120BidsSep 10, 2013 to Sep 3, 2026
47Wins (low bidder)
39.2%Win rate
$236,757,428Total won
Competitor scorecard
Last 5 years in Texas39.3%Win rate24 of 61 bids
+4.8%Average bid vs estimate
-1.6%Winning bids vs estimate
+14.9%Over the low bid when they loseAverage field: 4.6 bidders
| Head to head | Times met | Beat them | Lost to them | Record |
|---|---|---|---|---|
| CK NEWBERRY, LLC | 20 | 14 | 6 | 70% |
| A. L. HELMCAMP, INC. | 16 | 11 | 5 | 69% |
| RK HALL, LLC | 13 | 11 | 2 | 85% |
| FOUTSCO PAVING COMPANY, LLC | 12 | 6 | 6 | 50% |
| DUININCK, INC. | 12 | 8 | 4 | 67% |
| GILVIN-TERRILL, LTD. | 12 | 11 | 1 | 92% |
| BONTKE BROTHERS CONSTRUCTION COMPANY | 12 | 11 | 1 | 92% |
| REECE ALBERT, INC. | 10 | 7 | 3 | 70% |
| ZACK BURKETT CO. | 10 | 4 | 6 | 40% |
| TOUCHSTONE RESOURCES, LLC | 9 | 4 | 5 | 44% |
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Sep 3, 2026 | 0902-39-050 | PW within Possum Kingdom State ParkPalo Pinto · Fort Worth | 3 of 7 | $521,425 | $411,979JAY MILLS CONTRACTING, INCO… | +26.6% |
| Aug 13, 2026 | 6506-65-001 | ABL East HMANolan · Abilene | 1 of 1 | $991,674 | $991,674 | Won |
| Aug 5, 2026 | 6505-22-001 | OVERLAY EASTLAND COUNTYEastland · Brownwood | 3 of 9 | $3,117,542 | $2,982,235BLACKSMITH VENTURES LLC | +4.5% |
| Jun 4, 2026 | 6500-46-001 | ABL-East D-GR HMAShackelford · Abilene | 2 of 2 | $471,660 | $398,680ZACK BURKETT CO. | +18.3% |
| Apr 8, 2026 | 0908-23-058 | REPLACE BRIDGE CR 305 @ ALKALI CRK TRIBFisher · Abilene | 5 of 7 | $2,228,175 | $1,880,830TUCAN CONTRACTING, LLC | +18.5% |
| Apr 7, 2026 | 0181-03-029 | SH 36 SUPER 2 CR 479 TO CR 459Callahan · Abilene | 5 of 7 | $12,575,871 | $11,487,762BIG CREEK CONSTRUCTION, LTD. | +9.5% |
| Mar 4, 2026 | 0699-01-065 | FM 89 HSIP WIDENING TAYLOR COUNTYTaylor · Abilene | 1 of 5 | $6,284,525 | $6,284,525 | Won |
| Feb 12, 2026 | 6494-64-001 | Abilene District Flex baseHoward · Abilene | 4 of 4 | $174,833 | $146,692SOUTHERN SOURCING SOLUTIONS… | +19.2% |
| Feb 5, 2026 | 2398-01-064 | SL 322 OVERLAY IH 20 TO US 83Taylor · Abilene | 1 of 6 | $8,968,076 | $8,968,076 | Won |
| Jan 7, 2026 | 0975-02-023 | FM 1082 FY 24 HSIP JONES COJones · Abilene | 1 of 5 | $2,611,155 | $2,611,155 | Won |
| Jan 6, 2026 | 0985-02-011 | WIDEN FM 600 FROM US 380 TO FM 618Haskell · Abilene | 2 of 4 | $5,475,914 | $5,128,777ZACK BURKETT CO. | +6.8% |
| Dec 3, 2025 | 0974-03-014 | FM 604 AT JIM NED CREEKTaylor · Abilene | 1 of 9 | $2,697,516 | $2,697,516 | Won |
