Rigid Pavement Repair EAO/VH
6504-80-001 · let Aug 5, 2026 · El Paso, El Paso · Routine Maintenance Project
$1,772,400Low bid: WINDING ROAD CONSTRUCTION, INC.-27.1% vs estimate $2,430,000
$396,150Left on the table22.4% gap to the second bid
6BiddersSpread 59% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | WINDING ROAD CONSTRUCTION, INC. | $1,772,400 | -27.1% | $396,150 | 5+$727,499 | 1-$353,850 | |
| 2 | SYNERGY PROJECT CONTRACTORS, INC. | $2,168,550 | +22.4% | -10.8% | $37,500 | 1+$1,267,634 | 1-$517,750 |
| 3 | O. TREVINO CONSTRUCTION, LLC | $2,206,050 | +24.5% | -9.2% | $4,200 | 4+$1,138,265 | 1-$313,850 |
| 4 | DAN WILLIAMS COMPANY | $2,210,250 | +24.7% | -9.0% | $344,750 | 3+$1,146,077 | 1-$323,850 |
| 5 | HAWK CONSTRUCTION | $2,555,000 | +44.2% | 5.1% | $265,808 | 6+$1,696,472 | 1-$518,850 |
| 6 | ALLIED PAVING CO. | $2,820,808 | +59.2% | 16.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
WINDING ROAD CONSTRUCTION, INC. vs SYNERGY PROJECT CONTRACTORS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 600 CY | $2,224.00 | $3,324.50 | $1,211.78 | $660,300 |
| 500-7001 MOBILIZATION | 1 LS | $170,000.00 | $6,100.00 | $523,850.32 | -$163,900 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 3 EA | $15,000.00 | $1,220.00 | $599.93 | -$41,340 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 100 CF | $625.00 | $292.80 | $206.00 | -$33,220 |
| 505-7001 TMA (STATIONARY) | 250 DAY | $250.00 | $378.20 | $217.57 | $32,050 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 200 SF | $225.00 | $91.50 | $153.06 | -$26,700 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $2,300.00 | $122.00 | $87.82 | -$21,780 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 200 SF | $150.00 | $103.70 | $85.28 | -$9,260 |
Positive: the low bidder was cheaper on that item. These 8 items account for $396,150 of the $396,150 gap.
WINDING ROAD CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 600 CY | $2,224.00 | $1,211.78 | 1.84x | $607,334 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 3 EA | $15,000.00 | $599.93 | 25.00x | $43,200 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 100 CF | $625.00 | $206.00 | 3.03x | $41,900 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $2,300.00 | $87.82 | 26.19x | $22,122 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 200 SF | $150.00 | $85.28 | 1.76x | $12,943 |
| 500-7001 MOBILIZATION | 1 LS | $170,000.00 | $523,850.32 | 0.32x | -$353,850 |
SYNERGY PROJECT CONTRACTORS, INC.: unbalanced items
Placed 2O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 600 CY | $3,017.00 | $1,211.78 | 2.49x | $1,083,134 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 200 SF | $282.00 | $153.06 | 1.84x | $25,788 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 200 SF | $166.00 | $85.28 | 1.95x | $16,143 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 3 EA | $5,000.00 | $599.93 | 8.33x | $13,200 |
| 500-7001 MOBILIZATION | 1 LS | $210,000.00 | $523,850.32 | 0.40x | -$313,850 |
DAN WILLIAMS COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 600 CY | $3,045.00 | $1,211.78 | 2.51x | $1,099,934 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 3 EA | $10,000.00 | $599.93 | 16.67x | $28,200 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 200 SF | $175.00 | $85.28 | 2.05x | $17,943 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
HAWK CONSTRUCTION: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 600 CY | $3,460.00 | $1,211.78 | 2.86x | $1,348,934 |
| 505-7001 TMA (STATIONARY) | 250 DAY | $1,128.00 | $217.57 | 5.18x | $227,607 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 100 CF | $650.00 | $206.00 | 3.16x | $44,400 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 200 SF | $250.00 | $85.28 | 2.93x | $32,943 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 200 SF | $300.00 | $153.06 | 1.96x | $29,388 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 3 EA | $5,000.00 | $599.93 | 8.33x | $13,200 |
| 500-7001 MOBILIZATION | 1 LS | $5,000.00 | $523,850.32 | 0.01x | -$518,850 |