Hot Mix - McLennan and Limestone
6498-13-001 · let Jul 2, 2026 · McLennan, Waco · Material Maintenance Project
$1,955,438Low bid: BIG CREEK CONSTRUCTION, LTD.-2.5% vs estimate $2,004,625
$15,225Left on the table0.8% gap to the second bid
3BiddersSpread 10% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,955,438 | -2.5% | $15,225 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,970,663 | +0.8% | -1.7% | $185,288 | 0 | 0 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $2,155,950 | +10.3% | 7.5% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7062 D-GR HMA TY D PG 64-22 (DEL) SITE 7 | 4,000 TON | $86.00 | $79.66 | $90.71 | -$25,360 |
| 8011-7063 D-GR HMA TY D PG 64-22 (DEL) SITE 8 | 8,000 TON | $82.00 | $85.17 | $84.86 | $25,360 |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 3,750 TON | $67.00 | $72.14 | $89.12 | $19,275 |
| 8011-7044 D-GR HMA TY C PG 64-22 (DEL) SITE 7 | 1,000 TON | $84.75 | $76.15 | $83.61 | -$8,600 |
| 8011-7008 D-GR HMA TY B PG 64-22 (DEL) SITE 7 | 1,000 TON | $80.00 | $72.14 | $72.55 | -$7,860 |
| 8011-7001 D-GR HMA TY B PG 64-22 (PICKUP) | 1,750 TON | $61.00 | $65.13 | $69.58 | $7,227 |
| 8011-7037 D-GR HMA TY C PG 64-22 (PICKUP) | 1,750 TON | $66.75 | $69.14 | $82.72 | $4,183 |
| 8011-7009 D-GR HMA TY B PG 64-22 (DEL) SITE 8 | 1,500 TON | $76.00 | $77.65 | $77.94 | $2,475 |
| 8011-7045 D-GR HMA TY C PG 64-22 (DEL) SITE 8 | 2,500 TON | $80.75 | $80.16 | $81.20 | -$1,475 |
Positive: the low bidder was cheaper on that item. These 9 items account for $15,225 of the $15,225 gap.