32BidsNov 4, 2016 to Jul 9, 2020
6Wins (low bidder)
18.8%Win rate
$2,643,904Total won
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Jul 9, 2020 | 0913-29-048 | REPLACE BRIDGE AND APPROACHESLavaca · Yoakum | 2 of 7 | $481,170 | $469,444HILL COUNTRY BRIDGE, INC. | +2.5% |
| Jun 5, 2020 | 0923-06-058 | REPLACE BRIDGE AND APPROACHESBrown · Brownwood | 2 of 7 | $593,818 | $570,000PIERCE R & B LLC | +4.2% |
| May 7, 2020 | 0915-13-030 | CONSTRUCT CURB RAMPS, SIDEWALK, PED INFRASTRUCTUREAtascosa · San Antonio | 2 of 11 | $590,623 | $584,272DELGADO'S CONTRACTORS, LLC | +1.1% |
| Mar 17, 2020 | 6357-93-001 | REPLACE CULVERTMedina · San Antonio | 5 of 7 | $227,161 | $169,840TIERRA LEASE SERVICE, LLC | +33.7% |
| Mar 5, 2020 | 1206-01-019 | REPLACE BRIDGES AND APPROACHESLive Oak · Corpus Christi | 7 of 8 | $1,751,754 | $1,425,038LISKA CONSTRUCTION COMPANY,… | +22.9% |
| Dec 17, 2019 | 6351-40-001 | DITCH CLEANING & IMPROVEMENTSAransas · Corpus Christi | 4 of 4 | $171,345 | $125,270BECK-REIT & SONS, LTD. | +36.8% |
| Dec 4, 2019 | 0913-29-036 | REHABILITATE EXISTING BRIDGELavaca · Yoakum | 2 of 4 | $804,920 | $699,018GIBSON & ASSOCIATES, INC. | +15.1% |
| Oct 2, 2019 | 6339-32-001 | REMOVE AND REPLACE CULVERTAtascosa · San Antonio | 1 of 11 | $481,612 | $481,612 | Won |
| May 8, 2019 | 0913-22-046 | REPLACE BRIDGE AND APPROACHESGonzales · Yoakum | 1 of 9 | $399,752 | $399,752 | Won |
| May 7, 2019 | 0915-13-029 | REPLACE BRIDGE AND APPROACHESAtascosa · San Antonio | 2 of 8 | $636,892 | $619,854SB CONTRACTORS LLC | +2.7% |
| Jan 9, 2019 | 0089-07-156 | SLOPE REPAIRWharton · Yoakum | 5 of 8 | $378,078 | $286,694TREVWAY, INC. | +31.9% |
| Jan 8, 2019 | 0915-45-053 | REPLACE BRIDGE & APPROACHESMedina · San Antonio | 3 of 9 | $526,754 | $487,791RELMCO, INC. | +8.0% |
| Apr 3, 2018 | 0913-22-047 | REHABILITATE EXISTING BRIDGEGonzales · Yoakum | 1 of 6 | $773,076 | $773,076 | Won |
| Mar 14, 2018 | 6320-97-001 | REPAIR RIPRAP SLOPE AT OVERPASSAtascosa · San Antonio | 2 of 9 | $244,943 | $235,947TREVWAY, INC. | +3.8% |
| Mar 7, 2018 | 6327-01-001 | BRIDGE PREVENTATIVE MAINTENANCEBexar · San Antonio | 13 of 14 | $850,927 | $427,360RELMCO, INC. | +99.1% |
| Feb 1, 2018 | 2166-02-007 | REPLACE BRIDGE AND APPROACHESDe Witt · Yoakum | 7 of 10 | $402,135 | $338,050DALRYMPLE GRAVEL AND CONTRA… | +19.0% |
| Feb 1, 2018 | 0913-29-035 | REPLACE BRIDGE AND APPROACHESLavaca · Yoakum | 4 of 7 | $601,688 | $573,002DALRYMPLE GRAVEL AND CONTRA… | +5.0% |
| Jan 31, 2018 | 6322-18-001 | DRAINAGE IMPROVEMENTSComal · San Antonio | 5 of 10 | $192,337 | $165,000DAN WILLIAMS COMPANY | +16.6% |
| Dec 5, 2017 | 0913-09-062 | REPLACE BRIDGE AND APPROACHESWharton · Yoakum | 3 of 9 | $383,304 | $324,876CONSTAR CONSTRUCTION | +18.0% |
| Oct 4, 2017 | 0915-11-028 | REPLACE BRIDGE AND APPROACHESKendall · San Antonio | 7 of 11 | $579,689 | $514,523Curran Contracting Company | +12.7% |
| Aug 8, 2017 | 0913-09-065 | REPLACE BRIDGE AND APPROACHESWharton · Yoakum | 10 of 10 | $469,830 | $320,8043LW CIVIL LLC | +46.5% |
| Jul 12, 2017 | 0915-45-052 | REPLACE BRIDGE & APPROACHESMedina · San Antonio | 9 of 10 | $610,003 | $422,407RELMCO, INC. | +44.4% |
| Jul 11, 2017 | 1118-01-019 | REPLACE BRIDGE AND APPROACHESBee · Corpus Christi | 4 of 9 | $589,549 | $444,5763LW CIVIL LLC | +32.6% |
| Jun 6, 2017 | 0916-37-030 | REPLACE BRIDGE AND APPROACHESJim Wells · Corpus Christi | 4 of 7 | $395,529 | $348,041CRG | +13.6% |
| May 24, 2017 | 6313-44-001 | INSTALL CONCRETE RIPRAP AND GABIONSBexar · San Antonio | 1 of 7 | $260,354 | $260,354 | Won |
| Apr 12, 2017 | 6312-85-001 | CULVERT REPAIR AT VARIOUS LOCATIONSMedina · San Antonio | 1 of 9 | $279,243 | $279,243 | Won |
| Apr 5, 2017 | 0913-26-058 | REPLACE BRIDGE AND APPROACHESColorado · Yoakum | 3 of 7 | $299,247 | $233,008TREVWAY, INC. | +28.4% |
| Apr 4, 2017 | 0913-18-029 | REPLACE BRIDGE AND APPROACHESJackson · Yoakum | 4 of 8 | $529,650 | $462,864CONSTAR CONSTRUCTION | +14.4% |
| Mar 7, 2017 | 0916-29-006 | REPLACE BRIDGE AND APPROACHESLive Oak · Corpus Christi | 3 of 12 | $727,474 | $649,191LISKA CONSTRUCTION COMPANY,… | +12.1% |
| Jan 4, 2017 | 0913-17-040 | REPLACE BRIDGE AND APPROACHESDe Witt · Yoakum | 1 of 11 | $449,867 | $449,867 | Won |
| Dec 1, 2016 | 0026-03-042 | WIDEN BRIDGE AND APPROACHESFayette · Yoakum | 8 of 8 | $1,667,674 | $831,842HUNTER INDUSTRIES, LTD. | +100.5% |
| Nov 4, 2016 | 0839-01-015 | REPLACE BRIDGE AND APPROACHESGonzales · Yoakum | 9 of 11 | $1,632,477 | $1,222,091HILL COUNTRY BRIDGE, INC. | +33.6% |
Subcontracts on active jobs 0
No subcontracts on TxDOT's active contract list.