| Nov 19, 2025 | 6493-30-001 | AGGREGATE-TY B GR 4Runnels · San Angelo | 3 of 3 | $258,134 | $211,194MARTIN MARIETTA MATERIALS, … | +22.2% |
| Nov 6, 2025 | 0908-23-049 | CR 122 AT CLEARFORK BRAZOS RIVERFisher · Abilene | 4 of 8 | $1,984,297 | $1,728,544COPPELL CONSTRUCTION CO., I… | +14.8% |
| Oct 14, 2025 | 6490-55-001 | Call Out Mill and Inlay FY26Haskell · Abilene | 1 of 3 | $885,783 | $885,783 | Won |
| Oct 8, 2025 | 0317-02-017 | FM 57 OVERLAY US 180 TO JONES COUNTYFisher · Abilene | 2 of 7 | $2,982,134 | $2,898,665CK NEWBERRY, LLC | +2.9% |
| Oct 8, 2025 | 0034-01-130 | US 83/84 Y INTERCHANGETaylor · Abilene | 7 of 9 | $79,191,280 | $72,482,832JAMES CONSTRUCTION GROUP, L… | +9.3% |
| Aug 11, 2025 | 6488-87-001 | AGGR TY B Abilene DistrictCallahan · Abilene | 1 of 3 | $294,197 | $294,197 | Won |
| Jul 1, 2025 | 0181-01-067 | New sidewalk on SH 36Taylor · Abilene | 1 of 5 | $4,169,101 | $4,169,101 | Won |
| Jun 18, 2025 | 6485-70-001 | Flexible Base-NorthTom Green · San Angelo | 3 of 4 | $144,906 | $89,397SOUTHERN SOURCING SOLUTIONS… | +62.1% |
| May 15, 2025 | 6484-36-001 | RIPRAP (STONE PROTECTION) (MAT ONLY)Brown · Brownwood | 4 of 5 | $144,860 | $128,000TOUCHSTONE RESOURCES, LLC | +13.2% |
| May 2, 2025 | 0181-01-069 | SH 36 SUPER 2 CR 123 TO CALLAHAN COUNTYTaylor · Abilene | 6 of 8 | $11,227,634 | $10,612,471A. L. HELMCAMP, INC. | +5.8% |
| Apr 4, 2025 | 0006-03-149 | MILL AND FILL IH 20 FRS WEST OF SH 70Nolan · Abilene | 3 of 5 | $855,604 | $664,504CK NEWBERRY, LLC | +28.8% |
| Apr 3, 2025 | 0663-03-031 | FM 1235 TAYLOR CO CR 306 TO CR 300Taylor · Abilene | 1 of 6 | $3,167,591 | $3,167,591 | Won |
| Mar 5, 2025 | 1070-02-010 | FM 382 HSIP WIDENING TAYLOR COUNTYTaylor · Abilene | 1 of 6 | $1,784,682 | $1,784,682 | Won |
| Feb 21, 2025 | 6479-95-001 | Flex Base 1692 FDRTom Green · San Angelo | 4 of 5 | $1,163,497 | $849,232CSA MATERIALS, INC. | +37.0% |
| Jan 8, 2025 | 0907-13-017 | 0907-13-017 CR REPLACE BRIDGE AND APPROARunnels · San Angelo | 1 of 8 | $1,997,089 | $1,997,089 | Won |
| Dec 4, 2024 | 0011-04-029 | SH 351 SHACKELFORD - JONES TO E OF 604Shackelford · Abilene | 2 of 9 | $5,728,329 | $5,659,269FOUTSCO PAVING COMPANY, LLC | +1.2% |
| Nov 22, 2024 | 6476-68-001 | D-GR HMA Abilene District East RegionShackelford · Abilene | 3 of 3 | $388,750 | $320,925ZACK BURKETT CO. | +21.1% |
| Nov 6, 2024 | 2033-01-013 | WIDEN AND RESURFACE FM 608 NOLAN COUNTYNolan · Abilene | 3 of 5 | $9,236,504 | $7,895,450NOBLES ROAD CONSTRUCTION, I… | +17.0% |
