MCLENNAN - FY27 BASE FAILURE REPAIR
6510-37-001 · let Nov 3, 2026 · McLennan, Waco · Routine Maintenance Project
$2,172,910Low bid: TEXAS MATERIALS GROUP, INC.-12.6% vs estimate $2,486,802
$48,140Left on the table2.2% gap to the second bid
4BiddersSpread 63% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $2,172,910 | -12.6% | $48,140 | 0 | 1-$11,457 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $2,221,050 | +2.2% | -10.7% | $119,920 | 1+$20,102 | 0 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $2,340,970 | +7.7% | -5.9% | $1,201,130 | 2+$46,434 | 0 |
| 4 | LONE STAR PAVING COMPANY | $3,542,100 | +63.0% | 42.4% | 5+$567,264 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 354-7051 PLANE ASPH CONC PAV(2") | 118,000 SY | $1.50 | $2.00 | $1.86 | $59,000 |
| 3006-7001 UNDERSEAL COURSE | 20,000 GAL | $4.00 | $3.00 | $3.65 | -$20,000 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 2,000 SY | $45.00 | $35.00 | $35.01 | -$20,000 |
| 341-7048 D-GR HMA TY-D PG70-22 | 1,000 TON | $143.00 | $125.00 | $126.94 | -$18,000 |
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 45,000 LF | $0.7000 | $1.00 | $0.5533 | $13,500 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $10.00 | $700.00 | $600.85 | $6,900 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $3,250.00 | $50.00 | $844.81 | -$6,400 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 20,000 LF | $0.7000 | $1.00 | $0.5714 | $6,000 |
| 344-7019 SP MIXES SP-C PG70-22 | 12,000 TON | $119.50 | $119.00 | $142.22 | -$6,000 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 2,000 SY | $67.00 | $70.00 | $60.19 | $6,000 |
| 505-7002 TMA (MOBILE OPERATION) | 120 HR | $1.00 | $50.00 | $64.00 | $5,880 |
| 341-7082 TACK COAT | 2,000 GAL | $2.90 | $5.00 | $3.93 | $4,200 |
| 666-7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL) | 15,000 LF | $0.8000 | $1.00 | $0.5652 | $3,000 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,000 EA | $5.50 | $7.70 | $3.97 | $2,200 |
| 672-7006 REFL PAV MRKR TY II-C-R | 1,000 EA | $5.50 | $7.70 | $4.19 | $2,200 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 40 DAY | $1.00 | $50.00 | $117.34 | $1,960 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 400 LF | $12.00 | $16.50 | $7.19 | $1,800 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 2,500 EA | $0.9500 | $1.50 | $1.03 | $1,375 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,500 EA | $0.9500 | $1.50 | $0.5715 | $1,375 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 10 EA | $300.00 | $420.00 | $249.54 | $1,200 |
Positive: the low bidder was cheaper on that item. These 20 items account for $46,190 of the $48,140 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 100 DAY | $103.00 | $217.57 | 0.47x | -$11,457 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 45,000 LF | $1.00 | $0.5533 | 1.81x | $20,102 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3LONE STAR PAVING COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 2,000 SY | $155.00 | $60.19 | 2.58x | $189,618 |
| 354-7051 PLANE ASPH CONC PAV(2") | 118,000 SY | $3.25 | $1.86 | 1.75x | $164,374 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 2,000 SY | $89.00 | $35.01 | 2.54x | $107,970 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $9,300.00 | $600.85 | 15.48x | $86,992 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $10,000.00 | $844.81 | 11.84x | $18,310 |