GATESVILLE AO - FY27 BASE FAILURE REPAIR
6510-38-001 · let Nov 3, 2026 · Coryell, Waco · Routine Maintenance Project
$1,146,275Low bid: BIG CREEK CONSTRUCTION, LTD.-4.7% vs estimate $1,203,177
$160,415Left on the table14.0% gap to the second bid
4BiddersSpread 75% low to high
25Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,146,275 | -4.7% | $160,415 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,306,690 | +14.0% | 8.6% | $51,489 | 1+$23,116 | 1-$6,754 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,358,179 | +18.5% | 12.9% | $647,471 | 4+$77,952 | 0 |
| 4 | LONE STAR PAVING COMPANY | $2,005,650 | +75.0% | 66.7% | 7+$757,183 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7022 D-GR HMA TY-C PG70-22 | 3,000 TON | $130.00 | $152.00 | $114.77 | $66,000 |
| 344-7019 SP MIXES SP-C PG70-22 | 1,000 TON | $130.00 | $164.00 | $142.22 | $34,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $50.00 | $8,550.00 | $844.81 | $25,500 |
| 341-7048 D-GR HMA TY-D PG70-22 | 1,600 TON | $132.00 | $146.00 | $126.94 | $22,400 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 3,100 SY | $45.00 | $51.00 | $35.01 | $18,600 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 1,800 SY | $85.00 | $93.00 | $60.19 | $14,400 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $250.00 | $105.00 | $217.57 | -$8,700 |
| 3006-7001 UNDERSEAL COURSE | 3,600 GAL | $5.00 | $4.00 | $3.65 | -$3,600 |
| 672-7004 REFL PAV MRKR TY II-A-A | 2,400 EA | $4.50 | $5.50 | $3.97 | $2,400 |
| 341-7082 TACK COAT | 1,000 GAL | $5.00 | $2.90 | $3.93 | -$2,100 |
| 505-7002 TMA (MOBILE OPERATION) | 60 HR | $45.00 | $20.00 | $64.00 | -$1,500 |
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 2,000 LF | $1.85 | $1.10 | $0.5533 | -$1,500 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 2,000 LF | $1.85 | $1.10 | $0.5714 | -$1,500 |
| 666-7302 TY I HIGH PERF PM (Y)6"(BRK)(100MIL) | 2,000 LF | $1.80 | $1.25 | $0.5735 | -$1,100 |
| 666-7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL) | 2,000 LF | $1.75 | $1.25 | $0.5652 | -$1,000 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 21 DAY | $50.00 | $10.00 | $117.34 | -$840 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 18 EA | $265.00 | $300.00 | $201.69 | $630 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 18 EA | $335.00 | $300.00 | $249.54 | -$630 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 300 EA | $2.00 | $1.00 | $1.03 | -$300 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 300 EA | $2.00 | $1.00 | $0.5715 | -$300 |
Positive: the low bidder was cheaper on that item. These 20 items account for $160,860 of the $160,415 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3LONE STAR PAVING COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7022 D-GR HMA TY-C PG70-22 | 3,000 TON | $210.00 | $114.77 | 1.83x | $285,702 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 1,800 SY | $152.00 | $60.19 | 2.53x | $165,256 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 3,100 SY | $87.00 | $35.01 | 2.48x | $161,154 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $9,500.00 | $600.85 | 15.81x | $53,395 |
| 354-7051 PLANE ASPH CONC PAV(2") | 15,000 SY | $5.00 | $1.86 | 2.69x | $47,145 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $12,000.00 | $844.81 | 14.20x | $33,466 |
| 341-7082 TACK COAT | 1,000 GAL | $15.00 | $3.93 | 3.81x | $11,065 |