| 1 | 134-6008 |
BACKFILL (TY A OR B) | 100 | CY |
$20.00 |
$12.45 |
$50.00 |
$35.00 |
| 2 | 340-6104 |
D-GR HMA(SQ) TY-D SAC-B PG64-22 | 400 | TON |
$110.00 |
$106.00 |
$99.00 |
$150.00 |
| 3 | 342-6002 |
PFC (ASPHALT) PG76-22 | 30 | TON |
$120.00 |
$136.00 |
$140.00 |
$167.00 |
| 4 | 342-6006 |
PFC-C (AGGREGATE)(PG76 MIX) SAC-A | 435 | TON |
$150.00 |
$136.00 |
$140.00 |
$167.00 |
| 5 | 351-6004 |
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 3,000 | SY |
$45.00 |
$40.35 |
$46.00 |
$56.75 |
| 6 | 351-6013 |
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 13,880 | SY |
$25.00 |
$19.80 |
$24.00 |
$26.70 |
| 7 | 354-6045 |
PLANE ASPH CONC PAV (2") | 8,600 | SY |
$2.00 |
$1.70 |
$3.50 |
$5.60 |
| 8 | 500-6033 |
MOBILIZATION (CALLOUT) | 3 | EA |
$17,062.67 |
$250.00 |
$500.00 |
$325.00 |
| 9 | 662-6109 |
WK ZN PAV MRK SHT TERM (TAB)TY W | 100 | EA |
$1.00 |
$0.9000 |
$1.50 |
$1.00 |
| 10 | 662-6111 |
WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 100 | EA |
$1.00 |
$0.9000 |
$1.50 |
$1.00 |
| 11 | 666-6048 |
REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 100 | LF |
$6.00 |
$24.67 |
$10.00 |
$20.15 |
| 12 | 666-6300 |
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) | 1,000 | LF |
$1.00 |
$1.37 |
$2.00 |
$1.15 |
| 13 | 666-6303 |
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | 1,000 | LF |
$1.00 |
$1.23 |
$2.00 |
$1.00 |
| 14 | 666-6312 |
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) | 1,000 | LF |
$1.00 |
$1.37 |
$2.00 |
$1.15 |
| 15 | 666-6315 |
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | 1,000 | LF |
$1.00 |
$1.30 |
$2.00 |
$1.05 |
| 16 | 672-6007 |
REFL PAV MRKR TY I-C | 200 | EA |
$10.00 |
$4.11 |
$5.00 |
$3.35 |
| 17 | 672-6009 |
REFL PAV MRKR TY II-A-A | 10 | EA |
$10.00 |
$17.82 |
$5.00 |
$14.50 |
| 18 | 6001-6001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 100 | DAY |
$80.00 |
$1.00 |
$25.00 |
$1.00 |
| 19 | 6185-6002 |
TMA (STATIONARY) | 40 | DAY |
$160.00 |
$1.00 |
$35.00 |
$1.00 |
| 20 | 6185-6003 |
TMA (MOBILE OPERATION) | 100 | HR |
$45.00 |
$75.00 |
$25.00 |
$61.45 |