FM 969 from Utley Rd to Howard Ln
1186-02-028 · let May 6, 2026 · Bastrop, Austin · Safety Improvement Projects
$3,189,429Low bid: HUNTER INDUSTRIES, LTD.-4.5% vs estimate $3,339,794
$98,032Left on the table3.1% gap to the second bid
8BiddersSpread 21% low to high
63Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HUNTER INDUSTRIES, LTD. | $3,189,429 | -4.5% | $98,032 | 1+$25,207 | 2-$466,147 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $3,287,461 | +3.1% | -1.6% | $6,297 | 1+$22,533 | 4-$1,025,917 |
| 3 | TEXAS MATERIALS GROUP, INC. | $3,293,758 | +3.3% | -1.4% | $15,745 | 3+$206,484 | 4-$778,744 |
| 4 | DAN WILLIAMS COMPANY | $3,309,503 | +3.8% | -0.9% | $330,357 | 1+$35,262 | 2-$330,517 |
| 5 | JOE BLAND CONSTRUCTION LLC | $3,639,860 | +14.1% | 9.0% | $9,884 | 4+$152,456 | 3-$996,708 |
| 6 | AARON CONCRETE CONTRACTORS, LLC | $3,649,743 | +14.4% | 9.3% | $135,863 | ||
| 7 | ACME BRIDGE COMPANY, INC. | $3,785,606 | +18.7% | 13.3% | $81,447 | ||
| 8 | PATIN CONSTRUCTION LLC | $3,867,053 | +21.2% | 15.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HUNTER INDUSTRIES, LTD. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7007 EMBANK (FNL)(OC)(TY C1) | 6,354 CY | $50.64 | $17.00 | $50.95 | -$213,749 |
| 341-7003 D-GR HMA TY-B PG64-22 (EXEMPT) | 3,995 TON | $94.60 | $115.00 | $127.48 | $81,498 |
| 341-7065 D-GR HMA TY-D PG 76-22 (EXEMPT) | 3,251 TON | $105.60 | $127.00 | $111.42 | $69,571 |
| 100-7002 PREPARING ROW | 82 STA | $1,098.90 | $350.00 | $6,072.92 | -$61,410 |
| 347-7002 TOM-C PG76-22 SAC-B | 2,184 TON | $127.60 | $155.00 | $130.62 | $59,842 |
| 247-7191 FL BS (CMP IN PLC)(TY D GR 5)(FNAL POS) | 4,172 CY | $66.99 | $80.00 | $62.11 | $54,278 |
| 464-7040 RC PIPE (ARCH)(CL III)(DES 1) | 663 LF | $210.00 | $285.00 | $201.47 | $49,725 |
| 500-7001 MOBILIZATION | 1 LS | $274,515.53 | $250,000.00 | $523,850.32 | -$24,516 |
| 110-7001 EXCAV (ROADWAY) | 7,822 CY | $19.80 | $17.00 | $11.68 | -$21,902 |
| 662-7116 WK ZN PAV MRK SHT TERM RMV (Y)(4") | 16,400 LF | $0.7800 | $2.00 | $1.57 | $20,008 |
| 464-7042 RC PIPE (ARCH)(CL III)(DES 3) | 178 LF | $257.00 | $350.00 | $264.66 | $16,554 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $2,706.25 | $10,000.00 | $9,253.78 | $14,588 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 15,838 LF | $0.1900 | $1.00 | $0.2394 | $12,829 |
| 530-7010 DRIVEWAYS (ACP) | 1,447 SY | $48.40 | $40.00 | $54.96 | -$12,155 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 50 CY | $234.78 | $465.00 | $184.74 | $11,511 |
| 505-7001 TMA (STATIONARY) | 145 DAY | $108.25 | $185.00 | $217.57 | $11,129 |
| 105-7012 RMV (12"-16") TRT/UNTRT BASE & ASPH PAV | 1,765 SY | $8.73 | $15.00 | $8.45 | $11,067 |
| 466-7101 HEADWALL (CH - PW - 0) (DIA= 24 IN) | 1 EA | $10,280.00 | $20,500.00 | $8,593.16 | $10,220 |
| 354-7005 PLANE & TEXT ASPH CONC PAV(0" TO 6") | 2,369 SY | $1.65 | $5.75 | $4.63 | $9,713 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $3,259.68 | $2,000.00 | $11,585.04 | -$8,818 |
Positive: the low bidder was cheaper on that item. These 20 items account for $89,983 of the $98,032 gap.
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 1BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 196 TON | $230.00 | $115.04 | 2.00x | $22,533 |
| 100-7002 PREPARING ROW | 82 STA | $350.00 | $6,072.92 | 0.06x | -$469,280 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 132-7007 EMBANK (FNL)(OC)(TY C1) | 6,354 CY | $17.00 | $50.95 | 0.33x | -$215,692 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $2,000.00 | $11,585.04 | 0.17x | -$67,095 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7002 TMA (MOBILE OPERATION) | 208 HR | $595.00 | $64.00 | 9.30x | $110,449 |
| 530-7002 INTERSECTIONS (ACP) | 595 SY | $146.00 | $50.74 | 2.88x | $56,682 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 30,969 SY | $2.70 | $1.43 | 1.89x | $39,352 |
| 100-7002 PREPARING ROW | 82 STA | $400.00 | $6,072.92 | 0.07x | -$465,180 |
| 132-7007 EMBANK (FNL)(OC)(TY C1) | 6,354 CY | $17.30 | $50.95 | 0.34x | -$213,786 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,610.00 | $11,585.04 | 0.14x | -$69,825 |
| 505-7001 TMA (STATIONARY) | 145 DAY | $11.00 | $217.57 | 0.05x | -$29,953 |
DAN WILLIAMS COMPANY: unbalanced items
Placed 4JOE BLAND CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 30,969 SY | $3.00 | $1.43 | 2.10x | $48,643 |
| 467-7418 SET (TY II) (DES 1) (RCP) (6: 1) (P) | 18 EA | $4,500.00 | $1,799.60 | 2.50x | $48,607 |
| 105-7012 RMV (12"-16") TRT/UNTRT BASE & ASPH PAV | 1,765 SY | $25.00 | $8.45 | 2.96x | $29,213 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $22,250.00 | $9,253.78 | 2.40x | $25,992 |
| 100-7002 PREPARING ROW | 82 STA | $1,500.00 | $6,072.92 | 0.25x | -$374,980 |
| 500-7001 MOBILIZATION | 1 LS | $175,000.00 | $523,850.32 | 0.33x | -$348,850 |
| 132-7007 EMBANK (FNL)(OC)(TY C1) | 6,354 CY | $8.00 | $50.95 | 0.16x | -$272,878 |