| Aug 15, 2024 | 6471-43-001 | FLEXIBLE BASEHoward · Abilene | 2 of 2 | $135,288 | $123,295VULCAN CONSTRUCTION MATERIA… | +9.7% |
| May 28, 2024 | 6467-63-001 | AGGREGATERunnels · San Angelo | 2 of 3 | $215,000 | $202,248MARTIN MARIETTA MATERIALS, … | +6.3% |
| May 3, 2024 | 1360-01-031 | WIDEN ROAD - ADD SHOULDERSJones · Abilene | 1 of 4 | $9,538,048 | $9,538,048 | Won |
| May 3, 2024 | 0006-02-130 | REHABILITATE EXISTING ROADWAYNolan · Abilene | 2 of 2 | $6,422,740 | $6,255,552BONTKE BROTHERS CONSTRUCTIO… | +2.7% |
| May 2, 2024 | 0007-02-051 | PREVENTIVE MAINTENANCECallahan · Abilene | 1 of 1 | $10,411,767 | $10,411,767 | Won |
| May 2, 2024 | 0006-10-011 | REHABILITATE EXISTING ROADWAYTaylor · Abilene | 1 of 4 | $4,570,547 | $4,570,547 | Won |
| Apr 4, 2024 | 0157-04-056 | BRIDGE REPLACEMENTHaskell · Abilene | 3 of 6 | $5,372,956 | $4,673,134COPPELL CONSTRUCTION CO., I… | +15.0% |
| Mar 6, 2024 | 0972-03-023 | SURFACING/ROADWAY RESTORATIONJones · Abilene | 1 of 5 | $3,582,697 | $3,582,697 | Won |
| Mar 5, 2024 | 0317-01-043 | WIDEN ROAD - ADD SHOULDERSFisher · Abilene | 3 of 3 | $4,495,673 | $3,763,383GILVIN-TERRILL, LTD. | +19.5% |
| Jan 5, 2024 | 0296-01-039 | PREVENTIVE MAINTENANCEScurry · Abilene | 1 of 4 | $3,120,195 | $3,120,195 | Won |
| Dec 12, 2023 | 6460-72-001 | FLEXIBLE BASERunnels · San Angelo | 1 of 4 | $102,221 | $102,221 | Won |
| Dec 12, 2023 | 6460-73-001 | FLEXIBLE BASEConcho · San Angelo | 2 of 4 | $173,425 | $161,409CSA MATERIALS, INC. | +7.4% |
| Dec 5, 2023 | 0360-04-033 | PREVENTIVE MAINTENANCEHaskell · Abilene | 4 of 5 | $8,765,930 | $7,148,853A. L. HELMCAMP, INC. | +22.6% |
| Dec 5, 2023 | 6391-99-001 | MILL AND INLAYTaylor · Abilene | 2 of 3 | $1,826,475 | $1,663,364FOUTSCO PAVING COMPANY, LLC | +9.8% |
| Nov 1, 2023 | 0264-04-054 | ADD PASSING LANESCoke · San Angelo | 3 of 3 | $33,808,626 | $24,893,158REECE ALBERT, INC. | +35.8% |
| Oct 6, 2023 | 0983-03-030 | PREVENTIVE MAINTENANCENolan · Abilene | 3 of 5 | $3,658,542 | $3,360,261REECE ALBERT, INC. | +8.9% |
| Sep 6, 2023 | 2638-03-012 | PREVENTIVE MAINTENANCECallahan · Abilene | 1 of 4 | $1,595,478 | $1,595,478 | Won |
| May 4, 2023 | 2033-02-012 | REHAB AND BRIDGE REPLACEMENTNolan · Abilene | 1 of 1 | $12,460,122 | $12,460,122 | Won |
| May 4, 2023 | 0908-33-106 | BRIDGE REPLACEMENTTaylor · Abilene | 1 of 3 | $1,316,532 | $1,316,532 | Won |
| Nov 2, 2022 | 6423-64-001 | MILL AND INLAYScurry · Abilene | 2 of 3 | $1,328,430 | $1,251,245RK HALL, LLC | +6.2% |
