Material Maintenance Project - Sealed
CCSJ 6508-64-001 · lets Dec 10, 2026 · La Salle, Laredo · IH0035
$850,150Engineer's estimate
Items at market: $896,867 (+5.5%)
$852,467Most likely low bid$846,135 to $890,414 (middle half)
1.6Expected bidders3 plan holders, 3 regular bidders
87/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$852,467
Estimate $850,150
$832,066 (1 in 10 go lower)$922,078 (1 in 10 go higher)
From 13 comparable let jobs (district + work type, estimates of $340,060 to $2,125,375, last 3 years). 31% of them went under the estimate; the typical low bid was 0.3% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 1.6 bidders.
- Margin14 / 20Low bids land at 100% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6509-54-001Maverick · 1 bidders | $400,400-0.5% |
| Oct 2026 | 6506-34-001Duval · 1 bidders | $534,600-7.4% |
| Apr 2026 | 6498-98-001Duval · 2 bidders | $903,920+13.0% |
| Apr 2026 | 6500-53-001Dimmit · 2 bidders | $1,088,300+8.9% |
| Jun 2025 | 6484-41-001La Salle · 1 bidders | $474,4800.0% |
| May 2025 | 6483-87-001Val Verde · 2 bidders | $816,620+0.3% |
| May 2025 | 6483-92-001Duval · 2 bidders | $881,040-2.5% |
| May 2025 | 6484-38-001Webb · 2 bidders | $566,650+1.5% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Laredo | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| VULCAN CONSTRUCTION MATERIALS, LLC SharpestBidders | 220 | 106 | 10 of 11 | 4.9% | -1.1% | $891,506 |
| TOUCHSTONE RESOURCES, LLCBidders | 413 | 170 | 3 of 3 | 11.0% | 0.5% | $943,925 |
| MARTIN MARIETTA MATERIALS, INC.Bidders | 243 | 64 | 1 of 10 | 15.3% | 1.3% | $980,190 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.