FY 26 FUA - AUS BR Maint
0914-00-509 · let Mar 5, 2026 · Travis, Austin · Bridge Maintenance
$1,606,502Low bid: PREMIER CONTRACTORS LLC-14.4% vs estimate $1,877,685
$121,560Left on the table7.6% gap to the second bid
14BiddersSpread 144% low to high
32Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PREMIER CONTRACTORS LLC | $1,606,502 | -14.4% | $121,560 | 3+$245,446 | 6-$3,276,470 | |
| 2 | TAYLOR BRIDGE LLC | $1,728,062 | +7.6% | -8.0% | $4,588 | 2+$175,903 | 7-$3,278,935 |
| 3 | BLACKSMITH VENTURES LLC | $1,732,650 | +7.9% | -7.7% | $44,670 | 0 | 7-$3,262,131 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $1,777,320 | +10.6% | -5.3% | $95,018 | 0 | 4-$3,200,502 |
| 5 | BK FIELD OPERATIONS LLC | $1,872,338 | +16.5% | -0.3% | $66,568 | 1+$14,162 | 7-$3,309,935 |
| 6 | STRUCTURAL INTEGRITY GROUP LLC | $1,938,906 | +20.7% | 3.3% | $40,444 | ||
| 7 | ROY JORGENSEN ASSOCIATES, INC. | $1,979,350 | +23.2% | 5.4% | $42,190 | ||
| 8 | PATHFIELD INVESTMENTS LLC | $2,021,540 | +25.8% | 7.7% | $88,369 | ||
| 9 | SCR CIVIL CONSTRUCTION, LLC | $2,109,909 | +31.3% | 12.4% | $21,380 | ||
| 10 | RESTEK, INC. | $2,131,289 | +32.7% | 13.5% | $561,806 | ||
| 11 | MPB, INC. | $2,693,095 | +67.6% | 43.4% | $13,210 | ||
| 12 | ICOS MANAGEMENT, LLC | $2,706,305 | +68.5% | 44.1% | $100,835 | ||
| 13 | SOUTHERN ROAD & BRIDGE, LLC | $2,807,140 | +74.7% | 49.5% | $1,105,405 | ||
| 14 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $3,912,545 | +143.5% | 108.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
PREMIER CONTRACTORS LLC vs TAYLOR BRIDGE LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II) | 2 LS | $250,000.00 | $400,000.00 | $301,243.48 | $300,000 |
| 788-7001 CONCRETE BEAM REPAIR | 20 EA | $5,000.00 | $1,000.00 | $4,623.25 | -$80,000 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 631 SF | $500.00 | $400.00 | $150.68 | -$63,100 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $200,000.00 | $523,850.32 | $50,000 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 916 CY | $250.00 | $200.00 | $190.61 | -$45,800 |
| 420-7067 CL C CONC (MISC) | 18 CY | $2,000.00 | $850.00 | $1,569.38 | -$20,700 |
| 446-7021 CLEAN AND PAINT EXIST STR (REF NO. 2) | 40 EA | $500.00 | $1,000.00 | $67,579.16 | $20,000 |
| 446-7005 CLEAN & PAINT EXIST RAIL (SYSTEM II) | 3 LS | $25,000.00 | $30,000.00 | $48,200.00 | $15,000 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 10 SF | $1,500.00 | $500.00 | $192.68 | -$10,000 |
| 776-7001 REPAIR (STEEL RAIL) | 55 LF | $250.00 | $125.00 | $138.55 | -$6,875 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 221 LF | $70.00 | $100.00 | $15.92 | $6,630 |
| 401-7001 FLOWABLE BACKFILL | 9 CY | $1,000.00 | $350.00 | $298.77 | -$5,850 |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR) | 45 SF | $300.00 | $175.00 | $151.82 | -$5,625 |
| 100-7005 PREP ROW (TREE REMOVE) (24"-36" DIA) | 6 EA | $1,500.00 | $600.00 | $1,166.77 | -$5,400 |
| 506-7035 SANDBAGS FOR EROSION CONTROL | 130 EA | $35.00 | $1.00 | $14.97 | -$4,420 |
| 459-7010 GABIONS (3' X 3')(GALV) | 25 CY | $500.00 | $325.00 | $319.83 | -$4,375 |
| 459-7008 GABION MATTRESSES (GALV)(18 IN) | 20 SY | $500.00 | $285.00 | $176.35 | -$4,300 |
| 420-7044 CL C CONC (FOOTING) | 8 CY | $1,500.00 | $1,000.00 | $1,466.73 | -$4,000 |
| 480-7002 CLEAN EXIST CULVERTS | 16 CY | $500.00 | $250.00 | $42.86 | -$4,000 |
| 432-7029 RIPRAP (STONE COMMON)(DRY)(6 IN) | 5 CY | $300.00 | $1,000.00 | $165.45 | $3,500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $130,685 of the $121,560 gap.