| Oct 6, 2022 | 0157-09-004 | RESURFACE ROADWAYHaskell · Abilene | 3 of 7 | $5,991,089 | $5,949,106A. L. HELMCAMP, INC. | +0.7% |
| Sep 8, 2022 | 0033-04-072 | PREVENTIVE MAINTENANCEJones · Abilene | 2 of 4 | $5,533,925 | $5,224,760FOUTSCO PAVING COMPANY, LLC | +5.9% |
| Sep 8, 2022 | 0650-01-035 | WIDEN ROAD - ADD LANESNolan · Abilene | 2 of 3 | $15,226,206 | $14,078,927NOBLES ROAD CONSTRUCTION, I… | +8.1% |
| Sep 7, 2022 | 0007-03-108 | RESURFACE ROADWAYEastland · Brownwood | 1 of 1 | $3,280,637 | $3,280,637 | Won |
| Sep 7, 2022 | 6416-37-001 | MILL AND INLAYHaskell · Abilene | 2 of 4 | $1,249,964 | $1,170,303ZACK BURKETT CO. | +6.8% |
| Aug 30, 2022 | 6406-97-001 | HOT MIXNolan · Abilene | 2 of 2 | $378,600 | $307,984VULCAN CONSTRUCTION MATERIA… | +22.9% |
| Jan 7, 2022 | 0032-07-029 | WIDEN ROAD - ADD LANESStonewall · Abilene | 3 of 4 | $22,885,485 | $19,299,562DELHUR INDUSTRIES, INC. | +18.6% |
| Jan 7, 2022 | 0099-01-035 | HIGHWAY IMPROVEMENTColeman · Brownwood | 1 of 3 | $3,177,409 | $3,177,409 | Won |
| Jan 6, 2022 | 0033-01-038 | WIDEN ROAD - ADD LANESStonewall · Abilene | 1 of 6 | $14,492,854 | $14,492,854 | Won |
| Jan 6, 2022 | 0157-04-057 | PREVENTIVE MAINTENANCEHaskell · Abilene | 3 of 5 | $5,830,244 | $5,473,497ZACK BURKETT CO. | +6.5% |
| Dec 1, 2021 | 0264-01-045 | REHABILITATE EXISTING ROADWAYNolan · Abilene | 1 of 6 | $4,823,268 | $4,823,268 | Won |
| Nov 3, 2021 | 6390-50-001 | HOT MIX (MATERIAL ONLY)Nolan · Abilene | 1 of 2 | $2,635,030 | $2,635,030 | Won |
| Nov 3, 2021 | 6390-80-001 | HOT MIX (MATERIAL ONLY)Shackelford · Abilene | 1 of 2 | $2,161,690 | $2,161,690 | Won |
| Oct 7, 2021 | 6389-58-001 | MILL AND INLAYCallahan · Abilene | 2 of 4 | $888,525 | $841,350FOUTSCO PAVING COMPANY, LLC | +5.6% |
| Sep 1, 2021 | 0488-01-017 | REHAB ROADWAYNolan · Abilene | 1 of 6 | $1,166,773 | $1,166,773 | Won |
| Aug 5, 2021 | 2270-01-023 | PREVENTIVE MAINTENANCETaylor · Abilene | 1 of 4 | $4,152,368 | $4,152,368 | Won |
| Aug 4, 2021 | 0650-01-034 | WIDEN ROAD - ADD SHOULDERSNolan · Abilene | 2 of 8 | $6,321,831 | $5,924,739NOBLES ROAD CONSTRUCTION, I… | +6.7% |
| Aug 4, 2021 | 2032-03-013 | REHABILITATION OF EXISTING ROADWAYJones · Abilene | 5 of 6 | $4,081,322 | $3,551,480FOUTSCO PAVING COMPANY, LLC | +14.9% |
| Aug 4, 2021 | 0663-02-010 | ADD TURN LANETaylor · Abilene | 3 of 3 | $1,179,810 | $1,084,713CONTRACT PAVING CO. | +8.8% |
| Jul 1, 2021 | 0053-07-040 | INSTALL/UPGRADE ROADWAY LIGHTINGScurry · Abilene | 2 of 4 | $3,331,155 | $3,245,690A. L. HELMCAMP, INC. | +2.6% |
