Bid Tab X-ray: 6510-37-001

Nov 3, 2026 · McLennan Sign up free
Set your company to personalize scores

MCLENNAN - FY27 BASE FAILURE REPAIR

6510-37-001 · let Nov 3, 2026 · McLennan, Waco · Routine Maintenance Project

$2,172,910Low bid: TEXAS MATERIALS GROUP, INC.-12.6% vs estimate $2,486,802
$48,140Left on the table2.2% gap to the second bid
4BiddersSpread 63% low to high
24Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1TEXAS MATERIALS GROUP, INC. $2,172,910-12.6% $48,140 0 1-$11,457
2BIG CREEK CONSTRUCTION, LTD. $2,221,050+2.2%-10.7% $119,920 1+$20,102 0
3KNIFE RIVER CORPORATION - SOUTH $2,340,970+7.7%-5.9% $1,201,130 2+$46,434 0
4LONE STAR PAVING COMPANY $3,542,100+63.0%42.4% 5+$567,264 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

TEXAS MATERIALS GROUP, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings
ItemQtyLow2ndMarket2nd minus low
354-7051 PLANE ASPH CONC PAV(2")118,000 SY $1.50$2.00$1.86 $59,000
3006-7001 UNDERSEAL COURSE20,000 GAL $4.00$3.00$3.65 -$20,000
351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")2,000 SY $45.00$35.00$35.01 -$20,000
341-7048 D-GR HMA TY-D PG70-221,000 TON $143.00$125.00$126.94 -$18,000
666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL)45,000 LF $0.7000$1.00$0.5533 $13,500
500-7002 MOBILIZATION (CALLOUT)10 EA $10.00$700.00$600.85 $6,900
500-7033 MOBILIZATION (EMERGENCY)2 EA $3,250.00$50.00$844.81 -$6,400
666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL)20,000 LF $0.7000$1.00$0.5714 $6,000
344-7019 SP MIXES SP-C PG70-2212,000 TON $119.50$119.00$142.22 -$6,000
351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")2,000 SY $67.00$70.00$60.19 $6,000
505-7002 TMA (MOBILE OPERATION)120 HR $1.00$50.00$64.00 $5,880
341-7082 TACK COAT2,000 GAL $2.90$5.00$3.93 $4,200
666-7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL)15,000 LF $0.8000$1.00$0.5652 $3,000
672-7004 REFL PAV MRKR TY II-A-A1,000 EA $5.50$7.70$3.97 $2,200
672-7006 REFL PAV MRKR TY II-C-R1,000 EA $5.50$7.70$4.19 $2,200
7010-7002 MAINTENANCE SPEED LIMIT SIGNING40 DAY $1.00$50.00$117.34 $1,960
666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL)400 LF $12.00$16.50$7.19 $1,800
662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W2,500 EA $0.9500$1.50$1.03 $1,375
662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-22,500 EA $0.9500$1.50$0.5715 $1,375
668-7103 PREFAB PM TY C (W)(WORD)10 EA $300.00$420.00$249.54 $1,200

Positive: the low bidder was cheaper on that item. These 20 items account for $46,190 of the $48,140 gap.

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)100 DAY $103.00$217.570.47x-$11,457

BIG CREEK CONSTRUCTION, LTD.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL)45,000 LF $1.00$0.55331.81x$20,102

KNIFE RIVER CORPORATION - SOUTH: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)100 DAY $525.00$217.572.41x$30,743
500-7002 MOBILIZATION (CALLOUT)10 EA $2,170.00$600.853.61x$15,692

LONE STAR PAVING COMPANY: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")2,000 SY $155.00$60.192.58x$189,618
354-7051 PLANE ASPH CONC PAV(2")118,000 SY $3.25$1.861.75x$164,374
351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")2,000 SY $89.00$35.012.54x$107,970
500-7002 MOBILIZATION (CALLOUT)10 EA $9,300.00$600.8515.48x$86,992
500-7033 MOBILIZATION (EMERGENCY)2 EA $10,000.00$844.8111.84x$18,310