Safety Improvement Projects
CCSJ 0893-04-015 · lets Dec 1, 2026 · Angelina, Shelby, Lufkin · FM 2026, FM 328, Various · Highway Improvement
$4,851,340Engineer's estimate
Items at market: $3,790,009 (-21.9%)
$4,602,826Most likely low bid$4,154,103 to $4,959,363 (middle half)
5.3Expected bidders5 plan holders, 5 regular bidders
56/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$4,602,826
Estimate $4,851,340
$3,784,661 (1 in 10 go lower)$5,594,038 (1 in 10 go higher)
From 31 comparable let jobs (district, estimates of $1,940,536 to $12,128,349, last 3 years). 68% of them went under the estimate; the typical low bid was -5.1% vs estimate.
Bid / no-bid score
- Competition15 / 25Jobs like this draw about 5.3 bidders.
- Margin10 / 20Low bids land at 95% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 0059-05-048Shelby · 5 bidders | $10,730,970+4.0% |
| Oct 2026 | 0911-00-188Angelina · 5 bidders | $3,269,224+34.6% |
| Aug 2026 | 0911-28-082Houston · 6 bidders | $2,809,388+13.5% |
| Jul 2026 | 0213-03-112Polk · 8 bidders | $3,332,948+0.0% |
| Jul 2026 | 3110-01-003Houston · 5 bidders | $3,814,102-7.1% |
| Jun 2026 | 0937-01-027Houston · 9 bidders | $4,462,648-11.9% |
| May 2026 | 0138-06-049Nacogdoches · 6 bidders | $2,886,840-4.7% |
| May 2026 | 0176-01-116Nacogdoches · 3 bidders | $5,689,159-7.8% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Lufkin | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| CENTERLINE TECHNOLOGIES, LLC SharpestBidders | 98 | 26 | 1 of 3 | -14.5% | -23.4% | $4,147,076 |
| STRIPE-A-ZONE, LLCBidders | 188 | 51 | 2 of 7 | -8.9% | -22.7% | $4,420,858 |
| STRIPING TECHNOLOGY, L.P.Bidders | 97 | 22 | 2 of 10 | -4.0% | -21.9% | $4,654,866 |
| VIZCAINO, L.P.Bidders | 25 | 10 | -0.8% | -4.7% | $4,814,647 | |
| DREWERY CONSTRUCTION COMPANY, INCORPORATEDBidders | 55 | 10 | 4 of 28 | 10.0% | 3.4% | $5,334,476 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
27 of 31 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 666-7501 RE PROFILE PM TY I(W)6"(SLD)(125MIL)2 low bids · prices swing 7x | 2,501,314 LF | $0.7680 | $0.7500 – $5.50 | $1,921,086 | 50.7% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.9 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $471,465 | 12.4% |
| 666-7519 REFL PAV MRK TY I (W)6"(SLD)(125MIL)5 low bids | 565,978 LF | $0.6060 | $0.5500 – $1.00 | $342,992 | 9.0% |
| 666-7523 REFL PAV MRK TY I (Y)6"(SLD)(125MIL)5 low bids | 505,829 LF | $0.6108 | $0.5500 – $1.00 | $308,965 | 8.2% |
| 666-7505 RE PROFILE PM TY I(Y)6"(BRK)(125MIL)1 low bids | 103,860 LF | $0.7500 | $0.7500 – $0.7500 | $77,895 | 2.1% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 6 MO | $11,585.04 | $0.0010 – $273,686.48 | $69,510 | 1.8% |
| 666-7519 REFL PAV MRK TY I (W)6"(SLD)(125MIL)5 low bids | 110,679 LF | $0.6060 | $0.5500 – $1.00 | $67,073 | 1.8% |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)352 low bids · prices swing 380x | 301,619 LF | $0.2040 | $0.0500 – $19.00 | $61,530 | 1.6% |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)43 low bids · prices swing 188x | 22,136 LF | $2.68 | $0.1000 – $18.75 | $59,354 | 1.6% |
| 666-7523 REFL PAV MRK TY I (Y)6"(SLD)(125MIL)5 low bids | 89,706 LF | $0.6108 | $0.5500 – $1.00 | $54,793 | 1.4% |
| 666-7522 REFL PAV MRK TY I (Y)6"(BRK)(125MIL)4 low bids | 60,506 LF | $0.6313 | $0.5500 – $1.00 | $38,195 | 1.0% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.07 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $36,670 | 1.0% |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)260 low bids · prices swing 250x | 149,810 LF | $0.2394 | $0.0800 – $20.00 | $35,865 | 0.9% |
| 505-7003 TMA (MOBILE OPERATION)1256 low bids · prices swing 3,000,000x | 155 DAY | $229.60 | $0.0010 – $3,000.00 | $35,588 | 0.9% |
| 666-7519 REFL PAV MRK TY I (W)6"(SLD)(125MIL)5 low bids | 54,943 LF | $0.6060 | $0.5500 – $1.00 | $33,296 | 0.9% |