Hot Mix - Falls and Limestone
6491-85-001 · let Jan 7, 2026 · Falls, Waco · Material Maintenance Project
$1,531,500Low bid: BIG CREEK CONSTRUCTION, LTD.-12.2% vs estimate $1,743,375
$169,740Left on the table11.1% gap to the second bid
3BiddersSpread 13% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,531,500 | -12.2% | $169,740 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,701,240 | +11.1% | -2.4% | $30,510 | 0 | 0 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,731,750 | +13.1% | -0.7% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 3,500 TON | $59.00 | $70.25 | $89.12 | $39,375 |
| 8011-7062 D-GR HMA TY D PG 64-22 (DEL) SITE 7 | 5,000 TON | $82.00 | $89.36 | $90.71 | $36,800 |
| 8011-7001 D-GR HMA TY B PG 64-22 (PICKUP) | 3,000 TON | $54.00 | $63.02 | $69.58 | $27,060 |
| 8011-7008 D-GR HMA TY B PG 64-22 (DEL) SITE 7 | 2,000 TON | $72.00 | $82.13 | $72.55 | $20,260 |
| 8011-7037 D-GR HMA TY C PG 64-22 (PICKUP) | 1,500 TON | $58.00 | $69.22 | $82.72 | $16,830 |
| 8011-7060 D-GR HMA TY D PG 64-22 (DEL) SITE 5 | 5,000 TON | $82.00 | $85.23 | $87.20 | $16,150 |
| 8011-7044 D-GR HMA TY C PG 64-22 (DEL) SITE 7 | 500 TON | $76.00 | $88.33 | $83.61 | $6,165 |
| 8011-7042 D-GR HMA TY C PG 64-22 (DEL) SITE 5 | 500 TON | $76.00 | $84.20 | $80.01 | $4,100 |
| 8011-7006 D-GR HMA TY B PG 64-22 (DEL) SITE 5 | 500 TON | $72.00 | $78.00 | $75.07 | $3,000 |
Positive: the low bidder was cheaper on that item. These 9 items account for $169,740 of the $169,740 gap.