| Dec 3, 2020 | 0908-00-103 | SPOT REPAIR MILL AND FILLTaylor · Abilene | 3 of 7 | $949,053 | $914,854FOUTSCO PAVING COMPANY, LLC | +3.7% |
| Dec 2, 2020 | 0908-00-104 | SPOT REPAIR MILL AND FILLTaylor · Abilene | 1 of 6 | $1,094,532 | $1,094,532 | Won |
| Nov 5, 2020 | 0034-03-019 | ADD PASSING LANESRunnels · San Angelo | 1 of 8 | $24,497,111 | $24,497,111 | Won |
| Nov 5, 2020 | 6370-00-001 | MATERIALS ONLY SUPERPAVE MIXTURESTaylor · Abilene | 1 of 2 | $408,950 | $408,950 | Won |
| Nov 5, 2020 | 6370-04-001 | MATERIALS ONLY AGGREGATESTaylor · Abilene | 3 of 3 | $366,570 | $311,125ZACK BURKETT CO. | +17.8% |
| Nov 4, 2020 | 6369-89-001 | MATERIALS ONLY: DENSE GRADED HMATaylor · Abilene | 2 of 2 | $1,624,685 | $1,558,815VULCAN CONSTRUCTION MATERIA… | +4.2% |
| Oct 1, 2020 | 0982-07-013 | WIDEN AND REHABILITATE ROADWAYHaskell · Abilene | 2 of 4 | $9,519,630 | $9,371,184A. L. HELMCAMP, INC. | +1.6% |
| Oct 1, 2020 | 0181-01-061 | OVERLAYTaylor · Abilene | 2 of 7 | $2,435,920 | $2,378,250FOUTSCO PAVING COMPANY, LLC | +2.4% |
| Aug 6, 2020 | 0034-01-127 | ADD FRONTAGE ROAD CONNECTING FM 707 TO ANTILLEYTaylor · Abilene | 1 of 5 | $3,381,358 | $3,381,358 | Won |
| Aug 5, 2020 | 0181-02-032 | ADD TURN , ACCEL AND DECEL LANESCallahan · Abilene | 2 of 4 | $1,580,997 | $1,433,561CONTRACT PAVING CO. | +10.3% |
| Jul 9, 2020 | 0908-19-026 | BRIDGE REPLACEMENTScurry · Abilene | 3 of 5 | $2,319,059 | $2,002,574HODGES AND SON CONSTRUCTION… | +15.8% |
| May 8, 2020 | 0157-05-064 | SPOT REPAIR, OVERLAYJones · Abilene | 3 of 9 | $16,078,019 | $15,184,947ZACK BURKETT CO. | +5.9% |
| May 7, 2020 | 0011-05-051 | MILL AND FILL AND EXCAVATIONShackelford · Abilene | 2 of 4 | $10,674,159 | $10,086,760A. L. HELMCAMP, INC. | +5.8% |
| May 7, 2020 | 0908-24-050 | BRIDGE REPLACMENTJones · Abilene | 1 of 5 | $1,790,933 | $1,790,933 | Won |
| Dec 3, 2019 | 0011-01-038 | PEDTaylor · Abilene | 4 of 6 | $7,293,174 | $4,596,548BONTKE BROTHERS CONSTRUCTIO… | +58.7% |
| Sep 6, 2019 | 0126-01-039 | MILL, OVERLAY AND SAFETYShackelford · Abilene | 3 of 5 | $16,207,809 | $12,663,688A. L. HELMCAMP, INC. | +28.0% |
| Jun 4, 2019 | 0034-01-137 | PLAN, SEAL, SPOT REPAIR OVERLAYTaylor · Abilene | 1 of 3 | $4,451,082 | $4,451,082 | Won |
| May 7, 2019 | 0006-07-080 | MILL & SMA OVRLAYCallahan · Abilene | 2 of 6 | $11,175,409 | $10,684,705A. L. HELMCAMP, INC. | +4.6% |
| Apr 2, 2019 | 0181-01-061 | OVERLAYTaylor · Abilene | 1 of 1 | $5,300,067 | $5,300,067 | Won |
| Mar 6, 2019 | 0006-02-115 | 2" MILL & FILL, 1 CST AND 2" SMA DNolan · Abilene | 1 of 2 | $16,511,820 | $16,511,820 | Won |
