Bid tab 0913-09-065

Let Aug 8, 2017 · Yoakum · Wharton Sign up free

‹ Aug 2017 results

REPLACE BRIDGE AND APPROACHES

Let date
Tuesday, August 8, 2017
CCSJ
0913-09-065
District
Yoakum
County
Wharton
Highway
CR
Limits
AT EAST FORK JONES CREEK CR 461 to (CR 461)
Classification
Construction
Project number
BR 2014(682)
Working days
60

Bidders 10

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$316,096
1 3LW CIVIL LLC Low bidder $320,804 +1.5%
2 HILL COUNTRY BRIDGE, INC. $335,237 +6.1% +4.5%
3 REXCO CONSTRUCTION SERVICES, INC. $337,875 +6.9% +5.3%
4 CONSTAR CONSTRUCTION $343,294 +8.6% +7.0%
5 TREVWAY, INC. $353,042 +11.7% +10.0%
6 JOHN REED AND COMPANY, LLC $374,477 +18.5% +16.7%
7 SB CONTRACTORS LLC $388,126 +22.8% +21.0%
8 ISI CONTRACTING, INC. $409,679 +29.6% +27.7%
9 A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C. $452,961 +43.3% +41.2%
10 TMES LLC $469,830 +48.6% +46.5%

Bid tab: unit prices 36 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 3LW CIVIL LLC#2 HILL COUNTRY BR…#3 REXCO CONSTRUCT…#4 CONSTAR CONSTRU…#5 TREVWAY, INC.#6 JOHN REED AND C…#7 SB CONTRACTORS …#8 ISI CONTRACTING…
1100-6002 PREPARING ROW3.4STA $3,000.00 $1,500.00 $2,755.00 $2,900.00 $800.00 $1,400.00 $6,000.00 $5,000.00 $3,800.00
2110-6001 EXCAVATION (ROADWAY)30CY $20.00 $100.00 $25.00 $100.00 $27.00 $50.00 $80.00 $20.00 $50.00
3132-6005 EMBANKMENT (FINAL)(ORD COMP)(TY C)325CY $25.00 $50.00 $27.60 $36.70 $30.00 $25.00 $60.00 $35.00 $36.00
4150-6002 BLADING10HR $100.00 $200.00 $115.00 $90.00 $100.00 $50.00 $20.00 $85.00 $100.00
5164-6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)670SY $2.00 $1.80 $3.75 $1.58 $2.00 $1.00 $0.1000 $2.00 $1.10
6164-6029 CELL FBR MLCH SEED(TEMP)(WARM)168SY $3.00 $1.80 $4.60 $1.58 $2.00 $2.00 $0.1000 $5.00 $1.10
7164-6031 CELL FBR MLCH SEED(TEMP)(COOL)168SY $3.00 $1.80 $4.60 $1.58 $2.00 $2.00 $0.1000 $5.00 $1.10
8168-6001 VEGETATIVE WATERING3MG $100.00 $85.00 $250.00 $250.00 $180.00 $100.00 $20.00 $65.00 $25.00
9247-6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)180CY $100.00 $120.00 $128.35 $138.36 $130.00 $129.00 $120.00 $115.00 $115.00
10416-6002 DRILL SHAFT (24 IN)270LF $200.00 $125.00 $206.00 $183.00 $250.00 $275.00 $230.00 $250.00 $325.00
11420-6013 CL C CONC (ABUT)24CY $900.00 $800.00 $785.00 $877.93 $1,000.00 $585.00 $1,250.00 $1,100.00 $1,100.00
12422-6001 REINF CONC SLAB1,607SF $15.00 $22.00 $19.75 $21.98 $16.00 $25.00 $14.00 $17.00 $24.00
13425-6011 PRESTR CONC SLAB BEAM (4SB15)396LF $140.00 $146.00 $132.60 $129.90 $164.00 $160.00 $186.00 $140.00 $138.00
14432-6033 RIPRAP (STONE PROTECTION)(18 IN)156CY $150.00 $170.00 $151.45 $138.15 $170.00 $150.00 $120.00 $210.00 $130.00
