Bid Tab X-ray: 6498-13-001

Jul 2, 2026 · McLennan Sign up free
Set your company to personalize scores

Hot Mix - McLennan and Limestone

6498-13-001 · let Jul 2, 2026 · McLennan, Waco · Material Maintenance Project

$1,955,438Low bid: BIG CREEK CONSTRUCTION, LTD.-2.5% vs estimate $2,004,625
$15,225Left on the table0.8% gap to the second bid
3BiddersSpread 10% low to high
9Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BIG CREEK CONSTRUCTION, LTD. $1,955,438-2.5% $15,225 0 0
2TEXAS MATERIALS GROUP, INC. $1,970,663+0.8%-1.7% $185,288 0 0
3KNIFE RIVER CORPORATION - SOUTH $2,155,950+10.3%7.5% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8011-7062 D-GR HMA TY D PG 64-22 (DEL) SITE 74,000 TON $86.00$79.66$90.71 -$25,360
8011-7063 D-GR HMA TY D PG 64-22 (DEL) SITE 88,000 TON $82.00$85.17$84.86 $25,360
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)3,750 TON $67.00$72.14$89.12 $19,275
8011-7044 D-GR HMA TY C PG 64-22 (DEL) SITE 71,000 TON $84.75$76.15$83.61 -$8,600
8011-7008 D-GR HMA TY B PG 64-22 (DEL) SITE 71,000 TON $80.00$72.14$72.55 -$7,860
8011-7001 D-GR HMA TY B PG 64-22 (PICKUP)1,750 TON $61.00$65.13$69.58 $7,227
8011-7037 D-GR HMA TY C PG 64-22 (PICKUP)1,750 TON $66.75$69.14$82.72 $4,183
8011-7009 D-GR HMA TY B PG 64-22 (DEL) SITE 81,500 TON $76.00$77.65$77.94 $2,475
8011-7045 D-GR HMA TY C PG 64-22 (DEL) SITE 82,500 TON $80.75$80.16$81.20 -$1,475

Positive: the low bidder was cheaper on that item. These 9 items account for $15,225 of the $15,225 gap.