FY 2026 BRIDGE MAINT (DISTRICTWIDE)
0924-00-162 · let Jun 2, 2026 · El Paso, El Paso · Bridge Maintenance
$812,410Low bid: RAGLE CONSTRUCTION, INC.+5.6% vs estimate $769,257
$207,821Left on the table25.6% gap to the second bid
6BiddersSpread 56% low to high
33Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RAGLE CONSTRUCTION, INC. | $812,410 | 5.6% | $207,821 | 3+$246,187 | 3-$453,667 | |
| 2 | PREMIER CONTRACTORS LLC | $1,020,230 | +25.6% | 32.6% | $54,916 | 11+$327,175 | 3-$535,495 |
| 3 | HAWK CONSTRUCTION | $1,075,146 | +32.3% | 39.8% | $58,515 | 13+$387,543 | 1-$501,850 |
| 4 | INTERNATIONAL EAGLE ENTERPRISES, INC. | $1,133,661 | +39.5% | 47.4% | $10,257 | 8+$470,424 | 1-$493,850 |
| 5 | GIBSON & ASSOCIATES, INC. | $1,143,917 | +40.8% | 48.7% | $124,351 | 8+$353,492 | 1-$361,850 |
| 6 | THE TRUESDELL CORPORATION | $1,268,268 | +56.1% | 64.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
RAGLE CONSTRUCTION, INC. vs PREMIER CONTRACTORS LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 785-7011 BRIDGE JOINT REPLACEMENT (SEJ) | 223 LF | $320.00 | $1,200.00 | $634.97 | $196,240 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $52,750.00 | $1.00 | $11,585.04 | -$158,247 |
| 439-7021 POLYESTER POLYMER CONC OVERLAY (1") | 1,172 SY | $150.00 | $250.00 | $158.64 | $117,200 |
| 480-7001 CLEAN EXIST CULVERTS | 1 EA | $119,000.00 | $10,000.00 | $1,712.97 | -$109,000 |
| 786-7002 CARBON FIBER REINF POLYMER STRENGTHNING | 252.5 SF | $75.00 | $250.00 | $50.56 | $44,188 |
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $40,000.00 | $523,850.32 | -$40,000 |
| 785-7008 BRIDGE JOINT REPAIR (PARTIAL DEPTH) | 57 LF | $185.00 | $800.00 | $254.54 | $35,055 |
| 439-7016 POLYESTER POLYMER CONC OVERLAY (1-1/2") | 308 SY | $200.00 | $300.00 | $186.40 | $30,800 |
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 394 LF | $30.00 | $100.00 | $46.07 | $27,580 |
| 505-7001 TMA (STATIONARY) | 78 DAY | $350.00 | $1.00 | $217.57 | -$27,222 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 717 LF | $23.00 | $50.00 | $15.92 | $19,359 |
| 483-7016 SHOT BLASTING | 1,172 SY | $4.00 | $20.00 | $5.25 | $18,752 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 106 SF | $150.00 | $300.00 | $150.68 | $15,900 |
| 427-7002 CONCRETE PAINT FINISH | 384 SF | $15.00 | $40.00 | $0.9252 | $9,600 |
| 5008-7001 BIRD DETERRENT | 159 LF | $20.00 | $70.00 | $46.93 | $7,950 |
| 429-7009 CONC STR REPAIR (STANDARD) | 24 SF | $175.00 | $500.00 | $146.35 | $7,800 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 6 EA | $850.00 | $2,000.00 | $475.41 | $6,900 |
| 785-7007 BRIDGE JOINT REPAIR (FULL DEPTH) | 8 LF | $210.00 | $1,000.00 | $901.98 | $6,320 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $250.00 | $1.00 | $87.82 | -$4,980 |
| 442-7017 MISC NON-BRIDGE (NBIS) | 6 LB | $205.00 | $500.00 | $47.98 | $1,770 |
Positive: the low bidder was cheaper on that item. These 20 items account for $205,965 of the $207,821 gap.
