE | 561 | FOOT | $3.00 | $1.75 | $2.07 | $0.0100 | $1.00 | $4.00 | $1.00 | |
| 5 | X0327009 | REMOVE SIGN SPECIAL | 2 | EACH | $1,500.00 | $1,500.00 | $580.00 | $2,000.00 | $700.00 | $2,000.00 | $1,500.00 | |
| 6 | X0350810 | BOLLARD REMOVAL | 18 | EACH | $200.00 | $20.00 | $64.45 | $50.00 | $150.00 | $100.00 | $115.00 | |
| 7 | X0840000 | SAN SEW REMOV 8 | 92 | FOOT | $8.00 | $11.00 | $12.61 | $15.00 | $55.00 | $15.00 | $50.00 | |
| 8 | X1700114 | CONCRETE PAD REMOVAL | 297 | SQ FT | $3.00 | $6.00 | $1.97 | $1.50 | $4.00 | $4.00 | $3.00 | |
| 9 | X5510100 | STORM SEWER REMOVAL | 579 | FOOT | $11.00 | $9.00 | $6.77 | $10.00 | $12.00 | $8.00 | $50.00 | |
| 10 | X5620124 | WATER SERV LINE REM | 40 | FOOT | $37.00 | $8.00 | $11.50 | $25.00 | $50.00 | $100.00 | $300.00 | |
| 11 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $33,000.00 | $29,000.00 | $18,791.25 | $67,971.27 | $14,000.00 | $25,000.00 | $32,500.00 | |
| 12 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $8,500.00 | $7,500.00 | $9,548.75 | $5,000.00 | $19,000.00 | $8,500.00 | $30,000.00 | |
| 13 | Z0015500 | DEBRIS REMOVAL | 1 | L SUM | $1,000.00 | $2,000.00 | $2,098.75 | $2,000.00 | $5,500.00 | $5,000.00 | $5,000.00 | |
| 14 | Z0030850 | TEMP INFO SIGNING | 135 | SQ FT | $3.00 | $15.00 | $3.15 | $3.00 | $20.00 | $25.00 | $25.00 | |
| 15 | Z0055905 | TEMP CONSTR FENCE | 726 | FOOT | $7.00 | $8.00 | $4.75 | $12.34 | $10.00 | $6.50 | $5.00 | |
| 16 | Z0064800 | SELECTIVE CLEARING | 2 | UNIT | $450.00 | $400.00 | $420.00 | $450.00 | $700.00 | $2,000.00 | $500.00 | |
| 17 | 20100110 | TREE REMOV 6-15 | 8 | UNIT | $30.00 | $120.00 | $126.00 | $90.00 | $50.00 | $30.00 | $75.00 | |
| 18 | 20101400 | NITROGEN FERT NUTR | 61 | POUND | $0.0100 | $0.0100 | $2.10 | $1.00 | $1.00 | $3.00 | $0.0100 | |
| 19 | 20101600 | POTASSIUM FERT NUTR | 61 | POUND | $0.0100 | $0.0100 | $2.10 | $1.00 | $1.00 | $3.00 | $0.0100 | |
| 20 | 20101700 | SUPPLE WATERING | 7 | UNIT | $800.00 | $50.00 | $105.00 | $0.1000 | $0.0100 | $125.00 | $60.00 | |
| 21 | 20800150 | TRENCH BACKFILL | 28 | CU YD | $60.00 | $43.00 | $99.86 | $20.00 | $45.00 | $40.00 | $125.00 | |
| 22 | 21101625 | TOPSOIL F & P 6 | 3,261 | SQ YD | $5.00 | $5.00 | $5.25 | $0.1000 | $6.00 | $6.50 | $5.75 | |
| 23 | 25000210 | SEEDING CL 2A | 0.75 | ACRE | $3,000.00 | $3,000.00 | $1,890.00 | $20,000.00 | $3,000.00 | $2,500.00 | $3,500.00 | |
| 24 | 25100115 | MULCH METHOD 2 | 0.75 | ACRE | $3,500.00 | $3,500.00 | $2,835.00 | $10,000.00 | $3,000.00 | $3,500.00 | $4,000.00 | |
| 25 | 28000400 | PERIMETER EROS BAR | 701 | FOOT | $2.50 | $2.50 | $2.10 | $2.50 | $3.00 | $3.00 | $3.00 | |
| 26 | 28000510 | INLET FILTERS | 1 | EACH | $500.00 | $195.00 | $235.00 | $200.00 | $110.00 | $125.00 | $220.00 | |
