FY 27 Athens AO Traffic Control
6509-96-001 · let Nov 4, 2026 · Henderson, Tyler · Routine Maintenance Project - Sealed
$1,217,140Low bid: HIGHWAY 19 CONSTRUCTION LLC+2.0% vs estimate $1,193,200
$84,860Left on the table7.0% gap to the second bid
4BiddersSpread 39% low to high
18Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HIGHWAY 19 CONSTRUCTION LLC | $1,217,140 | 2.0% | $84,860 | 0 | 1-$468,850 | |
| 2 | FLEX SUPPLY, LLC | $1,302,000 | +7.0% | 9.1% | $334,100 | 1+$108,828 | 1-$497,350 |
| 3 | FC TRAFFIC CONTROL, LLC | $1,636,100 | +34.4% | 37.1% | $55,850 | 4+$414,640 | 1-$522,850 |
| 4 | AWP SAFETY | $1,691,950 | +39.0% | 41.8% | 2+$328,889 | 1-$473,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
HIGHWAY 19 CONSTRUCTION LLC vs FLEX SUPPLY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 790-7020 LANE CLOSURE(MAINTENANCE)(TYP 1) | 4,600 HR | $98.00 | $115.00 | $104.45 | $78,200 |
| 500-7001 MOBILIZATION | 1 LS | $55,000.00 | $26,500.00 | $523,850.32 | -$28,500 |
| 505-7001 TMA (STATIONARY) | 650 DAY | $345.00 | $385.00 | $217.57 | $26,000 |
| 790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5) | 800 HR | $88.00 | $112.00 | $78.14 | $19,200 |
| 7007-7002 FLAGGER CONTROL METHOD (DAY) | 200 DAY | $300.00 | $250.00 | $247.50 | -$10,000 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 320 HR | $98.00 | $115.00 | $78.09 | $5,440 |
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $1,000.00 | $100.00 | $844.81 | -$4,500 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $375.00 | $400.00 | $229.60 | $3,750 |
| 790-7058 ADDITIONAL LANE CLOSURE ITEM(TYPE 20) | 700 HR | $45.00 | $40.00 | $48.40 | -$3,500 |
| 790-7059 ADDITIONAL LANE CLOSURE ITEM(TYPE 21) | 4,000 HR | $52.00 | $52.50 | $58.00 | $2,000 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 20 DAY | $155.00 | $75.00 | $117.34 | -$1,600 |
| 7007-7001 FLAGGER CONTROL METHOD (HR) | 200 HR | $35.00 | $30.00 | $37.86 | -$1,000 |
| 790-7060 ADDITIONAL LANE CLOSURE ITEM(TYPE 22) | 40 HR | $24.00 | $5.00 | $18.58 | -$760 |
| 790-7030 LANE CLOSURE(MAINTENANCE)(TYP 11) | 20 HR | $100.00 | $80.00 | $71.51 | -$400 |
| 505-7002 TMA (MOBILE OPERATION) | 100 HR | $70.00 | $73.50 | $64.00 | $350 |
| 790-7037 LANE CLOSURE(MAINTENANCE)(TYP 18) | 30 HR | $80.00 | $90.00 | $144.65 | $300 |
| 790-7025 LANE CLOSURE(MAINTENANCE)(TYP 6) | 20 HR | $86.00 | $80.00 | $62.12 | -$120 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $20.00 | $20.00 | $87.82 | $0 |
Positive: the low bidder was cheaper on that item. These 18 items account for $84,860 of the $84,860 gap.
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $55,000.00 | $523,850.32 | 0.10x | -$468,850 |
FLEX SUPPLY, LLC: unbalanced items
Placed 2FC TRAFFIC CONTROL, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 650 DAY | $600.00 | $217.57 | 2.76x | $248,578 |
| 505-7003 TMA (MOBILE OPERATION) | 150 DAY | $800.00 | $229.60 | 3.48x | $85,560 |
| 790-7024 LANE CLOSURE(MAINTENANCE)(TYP 5) | 800 HR | $150.00 | $78.14 | 1.92x | $57,490 |
| 790-7021 LANE CLOSURE(MAINTENANCE)(TYP 2) | 320 HR | $150.00 | $78.09 | 1.92x | $23,011 |
| 500-7001 MOBILIZATION | 1 LS | $1,000.00 | $523,850.32 | 0.00x | -$522,850 |