‹ Jan 2017 results
REPLACE BRIDGE AND APPROACHES
- Let date
- Wednesday, January 4, 2017
- CCSJ
- 0913-17-040
- District
- Yoakum
- County
- De Witt
- Highway
- CR
- Limits
- AT CABEZA CREEK CR 271 to (BACHLE RD) STR AA02-71-003
- Classification
- Construction
- Project number
- BR 1502(215)
- Working days
- 60
Bidders 11
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $545,017 | | |
| 1 |
TMES LLC Low bidder |
$449,867 |
-17.5% |
|
| 2 |
LISKA CONSTRUCTION COMPANY, INC. |
$452,833 |
-16.9% |
+0.7% |
| 3 |
HILL COUNTRY BRIDGE, INC. |
$465,601 |
-14.6% |
+3.5% |
| 4 |
CONSTAR CONSTRUCTION |
$495,137 |
-9.2% |
+10.1% |
| 5 |
SB CONTRACTORS LLC |
$508,726 |
-6.7% |
+13.1% |
| 6 |
DEAN WORD COMPANY, LTD. |
$510,362 |
-6.4% |
+13.4% |
| 7 |
3LW MANAGEMENT, LLC |
$537,524 |
-1.4% |
+19.5% |
| 8 |
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C. |
$550,521 |
+1.0% |
+22.4% |
| 9 |
TREVWAY, INC. |
$581,912 |
+6.8% |
+29.4% |
| 10 |
ANGEL BROTHERS HOLDINGS CORP. |
$589,024 |
+8.1% |
+30.9% |
| 11 |
RELMCO, INC. |
$654,511 |
+20.1% |
+45.5% |
Bid tab: unit prices 31 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 TMES LLC | #2 LISKA CONSTRUCT… | #3 HILL COUNTRY BR… | #4 CONSTAR CONSTRU… | #5 SB CONTRACTORS … | #6 DEAN WORD COMPA… | #7 3LW MANAGEMENT,… | #8 A GREATER AUSTI… |
| 1 | 100-6002 |
PREPARING ROW | 3.7 | STA |
$3,500.00 |
$3,500.00 |
$2,433.58 |
$3,270.00 |
$2,000.00 |
$5,000.00 |
$4,010.60 |
$2,000.00 |
$2,980.00 |
| 2 | 110-6001 |
EXCAVATION (ROADWAY) | 158.8 | CY |
$25.00 |
$30.00 |
$21.44 |
$25.00 |
$17.00 |
$25.00 |
$24.20 |
$30.00 |
$48.90 |
| 3 | 110-6002 |
EXCAVATION (CHANNEL) | 100 | CY |
$10.00 |
$20.00 |
$34.85 |
$27.50 |
$27.00 |
$25.00 |
$24.20 |
$35.00 |
$69.80 |
| 4 | 132-6005 |
EMBANKMENT (FINAL)(ORD COMP)(TY C) | 8.9 | CY |
$35.00 |
$100.00 |
$383.15 |
$205.00 |
$30.00 |
$85.00 |
$38.50 |
$45.00 |
$95.00 |
| 5 | 150-6002 |
BLADING | 10 | HR |
$100.00 |
$75.00 |
$80.00 |
$109.00 |
$100.00 |
$85.00 |
$119.79 |
$150.00 |
$80.00 |
| 6 | 164-6023 |
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) | 1,330 | SY |
$2.00 |
$1.15 |
$1.59 |
$1.80 |
$2.00 |
$1.05 |
$0.5820 |
$1.45 |
$1.20 |
| 7 | 164-6029 |
CELL FBR MLCH SEED(TEMP)(WARM) | 332 | SY |
$3.00 |
$0.1730 |
$2.00 |
$1.80 |
$1.00 |
$3.40 |
$2.08 |
$5.60 |
$3.82 |
| 8 | 164-6031 |
CELL FBR MLCH SEED(TEMP)(COOL) | 332 | SY |
$3.00 |
$0.1730 |
$2.00 |
$1.80 |
$1.00 |
$3.40 |
$2.08 |
$5.60 |
$3.81 |
| 9 | 168-6001 |
VEGETATIVE WATERING | 11.2 | MG |
$125.00 |
$90.00 |
$54.11 |
$48.50 |
$120.00 |
$41.00 |
$73.70 |
$85.00 |
$560.00 |
| 10 | 247-6366 |
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 160.8 | CY |
$120.00 |
$81.84 |
$77.80 |
$84.00 |
$120.00 |
$115.00 |
$119.73 |
$95.00 |
$98.40 |
| 11 | 407-6001 |
SHEET PILING (PZ - 27) | 4,291 | SF |
$42.00 |
$34.23 |
$31.45 |
$31.55 |
$42.00 |
$34.00 |
$37.18 |
$35.00 |
$31.00 |
| 12 | 409-6002 |
PRESTR CONC PIL (18 IN SQ) | 548 | LF |
$125.00 |
$86.82 |
$90.04 |
$89.30 |
$110.00 |
$92.00 |
