FM 227_FROM FM 2544 TO 3.3 MI EAST
0937-01-027 · let Jun 3, 2026 · Houston, Lufkin · Safety Improvement Projects
$4,462,648Low bid: PINTO CONSTRUCTION CO., INC.-11.9% vs estimate $5,065,573
$413,601Left on the table9.3% gap to the second bid
9BiddersSpread 47% low to high
88Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PINTO CONSTRUCTION CO., INC. | $4,462,648 | -11.9% | $413,601 | 0 | 4-$1,008,888 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $4,876,249 | +9.3% | -3.7% | $68,247 | 0 | 3-$753,101 |
| 3 | L. S. EQUIPMENT CO., INC. | $4,944,496 | +10.8% | -2.4% | $176,720 | 0 | 4-$1,004,038 |
| 4 | A. L. HELMCAMP, INC. | $5,121,216 | +14.8% | 1.1% | $168,465 | 1+$33,785 | 2-$720,193 |
| 5 | THK CONSTRUCTION LLC | $5,289,681 | +18.5% | 4.4% | $349,066 | 0 | 3-$935,336 |
| 6 | LONGVIEW BRIDGE AND ROAD, LTD. | $5,638,747 | +26.4% | 11.3% | $158,098 | ||
| 7 | ENVIRONMENTAL ALLIES, INC. | $5,796,845 | +29.9% | 14.4% | $347,365 | ||
| 8 | GARRET SHIELDS INFRASTRUCTURE | $6,144,210 | +37.7% | 21.3% | $417,385 | ||
| 9 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $6,561,594 | +47.0% | 29.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
PINTO CONSTRUCTION CO., INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 5,989 TON | $165.88 | $135.00 | $137.95 | -$184,940 |
| 500-7001 MOBILIZATION | 1 LS | $302,000.00 | $475,000.00 | $523,850.32 | $173,000 |
| 100-7002 PREPARING ROW | 175 STA | $1,600.00 | $2,500.00 | $6,072.92 | $157,500 |
| 247-7210 FL BS (RDWY DEL) (TY D GR 3) | 20,271 TON | $50.37 | $45.00 | $42.12 | -$108,855 |
| 132-7015 EMBANK (VEH)(OC)(TY B) | 7,491 CY | $20.33 | $29.00 | $25.35 | $64,947 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,500.00 | $5,000.00 | $11,585.04 | $52,500 |
| 505-7001 TMA (STATIONARY) | 294 DAY | $75.00 | $250.00 | $217.57 | $51,450 |
| 112-7001 SUBGR WIDEN (OC) | 175 STA | $342.55 | $500.00 | $458.34 | $27,554 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 3 EA | $5,000.00 | $12,500.00 | $9,253.78 | $22,500 |
| 204-7001 SPRINKLING (DUST CONTROL) | 544.4 TGL | $0.0100 | $35.00 | $8.40 | $19,049 |
| 505-7003 TMA (MOBILE OPERATION) | 38 DAY | $50.00 | $500.00 | $229.60 | $17,100 |
| 150-7001 BLADING | 175 STA | $164.28 | $250.00 | $152.64 | $15,001 |
| 506-7002 ROCK FILTER DAMS (INSTALL) (TY 2) | 1,430 LF | $30.75 | $40.00 | $44.91 | $13,228 |
| 275-7001 CEMENT | 980 TON | $211.51 | $225.00 | $224.93 | $13,220 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 7,076 LF | $3.50 | $5.00 | $3.92 | $10,614 |
| 134-7002 BACKFILL (TY B) | 175 STA | $196.38 | $250.00 | $206.94 | $9,384 |
| 275-7033 CEMENT TREAT (MX EXT MTL/NW BASE) (13") | 54,444 SY | $3.34 | $3.50 | $3.34 | $8,711 |
| 420-7061 CL C CONC (COLLAR) | 10 EA | $1,249.50 | $500.00 | $1,390.28 | -$7,495 |
| 530-7018 TURNOUTS (ACP) | 330 SY | $53.34 | $75.00 | $82.59 | $7,148 |
| 464-7003 RC PIPE (CL III)(18 IN) | 692 LF | $71.40 | $80.00 | $83.08 | $5,951 |
Positive: the low bidder was cheaper on that item. These 20 items account for $367,565 of the $413,601 gap.
PINTO CONSTRUCTION CO., INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 175 STA | $1,600.00 | $6,072.92 | 0.26x | -$782,761 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,500.00 | $11,585.04 | 0.13x | -$151,276 |
| 505-7001 TMA (STATIONARY) | 294 DAY | $75.00 | $217.57 | 0.34x | -$41,916 |
| 168-7001 VEGETATIVE WATERING | 3,909.8 TGL | $0.0100 | $8.43 | 0.00x | -$32,935 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2L. S. EQUIPMENT CO., INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 175 STA | $1,500.00 | $6,072.92 | 0.25x | -$800,261 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $2,500.00 | $11,585.04 | 0.22x | -$136,276 |
| 505-7001 TMA (STATIONARY) | 294 DAY | $100.00 | $217.57 | 0.46x | -$34,566 |
| 168-7001 VEGETATIVE WATERING | 3,909.8 TGL | $0.0100 | $8.43 | 0.00x | -$32,935 |