Hot Mix - Bosque and Hamilton
6493-71-001 · let Jan 6, 2026 · Bosque, Waco · Material Maintenance Project
$1,416,100Low bid: BIG CREEK CONSTRUCTION, LTD.-10.7% vs estimate $1,585,950
$171,250Left on the table12.1% gap to the second bid
4BiddersSpread 14% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,416,100 | -10.7% | $171,250 | 0 | 0 | |
| 2 | NORTHEASTERN PAVERS, LLC | $1,587,350 | +12.1% | 0.1% | $900 | 0 | 0 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,588,250 | +12.2% | 0.1% | $30,279 | 0 | 0 |
| 4 | TEXAS MATERIALS GROUP, INC. | $1,618,529 | +14.3% | 2.1% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs NORTHEASTERN PAVERS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7058 D-GR HMA TY D PG 64-22 (DEL) SITE 3 | 3,000 TON | $81.00 | $97.00 | $98.12 | $48,000 |
| 8011-7061 D-GR HMA TY D PG 64-22 (DEL) SITE 6 | 5,000 TON | $83.50 | $92.00 | $93.49 | $42,500 |
| 8011-7007 D-GR HMA TY B PG 64-22 (DEL) SITE 6 | 5,000 TON | $76.00 | $82.00 | $81.87 | $30,000 |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 1,800 TON | $62.00 | $72.00 | $89.12 | $18,000 |
| 8011-7004 D-GR HMA TY B PG 64-22 (DEL) SITE 3 | 1,000 TON | $74.00 | $87.00 | $75.45 | $13,000 |
| 8011-7001 D-GR HMA TY B PG 64-22 (PICKUP) | 1,500 TON | $56.00 | $62.00 | $69.58 | $9,000 |
| 8011-7037 D-GR HMA TY C PG 64-22 (PICKUP) | 750 TON | $61.00 | $67.00 | $82.72 | $4,500 |
| 8011-7040 D-GR HMA TY C PG 64-22 (DEL) SITE 3 | 250 TON | $79.00 | $92.00 | $119.54 | $3,250 |
| 8011-7043 D-GR HMA TY C PG 64-22 (DEL) SITE 6 | 500 TON | $81.00 | $87.00 | $88.63 | $3,000 |
Positive: the low bidder was cheaper on that item. These 9 items account for $171,250 of the $171,250 gap.