$165.25Avg low bid / LF
$198.23Avg of all bids
$178.93Avg engineer's estimate
35Jobs · 16,337.44 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 1 | 202 | $223.69 | $298.30 |
| 2022 | 2 | 2,095.7 | $250.75 | $200.87 |
| 2020 | 1 | 72 | $549.00 | $614.67 |
| 2019 | 6 | 7,559.8 | $112.66 | $179.88 |
| 2018 | 14 | 4,237.9 | $191.22 | $212.44 |
| 2017 | 10 | 2,051.04 | $201.61 | $226.34 |
| 2016 | 1 | 119 | $117.33 | $186.56 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 3, 2023 | 0483-01-052 | La SalleLaredo | 202 LF | $223.69 | HUNTER INDUSTRIES, LTD. |
| Oct 7, 2022 | 0089-10-026 | WhartonYoakum | 677.7 LF | $200.00 | JAMES CONSTRUCTION GROUP, LLC |
| Jan 7, 2022 | 0032-07-029 | StonewallAbilene | 1,418 LF | $275.00 | DELHUR INDUSTRIES, INC. |
| May 8, 2020 | 0068-09-012 | LynnLubbock | 72 LF | $549.00 | ALLEN BUTLER CONSTRUCTION, INC. |
| Nov 6, 2019 | 0073-07-064 | Live OakCorpus Christi | 212 LF | $150.00 | HUNTER INDUSTRIES, LTD. |
| Aug 6, 2019 | 0246-01-036 | RuskTyler | 440.8 LF | $129.00 | MADDEN CONTRACTING COMPANY, LLC. |
| Aug 6, 2019 | 1804-01-079 | HidalgoPharr | 3,998 LF | $102.23 | CLORE EQUIPMENT LLC |
| Apr 2, 2019 | 0206-04-042 | CherokeeTyler | 2,306 LF | $95.00 | MADDEN CONTRACTING COMPANY, LLC. |
| Feb 5, 2019 | 2452-04-016 | BexarSan Antonio | 516 LF | $220.00 | MARIO SINACOLA & SONS EXCAVATING, INC. |
| Jan 8, 2019 | 0457-03-028 | WashingtonBryan | 87 LF | $250.00 | BIG CREEK CONSTRUCTION, LTD. |
| Nov 7, 2018 | 0037-01-042 | UvaldeSan Antonio | 176 LF | $190.00 | HUNTER INDUSTRIES, LTD. |
| Nov 6, 2018 | 0906-00-185 | EctorOdessa | 687.3 LF | $200.00 | VIZCAINO, L.P. |
| Oct 3, 2018 | 0109-01-062 | AndersonTyler | 212 LF | $200.00 | A. L. HELMCAMP, INC. |
| Sep 7, 2018 | 0033-04-063 | JonesAbilene | 344 LF | $310.00 | J. H. STRAIN & SONS, INC. |
| Aug 8, 2018 | 1349-03-013 | BurnetAustin | 240 LF | $180.00 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
| Aug 8, 2018 | 0101-03-088 | San PatricioCorpus Christi | 75 LF | $112.00 | HAAS-ANDERSON CONSTRUCTION, LTD. |
| Jul 11, 2018 | 0102-16-001 | NuecesCorpus Christi | 336 LF | $300.00 | ZACHRY CONSTRUCTION CORPORATION |
| Jul 11, 2018 | 0922-00-064 | WebbLaredo | 264 LF | $275.00 | RELMCO, INC. |
| Jun 5, 2018 | 0254-03-079 | Jim WellsCorpus Christi | 150 LF | $205.00 | ANDERSON COLUMBIA CO., INC. |
| May 2, 2018 | 0415-01-025 | Jeff DavisEl Paso | 57.3 LF | $500.00 | VIZCAINO, L.P. |
| May 2, 2018 | 0138-04-046 | RuskTyler | 346 LF | $74.75 | MADDEN CONTRACTING COMPANY, LLC. |
| May 1, 2018 | 0006-04-072 | TaylorAbilene | 665 LF | $117.00 | FNH CONSTRUCTION, LLC |
| Apr 3, 2018 | 0813-01-101 | LibertyBeaumont | 166 LF | $210.00 | L.C. JORDAN & SON |
| Mar 7, 2018 | 0372-01-102 | San PatricioCorpus Christi | 519.3 LF | $130.00 | BAY LTD. |
| Dec 5, 2017 | 0043-05-107 | WilbargerWichita Falls | 280.7 LF | $250.00 | GIBSON & ASSOCIATES, INC. |
| Nov 2, 2017 | 0114-07-080 | LeeAustin | 186 LF | $125.00 | DAN WILLIAMS COMPANY |
| Aug 8, 2017 | 0339-03-037 | HardinBeaumont | 140 LF | $221.00 | WIDGEON CONSTRUCTION, INC. |
| Aug 8, 2017 | 0315-03-059 | GrimesBryan | 230 LF | $160.00 | ANGEL BROTHERS HOLDINGS CORP. |
| Jul 12, 2017 | 0396-02-026 | MasonAustin | 67 LF | $225.00 | L.C. JORDAN & SON |
| Apr 5, 2017 | 0233-01-044 | CulbersonEl Paso | 115.34 LF | $197.00 | VIZCAINO, L.P. |
| Apr 5, 2017 | 1200-01-023 | WilliamsonAustin | 200 LF | $200.00 | HUNTER INDUSTRIES, LTD. |
| Mar 8, 2017 | 6295-90-001 | CameronPharr | 100 LF | $150.00 | ARANDA BROTHERS CONSTRUCTION CO., INC. |
| Feb 3, 2017 | 0143-08-097 | De WittYoakum | 66 LF | $197.41 | HUNTER INDUSTRIES, LTD. |
| Jan 5, 2017 | 0373-02-093 | NuecesCorpus Christi | 666 LF | $220.00 | BAY LTD. |
| Dec 1, 2016 | 0669-01-049 | HidalgoPharr | 119 LF | $117.33 | ASAGO, LLC |