Safety Improvement Projects
CCSJ 0594-03-029 · lets Jan 7, 2027 · Rusk, Tyler · FM 225 · Hazard Elimination & Safety
$1,474,875Engineer's estimate
Items at market: $2,450,597 (+66.2%)
$1,360,026Most likely low bid$1,150,106 to $1,488,268 (middle half)
4.9Expected bidders0 plan holders, 0 regular bidders
56/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$1,360,026
Estimate $1,474,875
$1,017,595 (1 in 10 go lower)$1,717,520 (1 in 10 go higher)
From 80 comparable let jobs (district, estimates of $589,950 to $3,687,188, last 3 years). 71% of them went under the estimate; the typical low bid was -7.8% vs estimate.
Bid / no-bid score
- Competition17 / 25Jobs like this draw about 4.9 bidders.
- Margin8 / 20Low bids land at 92% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6504-71-001Wood · 1 bidders | $905,160+24.0% |
| Nov 2026 | 6509-96-001Henderson · 4 bidders | $1,217,140+2.0% |
| Nov 2026 | 6508-86-001Gregg · 4 bidders | $1,372,080-2.4% |
| Oct 2026 | 6508-38-001Smith · 3 bidders | $1,076,000+14.4% |
| Oct 2026 | 6508-42-001Cherokee · 3 bidders | $1,038,750+19.9% |
| Oct 2026 | 6496-83-001Gregg · 2 bidders | $1,287,808-15.8% |
| Oct 2026 | 6504-70-001Wood · 2 bidders | $2,735,000+18.7% |
| Sep 2026 | 6504-69-001Wood · 8 bidders | $667,750-31.0% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
62 of 64 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x | 179 STA | $6,072.92 | $0.0100 – $861,170.00 | $1,087,053 | 44.4% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 21.4% |
| 530-7010 DRIVEWAYS (ACP)299 low bids · prices swing 84x | 2,533 SY | $54.96 | $8.88 – $750.00 | $139,202 | 5.7% |
| 464-7003 RC PIPE (CL III)(18 IN)318 low bids · prices swing 13x | 1,152 LF | $83.08 | $36.17 – $475.00 | $95,710 | 3.9% |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P)249 low bids · prices swing 10x | 68 EA | $1,176.76 | $675.00 – $6,675.00 | $80,020 | 3.3% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 4 MO | $11,585.04 | $0.0010 – $273,686.48 | $46,340 | 1.9% |
| 134-7001 BACKFILL (TY A)113 low bids · prices swing 200x | 172 STA | $224.26 | $30.00 – $6,000.00 | $38,573 | 1.6% |
| 496-7037 REMOV STR (PIPE)64 low bids · prices swing 940x | 52 EA | $740.62 | $10.00 – $9,403.53 | $38,512 | 1.6% |
| 467-7327 SET (TY II) (24 IN) (RCP) (6: 1) (C)58 low bids · prices swing 6x | 16 EA | $2,267.09 | $1,300.00 – $7,775.00 | $36,273 | 1.5% |
| 464-7005 RC PIPE (CL III)(24 IN)353 low bids · prices swing 11x | 312 LF | $108.34 | $46.00 – $500.00 | $33,801 | 1.4% |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P)611 low bids · prices swing 67x | 47 EA | $696.14 | $60.00 – $4,000.00 | $32,719 | 1.3% |
| 530-7007 DRIVEWAYS (CONC) (HES)79 low bids · prices swing 12x | 219 SY | $122.10 | $32.00 – $395.00 | $26,740 | 1.1% |
| 451-7052 RETROFIT RAIL (ADD HSS)12 low bids | 212 LF | $125.03 | $100.00 – $243.85 | $26,506 | 1.1% |
| 432-7013 RIPRAP (MOW STRIP)(4 IN)593 low bids · prices swing 3,900x | 33 CY | $616.83 | $1.00 – $3,900.00 | $20,355 | 0.8% |
| 132-7017 EMBANK (VEH)(OC)(TY C)56 low bids · prices swing 28x | 538 CY | $37.09 | $9.00 – $250.00 | $19,954 | 0.8% |