Safety Improvement Projects
CCSJ 0001-04-109 · lets Jan 6, 2027 · El Paso, El Paso · US 85 · Hazard Elimination & Safety
$1,898,569Engineer's estimate
Items at market: $2,198,600 (+15.8%)
$1,798,002Most likely low bid$1,569,815 to $1,987,674 (middle half)
3.1Expected bidders0 plan holders, 0 regular bidders
78/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$1,798,002
Estimate $1,898,569
$1,487,724 (1 in 10 go lower)$2,358,902 (1 in 10 go higher)
From 71 comparable let jobs (district, estimates of $759,428 to $4,746,422, last 3 years). 66% of them went under the estimate; the typical low bid was -5.3% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 3.1 bidders.
- Margin10 / 20Low bids land at 95% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 6507-39-001El Paso · 6 bidders | $845,627+4.4% |
| Sep 2026 | 0001-01-075El Paso · 5 bidders | $3,622,712-4.8% |
| Sep 2026 | 6504-81-001El Paso · 3 bidders | $1,548,900-4.7% |
| Aug 2026 | 6500-72-001Culberson · 3 bidders | $1,106,900+10.8% |
| Aug 2026 | 6505-39-001El Paso · 3 bidders | $715,750-8.9% |
| Aug 2026 | 6504-80-001El Paso · 6 bidders | $1,772,400-27.1% |
| Jun 2026 | 6498-86-001El Paso · 1 bidders | $1,195,900+32.4% |
| Jun 2026 | 0924-00-162El Paso · 6 bidders | $812,410+5.6% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
128 of 134 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 23.8% |
| 527-7001 COLORED TEXTURED CONC (4")44 low bids · prices swing 14x | 2,040 SY | $92.06 | $55.00 – $775.00 | $187,799 | 8.5% |
| 531-7001 CONC SIDEWALKS (4")222 low bids · prices swing 57x | 2,220 SY | $70.57 | $21.64 – $1,237.00 | $156,655 | 7.1% |
| 529-7009 CONC CURB & GUTTER (TY II)233 low bids · prices swing 50x | 4,424 LF | $32.57 | $5.22 – $261.28 | $144,082 | 6.6% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 11 MO | $11,585.04 | $0.0010 – $273,686.48 | $127,435 | 5.8% |
| 610-7200 IN RD IL (TY SA) 50T-12 (400W EQ) LED16 low bids | 18 EA | $5,867.03 | $3,750.00 – $10,000.00 | $105,607 | 4.8% |
| 530-7006 DRIVEWAYS (CONC)295 low bids · prices swing 134x | 859 SY | $109.20 | $29.89 – $4,000.00 | $93,801 | 4.3% |
| 474-7005 SLOT DRAIN (GAL STL) (18 IN)2 low bids | 130 LF | $504.08 | $450.00 – $627.00 | $65,531 | 3.0% |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)94 low bids · prices swing 440x | 2 EA | $26,188.60 | $100.00 – $44,000.00 | $52,377 | 2.4% |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN)196 low bids · prices swing 12x | 180 LF | $270.84 | $65.00 – $778.01 | $48,752 | 2.2% |
| 465-7021 INLET (COMPL)(PCO)(5FT)(NONE)15 low bids | 5 EA | $9,252.16 | $5,120.00 – $14,056.92 | $46,261 | 2.1% |
| 104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP)224 low bids · prices swing 203x | 1,835 SY | $17.88 | $3.00 – $607.87 | $32,808 | 1.5% |
| 104-7017 REMOV CONC (CURB & GUTTER)138 low bids · prices swing 125x | 3,709 LF | $8.04 | $1.00 – $125.00 | $29,822 | 1.4% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 133 DAY | $217.57 | $0.0010 – $16,487.00 | $28,937 | 1.3% |
| 618-7054 CONDT (PVC) (SCH 80) (2")207 low bids · prices swing 34x | 2,380 LF | $12.03 | $3.00 – $103.38 | $28,640 | 1.3% |