15450-6006 RAIL (TY T223)124LF $100.00 $110.00 $98.50 $163.16 $140.00 $113.00 $60.00 $115.00 $89.00
16454-6004 ARMOR JOINT (SEALED)56LF $75.00 $65.00 $62.80 $76.61 $56.00 $70.00 $60.00 $75.00 $69.00
17464-6002 RC PIPE (CL III)(15 IN)46LF $50.00 $51.00 $43.25 $52.16 $35.00 $50.22 $50.00 $85.00 $52.00
18464-6003 RC PIPE (CL III)(18 IN)42LF $60.00 $55.00 $46.35 $57.20 $40.00 $57.41 $55.00 $85.00 $59.00
19467-6337 SET (TY II) (15 IN) (RCP) (3: 1) (P)1EA $400.00 $400.00 $864.00 $1,002.30 $1,000.00 $1,834.35 $500.00 $1,500.00 $1,000.00
20467-6341 SET (TY II) (15 IN) (RCP) (6: 1) (P)1EA $600.00 $600.00 $1,465.00 $1,452.75 $1,200.00 $1,609.46 $600.00 $1,500.00 $1,000.00
21467-6357 SET (TY II) (18 IN) (RCP) (3: 1) (P)1EA $800.00 $800.00 $1,010.00 $1,195.50 $1,300.00 $1,828.00 $700.00 $1,500.00 $1,000.00
22467-6363 SET (TY II) (18 IN) (RCP) (6: 1) (P)1EA $1,000.00 $1,100.00 $1,580.00 $1,231.20 $1,400.00 $1,713.00 $800.00 $1,500.00 $1,100.00
23496-6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH)1EA $15,000.00 $15,000.00 $20,500.00 $6,800.00 $10,000.00 $20,000.00 $28,000.00 $11,012.01 $32,000.00
24496-6050 REMOV STR (DRIVEWAY CULVERT)2EA $500.00 $250.00 $530.00 $750.00 $1,000.00 $500.00 $500.00 $750.00 $1,400.00
25500-6001 MOBILIZATION1LS $28,000.00 $30,000.00 $33,400.00 $36,000.00 $20,000.00 $35,000.00 $35,000.00 $38,500.00 $39,000.00
26502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING4MO $2,500.00 $2,000.00 $2,080.00 $1,286.25 $1,000.00 $600.00 $1,000.00 $5,000.00 $1,100.00
27506-6038 TEMP SEDMT CONT FENCE (INSTALL)695LF $3.50 $4.00 $2.00 $4.73 $5.00 $2.00 $3.00 $4.00 $4.50
28506-6039 TEMP SEDMT CONT FENCE (REMOVE)695LF $1.50 $1.50 $1.00 $1.05 $3.00 $1.00 $1.00 $1.00 $2.75
29530-6016 DRIVEWAYS (BASE)120SY $25.00 $25.00 $36.45 $29.00 $50.00 $26.00 $22.00 $40.00 $105.00
30540-6007 MTL BEAM GD FEN TRANS (TL2)4EA $1,000.00 $1,000.00 $745.00 $1,286.25 $1,500.00 $315.00 $900.00 $890.00 $1,000.00
31540-6014 SHORT RADIUS25LF $30.00 $30.00 $25.60 $42.00 $40.00 $32.00 $36.00 $69.45 $50.00
32540-6015 DRIVEWAY TERMINAL ANCHOR SECTION1EA $650.00 $750.00 $500.00 $997.50 $700.00 $1,262.00 $850.00 $625.00 $750.00
33544-6001 GUARDRAIL END TREATMENT (INSTALL)3EA $2,200.00 $2,400.00 $2,025.00 $2,467.50 $3,300.00 $420.00 $2,100.00 $2,530.00 $2,400.00
34658-6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)6EA $20.00 $20.00 $15.00 $28.88 $50.00 $20.00 $10.00 $15.00 $6.00
35658-6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)3EA $21.00 $20.00 $15.00 $28.88 $50.00 $25.00 $10.00 $15.00 $15.00
36658-6048 INSTL OM ASSM (OM-2Z)(FLX)GND2EA $50.00 $55.00 $50.00 $73.50 $45.00 $25.00 $36.00 $47.00 $21.00

Showing the first 8 bidders. The Excel and CSV downloads include all 10.