| Mar 6, 2019 | 0699-01-055 | MILL AND OVERLAYTaylor · Abilene | 2 of 4 | $1,947,093 | $1,793,003FOUTSCO PAVING COMPANY, LLC | +8.6% |
| Jan 9, 2019 | 0437-02-017 | 3"OVERLAYCallahan · Abilene | 1 of 8 | $3,259,093 | $3,259,093 | Won |
| Jan 8, 2019 | 0125-04-033 | REHABILITATE AND WIDEN ROADWAYShackelford · Abilene | 4 of 5 | $14,631,960 | $12,581,377A. L. HELMCAMP, INC. | +16.3% |
| Jan 8, 2019 | 0296-05-034 | BASE REPAIR LEVEL UP AND OVERLAYJones · Abilene | 2 of 7 | $7,721,610 | $7,597,360CONTRACT PAVING CO. | +1.6% |
| Dec 5, 2018 | 6336-99-001 | MILL AND INLAYEastland · Brownwood | 2 of 7 | $604,705 | $547,807CONTRACT PAVING CO. | +10.4% |
| Sep 7, 2018 | 0033-04-063 | CONSTRUCT SUPER TWOJones · Abilene | 1 of 7 | $10,819,114 | $10,819,114 | Won |
| Aug 8, 2018 | 0034-01-126 | EMB, FL BS, STRS, AND ACPTaylor · Abilene | 7 of 7 | $39,666,161 | $27,993,542ALLEN BUTLER CONSTRUCTION, … | +41.7% |
| Aug 7, 2018 | 0484-01-023 | WIDEN ROADWAYJones · Abilene | 1 of 3 | $13,833,694 | $13,833,694 | Won |
| Jun 6, 2018 | 0296-02-033 | BRIDGE REPLACEMENTFisher · Abilene | 1 of 8 | $1,763,519 | $1,763,519 | Won |
| Jun 6, 2018 | 0908-00-087 | MILLING, HOTMIXTaylor · Abilene | 5 of 6 | $1,557,373 | $1,386,588FOUTSCO PAVING COMPANY, LLC | +12.3% |
| Jun 6, 2018 | 0006-07-079 | MILL AND OVERLAYCallahan · Abilene | 1 of 6 | $7,087,728 | $7,087,728 | Won |
| May 1, 2018 | 0006-18-058 | MILL & FILL W/ 1-CST AND SMATaylor · Abilene | 2 of 4 | $6,078,789 | $5,844,818CONTRACT PAVING CO. | +4.0% |
| Mar 7, 2018 | 0733-03-054 | OVERLAYTaylor · Abilene | 1 of 6 | $1,017,875 | $1,017,875 | Won |
| Mar 6, 2018 | 0011-01-036 | MILL,SPOT REPAIR & OVERLAYTaylor · Abilene | 2 of 5 | $1,727,317 | $1,708,497FOUTSCO PAVING COMPANY, LLC | +1.1% |
| Feb 1, 2018 | 0053-12-065 | ROADWAY REHABILITATION / ARMORINGNolan · Abilene | 4 of 8 | $3,856,040 | $3,160,245REECE ALBERT, INC. | +22.0% |
| Dec 5, 2017 | 0437-02-014 | REHABILITATIONCallahan · Abilene | 3 of 5 | $3,585,788 | $3,117,046CONTRACT PAVING CO. | +15.0% |
| Oct 4, 2017 | 6321-31-001 | CALL OUT TRAFFIC CONTROLTaylor · Abilene | 5 of 5 | $966,675 | $710,738ALTUS TRAFFIC MANAGEMENT LLC | +36.0% |
| Jul 11, 2017 | 0870-04-040 | RESTORATION OF EXISTING ROADConcho · San Angelo | 1 of 6 | $2,792,438 | $2,792,438 | Won |
| Jun 7, 2017 | 0033-06-107 | PLANE,UNDERSEAL,SMA,BR RAIL,BR JTSTaylor · Abilene | 1 of 6 | $8,326,092 | $8,326,092 | Won |