$97.03 |
$110.00 |
$87.70 |
| 13 | 420-6013 |
CL C CONC (ABUT) | 19.6 | CY |
$1,000.00 |
$825.00 |
$1,090.98 |
$838.00 |
$900.00 |
$1,200.00 |
$1,163.80 |
$1,500.00 |
$1,300.00 |
| 14 | 420-6025 |
CL C CONC (BENT) | 6.6 | CY |
$1,500.00 |
$1,300.00 |
$1,151.39 |
$1,280.00 |
$1,500.00 |
$1,500.00 |
$1,332.10 |
$1,100.00 |
$1,700.00 |
| 15 | 422-6007 |
REINF CONC SLAB (SLAB BEAM) | 1,690 | SF |
$20.00 |
$19.37 |
$22.81 |
$21.20 |
$15.00 |
$18.00 |
$38.52 |
$35.00 |
$25.00 |
| 16 | 425-6010 |
PRESTR CONC SLAB BEAM (5SB12) | 320 | LF |
$175.00 |
$141.21 |
$156.98 |
$176.25 |
$160.00 |
$155.00 |
$140.80 |
$185.00 |
$180.00 |
| 17 | 432-6002 |
RIPRAP (CONC)(5 IN) | 5 | CY |
$350.00 |
$550.00 |
$564.63 |
$945.00 |
$540.00 |
$550.00 |
$572.00 |
$500.00 |
$700.00 |
| 18 | 450-6006 |
RAIL (TY T223) | 154 | LF |
$150.00 |
$105.40 |
$129.61 |
$126.30 |
$140.00 |
$135.00 |
$96.80 |
$170.00 |
$190.00 |
| 19 | 496-6009 |
REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 | EA |
$15,000.00 |
$14,395.00 |
$9,172.47 |
$18,200.00 |
$15,000.00 |
$19,860.00 |
$5,648.50 |
$10,000.00 |
$45,000.00 |
| 20 | 500-6001 |
MOBILIZATION | 1 | LS |
$51,000.00 |
$45,246.00 |
$47,100.00 |
$37,000.00 |
$35,000.00 |
$50,734.46 |
$51,030.66 |
$50,000.00 |
$55,800.00 |
| 21 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO |
$3,000.00 |
$1,077.19 |
$1,529.63 |
$2,530.00 |
$1,000.00 |
$4,500.00 |
$1,429.96 |
$4,000.00 |
$3,500.00 |
| 22 | 506-6001 |
ROCK FILTER DAMS (INSTALL) (TY 1) | 100 | LF |
$50.00 |
$34.50 |
$36.08 |
$45.40 |
$33.00 |
$45.00 |
$31.20 |
$35.00 |
$31.50 |
| 23 | 506-6011 |
ROCK FILTER DAMS (REMOVE) | 100 | LF |
$10.00 |
$9.20 |
$6.75 |
$41.20 |
$15.00 |
$12.00 |
$7.28 |
$10.00 |
$13.50 |
| 24 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 300 | LF |
$3.00 |
$3.45 |
$2.00 |
$6.80 |
$6.00 |
$6.00 |
$2.60 |
$4.50 |
$6.30 |
| 25 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 300 | LF |
$2.00 |
$0.5750 |
$1.80 |
$4.00 |
$2.00 |
$1.00 |
$1.56 |
$1.50 |
$1.10 |
| 26 | 540-6006 |
MTL BEAM GD FEN TRANS (THRIE-BEAM) | 4 | EA |
$1,500.00 |
$2,041.25 |
$1,791.71 |
$1,965.00 |
$2,400.00 |
$1,875.00 |
$2,082.96 |
$1,680.00 |
$2,000.00 |
| 27 | 544-6001 |
GUARDRAIL END TREATMENT (INSTALL) | 4 | EA |
$2,500.00 |
$2,702.50 |
$2,867.56 |
$1,995.00 |
$3,100.00 |
$2,575.00 |
$2,351.44 |
$2,250.00 |
$2,600.00 |
| 28 | 552-6001 |
WIRE FENCE (TY A) | 301 | LF |
$15.00 |
$15.00 |
$12.08 |
$20.10 |
$10.00 |
$30.00 |
$17.57 |
$12.00 |
$13.50 |
| 29 | 552-6008 |
WIRE FENCE (WATER GAP) | 64 | LF |
$20.00 |
$50.00 |
$16.23 |
$20.70 |
$21.00 |
$45.00 |
$40.27 |
$32.00 |
$33.50 |
| 30 | 658-6014 |
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | 6 | EA |
$25.00 |
$29.90 |
$20.20 |
$16.00 |
$70.00 |
$15.00 |
$16.38 |
$25.00 |
$29.00 |
| 31 | 658-6062 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 4 | EA |
$30.00 |
$48.30 |
$20.20 |
$26.00 |
$70.00 |
$15.00 |
$16.38 |
$25.00 |
$47.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 11.