| 27 | 30300001 | AGG SUBGRADE IMPROVE | 1,620 | CU YD | $35.00 | $49.25 | $46.27 | $45.00 | $38.00 | $40.00 | $45.00 | |
| 28 | 44000100 | PAVEMENT REM | 2,071 | SQ YD | $4.00 | $5.50 | $6.53 | $6.00 | $14.00 | $6.00 | $15.00 | |
| 29 | 44000300 | CURB REM | 180 | FOOT | $5.00 | $3.00 | $3.25 | $6.00 | $8.00 | $10.00 | $10.00 | |
| 30 | 44000500 | COMB CURB GUTTER REM | 134 | FOOT | $5.00 | $3.00 | $13.69 | $6.00 | $7.00 | $10.00 | $10.00 | |
| 31 | 44000600 | SIDEWALK REM | 503 | SQ FT | $2.00 | $1.45 | $1.17 | $1.00 | $3.00 | $2.00 | $5.00 | |
| 32 | 60500040 | REMOV MANHOLES | 1 | EACH | $800.00 | $445.00 | $350.00 | $600.00 | $700.00 | $550.00 | $1,000.00 | |
| 33 | 60500050 | REMOV CATCH BAS | 2 | EACH | $400.00 | $300.00 | $350.00 | $600.00 | $600.00 | $550.00 | $1,000.00 | |
| 34 | 60603800 | COMB CC&G TB6.12 | 102 | FOOT | $38.00 | $52.25 | $54.85 | $52.24 | $28.00 | $50.00 | $45.00 | |
| 35 | 66900105 | UNDERGR STOR TANK REM | 6 | EACH | $6,472.00 | $6,055.00 | $1,466.25 | $7,000.00 | $6,700.00 | $20,000.00 | $17,500.00 | |
| 36 | 66900200 | NON SPL WASTE DISPOSL | 1,610 | CU YD | $54.50 | $67.55 | $82.98 | $55.00 | $85.00 | $65.00 | $125.00 | |
| 37 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,460.00 | $1,150.00 | $1,132.65 | $1,500.00 | $1,400.00 | $1,500.00 | $1,400.00 | |
| 38 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $500.00 | $4,000.00 | $2,460.00 | $3,500.00 | $3,200.00 | $10,000.00 | $3,000.00 | |
| 39 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,440.00 | $950.00 | $2,870.00 | $3,500.00 | $2,400.00 | $1,500.00 | $4,000.00 | |
| 40 | 66901006 | REG SUB MON | 7 | CAL DA | $1,150.00 | $800.00 | $1,235.15 | $1,000.00 | $700.00 | $500.00 | $1,500.00 | |
| 41 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,000.00 | $1,500.00 | $2,500.00 | $2,000.00 | $1,500.00 | $500.00 | $2,000.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $21,000.00 | $23,160.00 | $41,609.00 | $25,000.00 | $27,615.00 | $25,000.00 | $50,000.00 | |
| 43 | 67201100 | SEAL ABAN MONIT WELLS | 4 | EACH | $4,000.00 | $875.00 | $1,025.00 | $1,000.00 | $600.00 | $2,000.00 | $5,000.00 | |
| 44 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $5,500.00 | $1.00 | $1.00 | $19,000.00 | $4,500.00 | $5,000.00 | |
| 45 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $5,000.00 | $2,600.00 | $5,250.00 | $5,000.00 | $300.00 | $3,500.00 | $5,000.00 | |
| 46 | 84200600 | REM LT U NO SALV | 5 | EACH | $500.00 | $250.00 | $103.35 | $200.00 | $1,000.00 | $700.00 | $650.00 | |
| 47 | 84200804 | REM POLE FDN | 5 | EACH | $400.00 | $250.00 | $208.00 | $200.00 | $600.00 | $1,500.00 | $750.00 |