PREMIER CONTRACTORS LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 631 SF | $500.00 | $150.68 | 3.32x | $220,421 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 10 SF | $1,500.00 | $192.68 | 7.78x | $13,073 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 221 LF | $70.00 | $15.92 | 4.40x | $11,952 |
| 446-7021 CLEAN AND PAINT EXIST STR (REF NO. 2) | 40 EA | $500.00 | $67,579.16 | 0.01x | -$2,683,166 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $1.00 | $11,585.04 | 0.00x | -$139,009 |
| 505-7003 TMA (MOBILE OPERATION) | 130 DAY | $1.00 | $229.60 | 0.00x | -$29,718 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $1.00 | $217.57 | 0.00x | -$28,154 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 260 DAY | $1.00 | $87.82 | 0.01x | -$22,573 |
TAYLOR BRIDGE LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 631 SF | $400.00 | $150.68 | 2.65x | $157,321 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 221 LF | $100.00 | $15.92 | 6.28x | $18,582 |
| 446-7021 CLEAN AND PAINT EXIST STR (REF NO. 2) | 40 EA | $1,000.00 | $67,579.16 | 0.01x | -$2,663,166 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $1.00 | $11,585.04 | 0.00x | -$139,009 |
| 788-7001 CONCRETE BEAM REPAIR | 20 EA | $1,000.00 | $4,623.25 | 0.22x | -$72,465 |
| 505-7003 TMA (MOBILE OPERATION) | 130 DAY | $1.00 | $229.60 | 0.00x | -$29,718 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $1.00 | $217.57 | 0.00x | -$28,154 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 260 DAY | $1.00 | $87.82 | 0.01x | -$22,573 |
BLACKSMITH VENTURES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7021 CLEAN AND PAINT EXIST STR (REF NO. 2) | 40 EA | $1,000.00 | $67,579.16 | 0.01x | -$2,663,166 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $5,000.00 | $11,585.04 | 0.43x | -$79,021 |
| 505-7003 TMA (MOBILE OPERATION) | 130 DAY | $1.00 | $229.60 | 0.00x | -$29,718 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $1.00 | $217.57 | 0.00x | -$28,154 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 260 DAY | $1.00 | $87.82 | 0.01x | -$22,573 |
| 420-7067 CL C CONC (MISC) | 18 CY | $700.00 | $1,569.38 | 0.45x | -$15,649 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 446-7021 CLEAN AND PAINT EXIST STR (REF NO. 2) | 40 EA | $2,200.00 | $67,579.16 | 0.03x | -$2,615,166 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 788-7001 CONCRETE BEAM REPAIR | 20 EA | $500.00 | $4,623.25 | 0.11x | -$82,465 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $5,000.00 | $11,585.04 | 0.43x | -$79,021 |
BK FIELD OPERATIONS LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 221 LF | $80.00 | $15.92 | 5.03x | $14,162 |
| 446-7021 CLEAN AND PAINT EXIST STR (REF NO. 2) | 40 EA | $1,350.00 | $67,579.16 | 0.02x | -$2,649,166 |
| 500-7001 MOBILIZATION | 1 LS | $130,000.00 | $523,850.32 | 0.25x | -$393,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $1.00 | $11,585.04 | 0.00x | -$139,009 |
| 788-7001 CONCRETE BEAM REPAIR | 20 EA | $2,250.00 | $4,623.25 | 0.49x | -$47,465 |
| 505-7003 TMA (MOBILE OPERATION) | 130 DAY | $1.00 | $229.60 | 0.00x | -$29,718 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $1.00 | $217.57 | 0.00x | -$28,154 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 260 DAY | $1.00 | $87.82 | 0.01x | -$22,573 |