OV | US 77 | FM 3148 | LP 340
0209-01-076 · let May 6, 2026 · McLennan, Waco · Overlay
$5,957,588Low bid: BIG CREEK CONSTRUCTION, LTD.-37.1% vs estimate $9,476,549
$819,910Left on the table13.8% gap to the second bid
4BiddersSpread 36% low to high
67Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $5,957,588 | -37.1% | $819,910 | 0 | 4-$565,655 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $6,777,497 | +13.8% | -28.5% | $512,308 | 0 | 4-$446,409 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $7,289,805 | +22.4% | -23.1% | $790,305 | 0 | 0 |
| 4 | LONE STAR PAVING COMPANY | $8,080,110 | +35.6% | -14.7% | 2+$160,300 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 347-7001 TOM-C PG76-22 SAC-A | 10,752 TON | $120.00 | $148.50 | $169.86 | $306,432 |
| 344-7021 SP MIXES SP-C SAC-B PG70-22 | 21,504 TON | $90.00 | $101.60 | $120.21 | $249,446 |
| 354-7052 PLANE ASPH CONC PAV(3") | 191,565 SY | $2.60 | $3.20 | $2.92 | $114,939 |
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $202,000.00 | $523,850.32 | $112,000 |
| 3007-7001 BONDING COURSE | 22,438 GAL | $1.00 | $4.00 | $3.32 | $67,314 |
| 530-7010 DRIVEWAYS (ACP) | 6,998 SY | $36.00 | $45.00 | $54.96 | $62,982 |
| 439-7025 POLYESTER POLYMER CONC OVERLAY | 251 CY | $4,000.00 | $3,763.00 | $3,291.39 | -$59,487 |
| 347-7011 TACK COAT | 18,699 GAL | $1.00 | $3.30 | $3.24 | $43,008 |
| 483-7020 MICROMILLING CONCRETE SLAB (1/2 IN) | 2,290 SY | $25.00 | $8.20 | $25.00 | -$38,472 |
| 505-7001 TMA (STATIONARY) | 109 DAY | $350.00 | $85.19 | $217.57 | -$28,864 |
| 479-7007 ADJUSTING MANHOLES (WATER VALVE BOX) | 22 EA | $900.00 | $1,715.00 | $781.02 | $17,930 |
| 483-7017 DIAMOND GRINDING SLAB | 459 SY | $35.00 | $70.00 | $50.11 | $16,065 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $4,000.00 | $1,500.00 | $11,585.04 | -$12,500 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 1,037.5 LF | $42.00 | $32.50 | $30.74 | -$9,856 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $7,500.00 | $5,400.00 | $9,253.78 | -$8,400 |
| 506-7003 ROCK FILTER DAMS (INSTALL) (TY 3) | 500 LF | $75.00 | $90.00 | $71.34 | $7,500 |
| 429-7009 CONC STR REPAIR (STANDARD) | 413 SF | $75.00 | $60.00 | $146.35 | -$6,195 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 125 CY | $680.00 | $723.00 | $616.83 | $5,375 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 500 LF | $10.00 | $20.00 | $12.47 | $5,000 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 43,205 LF | $0.6000 | $0.5000 | $0.5714 | -$4,321 |
Positive: the low bidder was cheaper on that item. These 20 items account for $839,896 of the $819,910 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $523,850.32 | 0.17x | -$433,850 |
| 3007-7001 BONDING COURSE | 22,438 GAL | $1.00 | $3.32 | 0.30x | -$52,083 |
| 347-7011 TACK COAT | 18,699 GAL | $1.00 | $3.24 | 0.31x | -$41,796 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $4,000.00 | $11,585.04 | 0.35x | -$37,925 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $202,000.00 | $523,850.32 | 0.39x | -$321,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $1,500.00 | $11,585.04 | 0.13x | -$50,425 |
| 483-7020 MICROMILLING CONCRETE SLAB (1/2 IN) | 2,290 SY | $8.20 | $25.00 | 0.33x | -$38,472 |
| 429-7009 CONC STR REPAIR (STANDARD) | 413 SF | $60.00 | $146.35 | 0.41x | -$35,661 |