HOT MIX
- Let date
- Thursday, August 1, 2024
- CCSJ
- 6467-50-001
- District
- Waco
- County
- Hill
- Highway
- SH 81
- Limits
- VARIOUS ROADWAYS to IN HILL & BOSQUE
- Classification
- Maintenance
- Project number
- MMC - 646750001
- Working days
- 183
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,696,600 | ||
| 1 | BIG CREEK CONSTRUCTION, LTD. Low bidder | $1,778,575 | +4.8% | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,802,829 | +6.3% | +1.4% |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,933,350 | +14.0% | +8.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BIG CREEK CONST… | #2 TEXAS MATERIALS… | #3 KNIFE RIVER COR… |
|---|---|---|---|---|---|---|---|---|
| 1 | 8011-6001 | D-GR HMA(SQ) TY D PG 64-22 (PICKUP) | 3,500 | TON | $70.00 | $71.00 | $75.90 | $83.00 |
| 2 | 8011-6002 | D-GR HMA(SQ) TY D PG 64-22 (DELIVERY) | 6,500 | TON | $89.00 | $94.25 | $94.48 | $99.50 |
| 3 | 8011-6014 | D-GR HMA(SQ)TY B PG 64-22 (PICKUP) | 1,500 | TON | $65.00 | $63.00 | $70.14 | $75.00 |
| 4 | 8011-6015 | D-GR HMA(SQ)TY B PG 64-22(DELIVERY) | 300 | TON | $82.00 | $85.50 | $89.68 | $90.00 |
| 5 | 8011-6016 | D-GR HMA(SQ)TY C PG 64-22 (PICKUP) | 1,300 | TON | $70.00 | $71.00 | $74.65 | $82.00 |
| 6 | 8011-6017 | D-GR HMA(SQ)TY C PG 64-22 (DELIVERY) | 7,500 | TON | $88.00 | $94.00 | $92.52 | $100.00 |