WAO Sweeping & Debris Removal
6505-39-001 · let Aug 12, 2026 · El Paso, El Paso · Routine Maintenance Project
$715,750Low bid: E. G. L. CONSTRUCTION, INC.-8.9% vs estimate $785,975
$260,670Left on the table36.4% gap to the second bid
3BiddersSpread 123% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | E. G. L. CONSTRUCTION, INC. | $715,750 | -8.9% | $260,670 | 2+$12,817 | 0 | |
| 2 | SWEEPING CORPORATION OF AMERICA, LLC | $976,420 | +36.4% | 24.2% | $622,280 | 3+$503,297 | 1-$117,236 |
| 3 | DOUBLE H CONTRACTING INC. | $1,598,700 | +123.4% | 103.4% | 7+$995,836 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
E. G. L. CONSTRUCTION, INC. vs SWEEPING CORPORATION OF AMERICA, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 738-7001 CLEANING / SWEEPING (CENTER MEDIAN) | 1,000 MI | $220.00 | $440.00 | $187.45 | $220,000 |
| 738-7025 CLEANING / SWEEPING (OUTSIDE MAIN LANE) | 1,000 MI | $230.00 | $440.00 | $197.36 | $210,000 |
| 505-7003 TMA (MOBILE OPERATION) | 730 DAY | $275.00 | $69.00 | $229.60 | -$150,380 |
| 738-7049 CLEANING / SWEEPING (FRONTAGE ROAD) | 200 MI | $200.00 | $140.00 | $175.99 | -$12,000 |
| 738-7104 CLEANING / SWEEPING (SPOT) | 10 MI | $1,000.00 | $85.00 | $109.57 | -$9,150 |
| 738-7091 CLEANING / SWEEPING (DIRECT CONNECTOR) | 30 MI | $300.00 | $440.00 | $169.58 | $4,200 |
| 738-7105 CLEANING / SWEEPING (HANDWORK) | 500 SY | $4.50 | $1.00 | $0.1919 | -$1,750 |
| 738-7070 CLEANING / SWEEPING(ENTRANCE/EXIT RAMP) | 25 MI | $150.00 | $140.00 | $162.48 | -$250 |
Positive: the low bidder was cheaper on that item. These 8 items account for $260,670 of the $260,670 gap.
E. G. L. CONSTRUCTION, INC.: unbalanced items
Placed 1SWEEPING CORPORATION OF AMERICA, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 738-7001 CLEANING / SWEEPING (CENTER MEDIAN) | 1,000 MI | $440.00 | $187.45 | 2.35x | $252,549 |
| 738-7025 CLEANING / SWEEPING (OUTSIDE MAIN LANE) | 1,000 MI | $440.00 | $197.36 | 2.23x | $242,635 |
| 738-7091 CLEANING / SWEEPING (DIRECT CONNECTOR) | 30 MI | $440.00 | $169.58 | 2.59x | $8,113 |
| 505-7003 TMA (MOBILE OPERATION) | 730 DAY | $69.00 | $229.60 | 0.30x | -$117,236 |
DOUBLE H CONTRACTING INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 730 DAY | $690.00 | $229.60 | 3.01x | $336,094 |
| 738-7001 CLEANING / SWEEPING (CENTER MEDIAN) | 1,000 MI | $450.00 | $187.45 | 2.40x | $262,549 |
| 738-7025 CLEANING / SWEEPING (OUTSIDE MAIN LANE) | 1,000 MI | $450.00 | $197.36 | 2.28x | $252,635 |
| 738-7049 CLEANING / SWEEPING (FRONTAGE ROAD) | 200 MI | $600.00 | $175.99 | 3.41x | $84,803 |
| 738-7091 CLEANING / SWEEPING (DIRECT CONNECTOR) | 30 MI | $1,500.00 | $169.58 | 8.85x | $39,913 |
| 738-7070 CLEANING / SWEEPING(ENTRANCE/EXIT RAMP) | 25 MI | $600.00 | $162.48 | 3.69x | $10,938 |
| 738-7104 CLEANING / SWEEPING (SPOT) | 10 MI | $1,000.00 | $109.57 | 9.13x | $8,904 |