FY 27 Pavement Markings Call Out
6496-83-001 · let Oct 6, 2026 · Gregg, Tyler · Routine Maintenance Project - Sealed
$1,287,808Low bid: STRIPING TECHNOLOGY, L.P.-15.8% vs estimate $1,529,895
$1,236,887Left on the table96.0% gap to the second bid
2BiddersSpread 96% low to high
81Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPING TECHNOLOGY, L.P. | $1,287,808 | -15.8% | $1,236,887 | 5+$172,610 | 1-$32,399 | |
| 2 | STRIPE LINES, INC. | $2,524,694 | +96.0% | 65.0% | 10+$1,258,745 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
STRIPING TECHNOLOGY, L.P. vs STRIPE LINES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 315-7004 FOG SEAL (CSS-1H) | 4,050 GAL | $12.25 | $125.00 | $4.02 | $456,638 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 550,000 LF | $0.1600 | $0.6200 | $0.1701 | $253,000 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 550,000 LF | $0.1600 | $0.6000 | $0.1749 | $242,000 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 125,000 LF | $0.5200 | $0.9900 | $0.4757 | $58,750 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 100,000 LF | $0.5200 | $0.9900 | $0.4986 | $47,000 |
| 505-7003 TMA (MOBILE OPERATION) | 250 DAY | $100.00 | $250.00 | $229.60 | $37,500 |
| 672-7004 REFL PAV MRKR TY II-A-A | 25,000 EA | $5.00 | $6.00 | $3.97 | $25,000 |
| 677-7002 ELIM EXT PM & MRKS (6") | 38,000 LF | $0.3000 | $0.6500 | $0.2755 | $13,300 |
| 666-7211 RE PM TY II (Y) 6" (BRK) | 30,000 LF | $0.2200 | $0.6000 | $0.1759 | $11,400 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 45,000 LF | $1.10 | $1.35 | $0.2040 | $11,250 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 45,000 LF | $1.10 | $1.35 | $0.2394 | $11,250 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 130,000 LF | $0.8000 | $0.8800 | $0.6629 | $10,400 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $250.00 | $150.00 | $217.57 | -$10,000 |
| 533-7003 MILL RUMBLE STRIPS (CONC) (SHLDR) | 5,000 LF | $5.00 | $3.00 | $0.8732 | -$10,000 |
| 668-7001 PRFB RUMBLE STRIP (BLK)(4')(TRANSVERSE) | 400 LF | $12.50 | $35.00 | $10.44 | $9,000 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 20,000 LF | $0.6000 | $0.9900 | $0.5627 | $7,800 |
| 666-7421 REFL PAV MRK TY I (Y)6"(SLD)(060MIL) | 250,000 LF | $0.4200 | $0.4500 | $0.3278 | $7,500 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $2,250.00 | $2,500.00 | $600.85 | $6,000 |
| 666-7172 RE PM TY II (W) 6" (BRK) | 15,000 LF | $0.2200 | $0.6200 | $0.2347 | $6,000 |
| 672-7002 REFL PAV MRKR TY I-C | 6,000 EA | $5.00 | $6.00 | $4.04 | $6,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,199,788 of the $1,236,887 gap.
STRIPING TECHNOLOGY, L.P.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 45,000 LF | $1.10 | $0.2040 | 5.39x | $40,320 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $2,250.00 | $600.85 | 3.74x | $39,580 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 45,000 LF | $1.10 | $0.2394 | 4.59x | $38,727 |
| 315-7004 FOG SEAL (CSS-1H) | 4,050 GAL | $12.25 | $4.02 | 3.05x | $33,349 |
| 533-7003 MILL RUMBLE STRIPS (CONC) (SHLDR) | 5,000 LF | $5.00 | $0.8732 | 5.73x | $20,634 |
| 505-7003 TMA (MOBILE OPERATION) | 250 DAY | $100.00 | $229.60 | 0.44x | -$32,399 |
STRIPE LINES, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 315-7004 FOG SEAL (CSS-1H) | 4,050 GAL | $125.00 | $4.02 | 31.13x | $489,987 |
| 666-7175 RE PM TY II (W) 6" (SLD) | 550,000 LF | $0.6200 | $0.1701 | 3.64x | $247,445 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 550,000 LF | $0.6000 | $0.1749 | 3.43x | $233,805 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 125,000 LF | $0.9900 | $0.4757 | 2.08x | $64,288 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 45,000 LF | $1.35 | $0.2040 | 6.62x | $51,570 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 45,000 LF | $1.35 | $0.2394 | 5.64x | $49,977 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 100,000 LF | $0.9900 | $0.4986 | 1.99x | $49,140 |
| 500-7002 MOBILIZATION (CALLOUT) | 24 EA | $2,500.00 | $600.85 | 4.16x | $45,580 |
| 677-7002 ELIM EXT PM & MRKS (6") | 38,000 LF | $0.6500 | $0.2755 | 2.36x | $14,231 |
| 666-7211 RE PM TY II (Y) 6" (BRK) | 30,000 LF | $0.6000 | $0.1759 | 3.41x | $12,723 |