Bid code X5510100

STORM SEWER REMOVAL · per FOOT

‹ All bid codes

$32.32Avg low bid / FOOT
$38.66Avg of all bids
—Avg engineer's estimate
12Jobs · 2,625 FOOT

Average low bid by year

YearJobsQuantityAvg lowAvg all
202671,689$39.21$44.72
20255936$19.90$28.42

Recent low bids

ExcelCSV
Let dateContractCounty / DistrictQuantityUnit priceLow bidder
Sep 18, 202697892 St. ClairDistrict 8478 FOOT $60.00Plocher Construction Company, Inc.
Apr 24, 202646948 MaconDistrict 7127 FOOT $38.50Illinois Valley Paving, a div of UCM, Inc.
Apr 24, 202666M55 LasalleDistrict 3168 FOOT $25.00D. Construction, Inc.
Apr 24, 202697865 St. ClairDistrict 8210 FOOT $28.00Baxmeyer Construction, Inc.
Feb 27, 202697872 St. ClairDistrict 8627 FOOT $31.00DMS Contracting, Inc.
Jan 16, 202664L27 StephensonDistrict 232 FOOT $20.00Martin & Company Excavating
Jan 16, 202693839 SangamonDistrict 647 FOOT $53.00Kinney Contractors, Inc.
Jun 13, 202564M76 LeeDistrict 2150 FOOT $9.00Martin & Company Excavating
Jun 13, 202599750 SalineDistrict 9387 FOOT $12.83E. T. Simonds Construction Company
Apr 25, 202589868 MercerDistrict 473 FOOT $24.00Phoenix Corporation of the Quad Cities
Mar 7, 202564R02 LeeDistrict 2165 FOOT $16.00Martin & Company Excavating
Mar 7, 202597793 MadisonDistrict 8161 FOOT $49.17Keller Construction, Inc.