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $52,750.00 | $11,585.04 | 4.55x | $123,495 |
| 480-7001 CLEAN EXIST CULVERTS | 1 EA | $119,000.00 | $1,712.97 | 69.47x | $117,287 |
| 427-7002 CONCRETE PAINT FINISH | 384 SF | $15.00 | $0.9252 | 16.21x | $5,405 |
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $523,850.32 | 0.15x | -$443,850 |
| 785-7007 BRIDGE JOINT REPAIR (FULL DEPTH) | 8 LF | $210.00 | $901.98 | 0.23x | -$5,536 |
| 5008-7001 BIRD DETERRENT | 159 LF | $20.00 | $46.93 | 0.43x | -$4,281 |
PREMIER CONTRACTORS LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 785-7011 BRIDGE JOINT REPLACEMENT (SEJ) | 223 LF | $1,200.00 | $634.97 | 1.89x | $126,002 |
| 786-7002 CARBON FIBER REINF POLYMER STRENGTHNING | 252.5 SF | $250.00 | $50.56 | 4.94x | $50,358 |
| 785-7008 BRIDGE JOINT REPAIR (PARTIAL DEPTH) | 57 LF | $800.00 | $254.54 | 3.14x | $31,091 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 717 LF | $50.00 | $15.92 | 3.14x | $24,437 |
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 394 LF | $100.00 | $46.07 | 2.17x | $21,249 |
| 483-7016 SHOT BLASTING | 1,172 SY | $20.00 | $5.25 | 3.81x | $17,283 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 106 SF | $300.00 | $150.68 | 1.99x | $15,828 |
| 427-7002 CONCRETE PAINT FINISH | 384 SF | $40.00 | $0.9252 | 43.23x | $15,005 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 6 EA | $2,000.00 | $475.41 | 4.21x | $9,148 |
| 429-7009 CONC STR REPAIR (STANDARD) | 24 SF | $500.00 | $146.35 | 3.42x | $8,488 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $523,850.32 | 0.08x | -$483,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1.00 | $11,585.04 | 0.00x | -$34,752 |
| 505-7001 TMA (STATIONARY) | 78 DAY | $1.00 | $217.57 | 0.00x | -$16,893 |
HAWK CONSTRUCTION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7001 CLEAN EXIST CULVERTS | 1 EA | $103,000.00 | $1,712.97 | 60.13x | $101,287 |
| 439-7016 POLYESTER POLYMER CONC OVERLAY (1-1/2") | 308 SY | $372.50 | $186.40 | 2.00x | $57,319 |
| 483-7016 SHOT BLASTING | 1,172 SY | $38.50 | $5.25 | 7.33x | $38,965 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 308 SY | $125.00 | $4.21 | 29.67x | $37,203 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 717 LF | $56.50 | $15.92 | 3.55x | $29,098 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 106 SF | $405.00 | $150.68 | 2.69x | $26,958 |
| 786-7002 CARBON FIBER REINF POLYMER STRENGTHNING | 252.5 SF | $138.00 | $50.56 | 2.73x | $22,078 |
| 785-7008 BRIDGE JOINT REPAIR (PARTIAL DEPTH) | 57 LF | $579.00 | $254.54 | 2.27x | $18,494 |
| 505-7001 TMA (STATIONARY) | 78 DAY | $410.00 | $217.57 | 1.88x | $15,009 |
| 429-7009 CONC STR REPAIR (STANDARD) | 24 SF | $762.00 | $146.35 | 5.21x | $14,776 |
| 500-7001 MOBILIZATION | 1 LS | $22,000.00 | $523,850.32 | 0.04x | -$501,850 |
INTERNATIONAL EAGLE ENTERPRISES, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 439-7021 POLYESTER POLYMER CONC OVERLAY (1") | 1,172 SY | $350.00 | $158.64 | 2.21x | $224,271 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 308 SY | $300.00 | $4.21 | 71.22x | $91,103 |
| 439-7016 POLYESTER POLYMER CONC OVERLAY (1-1/2") | 308 SY | $432.00 | $186.40 | 2.32x | $75,645 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 106 SF | $350.00 | $150.68 | 2.32x | $21,128 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 717 LF | $45.00 | $15.92 | 2.83x | $20,852 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 6 EA | $3,000.00 | $475.41 | 6.31x | $15,148 |
| 785-7008 BRIDGE JOINT REPAIR (PARTIAL DEPTH) | 57 LF | $500.00 | $254.54 | 1.96x | $13,991 |
| 480-7001 CLEAN EXIST CULVERTS | 1 EA | $10,000.00 | $1,712.97 | 5.84x | $8,287 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
GIBSON & ASSOCIATES, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7001 CLEAN EXIST CULVERTS | 1 EA | $166,000.00 | $1,712.97 | 96.91x | $164,287 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $32,600.00 | $11,585.04 | 2.81x | $63,045 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 717 LF | $67.00 | $15.92 | 4.21x | $36,626 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 106 SF | $470.00 | $150.68 | 3.12x | $33,848 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 308 SY | $63.23 | $4.21 | 15.01x | $18,177 |
| 483-7016 SHOT BLASTING | 1,172 SY | $20.50 | $5.25 | 3.90x | $17,869 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 6 EA | $2,400.00 | $475.41 | 5.05x | $11,548 |
| 427-7002 CONCRETE PAINT FINISH | 384 SF | $22.00 | $0.9252 | 23.78x | $8,093 |
| 500-7001 MOBILIZATION | 1 LS | $162,000.00 | $523,850.32 | 0.31x | -$361,850 |