Limestone Rock Asphalt Dimmit County
6500-53-001 · let Apr 22, 2026 · Dimmit, Laredo · Material Maintenance Project - Sealed
$1,088,300Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+8.9% vs estimate $999,200
$23,540Left on the table2.2% gap to the second bid
2BiddersSpread 2% low to high
6Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $1,088,300 | 8.9% | $23,540 | 0 | 0 | |
| 2 | MARTIN MARIETTA MATERIALS, INC. | $1,111,840 | +2.2% | 11.3% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7009 LRA (TY I GR AA) (DEL) (ST1) | 5,000 TON | $94.35 | $99.22 | $112.79 | $24,350 |
| 8001-7093 LRA (TY II GR CS) (DEL) (ST1) | 5,000 TON | $95.35 | $99.22 | $104.61 | $19,350 |
| 8000-7099 AGGR (TY B GR 4) (DEL) (ST1) | 1,000 TON | $62.35 | $51.22 | $67.96 | -$11,130 |
| 8000-7085 AGGR (TY B GR 3) (DEL) (ST1) | 1,000 TON | $62.35 | $52.22 | $72.41 | -$10,130 |
| 8001-7007 LRA (TY II GR CS) (PICKUP) | 100 TON | $76.00 | $82.00 | $74.00 | $600 |
| 8001-7001 LRA (TY I GR AA) (PICKUP) | 100 TON | $75.00 | $80.00 | $73.50 | $500 |
Positive: the low bidder was cheaper on that item. These 6 items account for $23,540 of the $23,540 gap.