$105.44Avg low bid / TON
$105.78Avg of all bids
$87.83Avg engineer's estimate
9Jobs · 128,699 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2019 | 4 | 97,656 | $111.58 | $107.24 |
| 2018 | 2 | 11,658 | $88.02 | $99.89 |
| 2017 | 2 | 11,363 | $82.95 | $110.15 |
| 2016 | 1 | 8,022 | $88.00 | $91.00 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 6, 2019 | 0185-01-030 | BellWaco | 73,960 TON | $105.00 | J.D. ABRAMS, L.P. |
| Nov 5, 2019 | 0249-01-047 | WichitaWichita Falls | 9,554 TON | $165.00 | A. L. HELMCAMP, INC. |
| May 7, 2019 | 0048-09-029 | HillWaco | 1,025 TON | $185.00 | SACYR CONSTRUCTION USA LLC |
| Apr 3, 2019 | 0320-01-072 | BellWaco | 13,117 TON | $104.00 | TEXAS MATERIALS GROUP, INC. |
| Nov 6, 2018 | 6312-48-001 | JasperBeaumont | 1,631 TON | $125.00 | OLDCASTLE MATERIALS TEXAS, INC. |
| Aug 8, 2018 | 0327-10-062 | WillacyPharr | 10,027 TON | $82.00 | FOREMOST PAVING, INC. |
| Aug 9, 2017 | 0920-38-187 | JeffersonBeaumont | 9,283 TON | $87.00 | OLDCASTLE MATERIALS TEXAS, INC. |
| Jan 5, 2017 | 0015-21-012 | McLennanWaco | 2,080 TON | $64.90 | KNIFE RIVER CORPORATION - SOUTH |
| Dec 1, 2016 | 0056-03-061 | LimestoneWaco | 8,022 TON | $88.00 | BIG CREEK CONSTRUCTION, LTD. |