Material Maintenance Project
CCSJ 6512-38-001 · lets Jan 6, 2027 · Bosque, Waco · SH0006
$1,579,936Engineer's estimate
Items at market: $1,777,610 (+12.5%)
$1,483,175Most likely low bid$1,395,410 to $1,531,588 (middle half)
3.2Expected bidders0 plan holders, 0 regular bidders
73/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$1,483,175
Estimate $1,579,936
$1,357,479 (1 in 10 go lower)$1,572,604 (1 in 10 go higher)
From 23 comparable let jobs (district + work type, estimates of $631,974 to $3,949,840, last 3 years). 91% of them went under the estimate; the typical low bid was -6.1% vs estimate.
Bid / no-bid score
- Competition24 / 25Jobs like this draw about 3.2 bidders.
- Margin9 / 20Low bids land at 94% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Jul 2026 | 6498-12-001Hill · 3 bidders | $1,864,225-4.8% |
| Jul 2026 | 6498-13-001McLennan · 3 bidders | $1,955,438-2.5% |
| Jul 2026 | 6498-75-001Bell · 4 bidders | $1,302,581-4.8% |
| Jul 2026 | 6498-77-001Coryell · 4 bidders | $1,194,788-2.6% |
| Jan 2026 | 6493-72-001Bell · 4 bidders | $761,450-3.5% |
| Jan 2026 | 6493-73-001Hill · 3 bidders | $704,310-20.2% |
| Jan 2026 | 6491-85-001Falls · 3 bidders | $1,531,500-12.2% |
| Jan 2026 | 6493-71-001Bosque · 4 bidders | $1,416,100-10.7% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
9 of 9 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 8011-7061 D-GR HMA TY D PG 64-22 (DEL) SITE 66 low bids | 5,000 TON | $93.49 | $83.50 – $110.75 | $467,431 | 26.3% |
| 8011-7007 D-GR HMA TY B PG 64-22 (DEL) SITE 66 low bids | 5,000 TON | $81.87 | $76.00 – $139.50 | $409,348 | 23.0% |
| 8011-7058 D-GR HMA TY D PG 64-22 (DEL) SITE 329 low bids | 3,000 TON | $98.12 | $81.00 – $205.00 | $294,366 | 16.6% |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)150 low bids | 1,800 TON | $89.12 | $59.00 – $147.00 | $160,423 | 9.0% |
| 8011-7043 D-GR HMA TY C PG 64-22 (DEL) SITE 64 low bids | 1,500 TON | $88.63 | $81.00 – $91.00 | $132,946 | 7.5% |
| 8011-7001 D-GR HMA TY B PG 64-22 (PICKUP)56 low bids | 1,500 TON | $69.58 | $54.00 – $132.00 | $104,370 | 5.9% |
| 8011-7037 D-GR HMA TY C PG 64-22 (PICKUP)45 low bids | 1,250 TON | $82.72 | $58.00 – $150.00 | $103,398 | 5.8% |
| 8011-7004 D-GR HMA TY B PG 64-22 (DEL) SITE 323 low bids | 1,000 TON | $75.45 | $69.00 – $106.11 | $75,445 | 4.2% |
| 8011-7040 D-GR HMA TY C PG 64-22 (DEL) SITE 311 low bids | 250 TON | $119.54 | $79.00 – $200.00 | $29,884 | 1.7% |