Hot Mix - Coryell and Hamilton

6498-77-001 · let Jul 1, 2026 · Coryell, Waco · Material Maintenance Project

$1,194,788Low bid: BIG CREEK CONSTRUCTION, LTD.-2.6% vs estimate $1,227,192
$53,138Left on the table4.4% gap to the second bid
4BiddersSpread 16% low to high
9Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BIG CREEK CONSTRUCTION, LTD. $1,194,788-2.6% $53,138 0 0
2LONE STAR PAVING COMPANY $1,247,925+4.4%1.7% $53,161 0 0
3TEXAS MATERIALS GROUP, INC. $1,301,086+8.9%6.0% $87,052 0 0
4KNIFE RIVER CORPORATION - SOUTH $1,388,138+16.2%13.1% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

BIG CREEK CONSTRUCTION, LTD. vs LONE STAR PAVING COMPANY, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8011-7058 D-GR HMA TY D PG 64-22 (DEL) SITE 33,000 TON $86.00$94.75$98.12 $26,250
8011-7004 D-GR HMA TY B PG 64-22 (DEL) SITE 31,000 TON $80.75$90.75$75.45 $10,000
8011-7057 D-GR HMA TY D PG 64-22 (DEL) SITE 25,000 TON $88.00$89.25$96.66 $6,250
8011-7003 D-GR HMA TY B PG 64-22 (DEL) SITE 21,500 TON $82.75$85.25$84.72 $3,750
8011-7040 D-GR HMA TY C PG 64-22 (DEL) SITE 3250 TON $85.25$95.75$119.54 $2,625
8011-7001 D-GR HMA TY B PG 64-22 (PICKUP)1,000 TON $61.75$63.25$69.58 $1,500
8011-7037 D-GR HMA TY C PG 64-22 (PICKUP)750 TON $66.25$68.25$82.72 $1,500
8011-7039 D-GR HMA TY C PG 64-22 (DEL) SITE 2250 TON $87.25$90.25$123.86 $750
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)2,050 TON $67.00$67.25$89.12 $513

Positive: the low bidder was cheaper on that item. These 9 items account for $53,138 of the $53,138 gap.