| Jun 6, 2017 | 0034-01-129 | REMOVE EXIST PVMNT,REPLC WITH CONCTaylor · Abilene | 4 of 4 | $3,413,345 | $2,346,056O. TREVINO CONSTRUCTION, LLC | +45.5% |
| Apr 5, 2017 | 2638-01-023 | RECONSTRUCT ROADWAYEastland · Brownwood | 7 of 8 | $870,784 | $712,724A. L. HELMCAMP, INC. | +22.2% |
| Apr 4, 2017 | 0007-01-054 | OVERLAYCallahan · Abilene | 1 of 8 | $8,248,492 | $8,248,492 | Won |
| Mar 8, 2017 | 0437-02-016 | RESTORATIONCallahan · Abilene | 8 of 12 | $2,339,696 | $1,793,914IOC COMPANY LLC | +30.4% |
| Mar 8, 2017 | 0006-03-132 | MILL,SPOT REPAIR,UNDERSEAL & OVERLAYNolan · Abilene | 6 of 10 | $15,617,804 | $14,579,827REECE ALBERT, INC. | +7.1% |
| Jan 5, 2017 | 0005-12-013 | FLX PAV STR RPR,UNDSL,&ACP OVERLAYMitchell · Abilene | 4 of 8 | $3,164,173 | $2,838,058PRICE CONSTRUCTION, LTD. | +11.5% |
| Jan 5, 2017 | 0078-03-055 | IMPRV GR, SFT TREAT OBJECTS, ADD PAColeman · Brownwood | 1 of 11 | $1,678,694 | $1,678,694 | Won |
| Oct 8, 2013 | 0053-12-057 | RECONSTR, REALIGN, WIDN, STRS, SFTY & SURFNolan · Abilene | 3 of 3 | $12,571,378 | $11,548,046PRICE CONSTRUCTION, LTD. | +8.9% |
| Sep 11, 2013 | 0034-01-124 | CONSTRUCT FRTGS TO ONE-WAY OPERATIONTaylor · Abilene | 1 of 2 | $4,055,813 | $4,055,813 | Won |
| Sep 10, 2013 | 0908-23-030 | REPLACE BRIDGE AND APPROACHESFisher · Abilene | 3 of 6 | $753,778 | $714,924ASHLAR CONTRACTING COMPANY | +5.4% |
| Sep 10, 2013 | 2398-01-047 | REL RAMPS RECONST FRONTAGE RD.Taylor · Abilene | 2 of 2 | $5,034,666 | $4,222,065CONTRACT PAVING CO. | +19.2% |
Active prime contracts 6
| CCSJ | Where | Work | Contract | Complete | Report |
|---|---|---|---|---|---|
| 0974-03-014Let Dec 3, 2025 | TaylorAbilene · FM 604 | BRIDGE REPLACEMENT | $2,739,392 | 37% | |
| 6490-55-001Let Oct 14, 2025 | HaskellAbilene · FM0600 | MAINTENANCE | $885,783 | 176% | |
| 6488-87-001Let Aug 11, 2025 | CallahanAbilene · US0283 | MATERIALS-ONLY CONTRACT | $1,042,727 | 70% | |
| 0181-01-067Let Jul 1, 2025 | TaylorAbilene · SH 36 | MISCELLANEOUS CONSTRUCTION | $4,175,101 | 44% | |
| 0663-03-031Let Apr 3, 2025 | TaylorAbilene · FM 1235 | WIDEN NON-FREEWAY | $3,259,427 | 95% | |
| 0907-13-017Let Jan 8, 2025 | RunnelsSan Angelo · CR | BRIDGE REPLACEMENT | $2,144,186 | 99% |
Subcontracts on active jobs 2
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 0034-01-130Let Oct 8, 2025 | JAMES CONSTRUCTION GROUP, LLC | TaylorAbilene | MISCELLANEOUS CONSTRUCTION | 0.07% | $51,817 |
| 0548-04-025Let Jun 6, 2024 | WESTFIELD INSURANCE COMPANY | HowardAbilene | BRIDGE REPLACEMENT | 9.71% | $246,343 |