Bridge Maintenance
CCSJ 0914-00-510 · lets Jan 7, 2027 · Travis, Austin · Various
$1,030,008Engineer's estimate
Items at market: $1,349,636 (+31.0%)
$717,747Most likely low bid$623,148 to $907,805 (middle half)
9.6Expected bidders0 plan holders, 0 regular bidders
0/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$717,747
Estimate $1,030,008
$547,367 (1 in 10 go lower)$1,107,312 (1 in 10 go higher)
From 12 comparable let jobs (district + work type, estimates of $412,003 to $2,575,021, last 3 years). 83% of them went under the estimate; the typical low bid was -30.3% vs estimate.
Bid / no-bid score
- Competition0 / 25Jobs like this draw about 9.6 bidders.
- Margin0 / 20Low bids land at 70% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 0204-01-075Williamson · 14 bidders | $344,329-43.3% |
| Jul 2026 | 0700-04-058Llano · 11 bidders | $526,435-33.6% |
| Mar 2026 | 0914-00-509Travis · 14 bidders | $1,606,502-14.4% |
| Mar 2026 | 0914-00-574Travis · 13 bidders | $327,386-36.9% |
| Mar 2026 | 0914-00-575Travis · 13 bidders | $769,928-25.5% |
| Aug 2025 | 0151-06-157Travis · 2 bidders | $498,058-38.2% |
| May 2025 | 0914-00-557Travis · 6 bidders | $865,709-47.3% |
| May 2025 | 0914-00-508Travis · 9 bidders | $659,812-58.5% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
34 of 38 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 38.8% |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT59 low bids · prices swing 23x | 19,611 SY | $10.07 | $4.35 – $100.00 | $197,531 | 14.6% |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH))96 low bids · prices swing 200x | 1,764 SF | $95.74 | $5.00 – $1,000.00 | $168,891 | 12.5% |
| 788-7001 CONCRETE BEAM REPAIR39 low bids · prices swing 32x | 15 EA | $4,623.25 | $935.00 – $30,000.00 | $69,349 | 5.1% |
| 446-7021 CLEAN AND PAINT EXIST STR (REF NO. 2)12 low bids · prices swing 3,513x | 1 EA | $67,579.16 | $500.00 – $1,756,700.00 | $67,579 | 5.0% |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN)119 low bids · prices swing 11x | 200 CY | $190.61 | $45.00 – $500.00 | $38,122 | 2.8% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 3 MO | $11,585.04 | $0.0010 – $273,686.48 | $34,755 | 2.6% |
| 788-7002 CONCRETE BEAM REPAIR (CFRP)26 low bids · prices swing 12x | 5 EA | $6,492.05 | $2,540.18 – $30,000.00 | $32,460 | 2.4% |
| 446-7020 CLEAN AND PAINT EXIST STR (REF NO. 1)16 low bids · prices swing 1,333x | 1 EA | $28,146.70 | $600.00 – $800,000.00 | $28,147 | 2.1% |
| 420-7061 CL C CONC (COLLAR)56 low bids · prices swing 12x | 20 EA | $1,390.28 | $500.00 – $6,000.00 | $27,806 | 2.1% |
| 459-7010 GABIONS (3' X 3')(GALV)22 low bids · prices swing 4x | 82 CY | $319.83 | $150.00 – $617.47 | $26,226 | 1.9% |
| 446-7009 CLEAN & PAINT EXIST PIL (SPL PROT SYS)1 low bids | 1 LS | $25,000.00 | $25,000.00 – $25,000.00 | $25,000 | 1.9% |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD)271 low bids · prices swing 1,700x | 130 SF | $150.68 | $1.00 – $1,700.00 | $19,588 | 1.5% |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR)37 low bids · prices swing 22x | 120 SF | $151.82 | $25.00 – $547.00 | $18,218 | 1.3% |
| 420-7059 CL C CONC(PILE ENCASEMENT)17 low bids · prices swing 13x | 24 LF | $435.92 | $111.63 – $1,500.00 | $10,462 | 0.8% |