21Let jobs
$28,726,857Total low bids
$24,067,794Total estimates
+19.4%Low bids vs estimates
Sep 2019 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Sep 19, 2019 | 190278NHPPI-4000(073)PM | Custer Division 5 |
RESURFACE (ASPHALT ), BRIDGE REHABILITATION , AND CABLE BARRIER I-40: FROM 7.1 MILES WEST OF US -183, EXTEND EAST NEAR CLINTON . PROJECT LENGTH = 5.352 MILES · | $8,400,213 | $8,606,210 | CASWELL CONSTRUCTION, INC. | +2.5% | 1 |
| Sep 19, 2019 | 190216NHPPI-0035(297)SS | Mcclain Division 3 |
GRADE, DRAIN, AND SURFACE I -35: FROM 0.5 MILES NORTHWEST OF SH -74, EXTEND SOUTHEAST IN GOLDSBY. PROJECT LENGTH = 1.065 MILES · | $4,642,822 | $4,792,565 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) | +3.2% | 3 |
| Sep 19, 2019 | 190272STP-202C(037)CI | Alfalfa Division 6 |
GRADE, DRAIN, AND SURFACE COUNTY ROAD (EW-33): FROM THE SH -45 JUNCTION, EXTEND EAST IN GOLTRY . PROJECT LENGTH = 2.798 MILES · | $2,424,850 | $2,703,544 | THE CUMMINS CONSTRUCTION CO., INC. | +11.5% | 2 |
| Sep 19, 2019 | 190290CIRB-248D(039)RB | Marshall Division 2 |
RESURFACE (ASPHALT ) COUNTY ROAD (POWELL ROAD ): FROM 0.2 MILES SOUTH OF THE SH -32 JUNCTION, EXTEND SOUTH, THEN EAST NEAR LEBANON . PROJECT LENGTH = 4.979 MILES · | — | $1,628,786 | OVERLAND CORPORATION | 2 | |
| Sep 19, 2019 | 190285HSIPG-226N(067)TR | Grady Division 7 |
SAFETY IMPROVEMENT (CABLE BARRIER) US-81: FROM THE STEPHENS COUNTY LINE , EXTEND NORTH NEAR RUSH SPRINGS . PROJECT LENGTH = 7.07 MILES · | $1,502,742 | $1,570,196 | ACTION SAFETY SUPPLY CO., LLC | +4.5% | 4 |
| Sep 19, 2019 | 190225NHPPI-4000-(082)3P | Oklahoma Division 4 |
RESURFACE (ASPHALT ) I-40: FROM THE I -35 INTERCHANGE, EXTEND SOUTHEAST IN DEL CITY . PROJECT LENGTH = 2.64 MILES · | — | $1,419,438 | T.J. CAMPBELL CONSTRUCTION COMPANY | 3 | |
| Sep 19, 2019 | 190301STP-272F(276)3B | Tulsa Division 8 |
JOINT SEAL /REPAIR I -44/CITY STREET (ADMIRAL PLACE ): AT MULTIPLE LOCATIONS IN DIVISION VIII. PROJECT LENGTH = 0.00 MILE · | $889,503 | $1,048,323 | PBX Corporation | +17.9% | 4 |
| Sep 19, 2019 | 190222STP-252F(055)PM | Noble, Oklahoma |
BRIDGE PAINTING US -62/CITY STREETS ('A' AVENUE /POLE YARD ROAD /POST ROAD ): AT MULTIPLE LOCATIONS IN DIVISION IV. PROJECT LENGTH = 0.00 MILE · | $1,192,720 | $865,860 | POSEIDON CONSTRUCTION, INC. | -27.4% | 8 |
| Sep 19, 2019 | 190295STP-255F(501)3B | Oklahoma Division 4 |
JOINT SEAL /REPAIR I -35/US-77 NB/CITY STREETS (SOONER ROAD SB/WESTERN AVENUE ): AT MULTIPLE LOCATIONS IN DIVISION IV. PROJECT LENGTH = 0.00 MILE · | $710,860 | $814,539 | Built Right Construction, LLC | +14.6% | 2 |
| Sep 19, 2019 | 190302STP-275F(050)3B | Washita Division 5 |
JOINT SEAL /REPAIR US -183 SB/SH-152: AT MULTIPLE LOCATIONS IN DIVISION V. PROJECT LENGTH = 0.00 MILE · | $667,037 | $739,398 | Built Right Construction, LLC | +10.8% | 3 |
| Sep 19, 2019 | 190242HSIPG-212N(045)AD | Choctaw Division 2 |
PEDESTRIAN IMPROVEMENT (SIDEWALKS ) US-70B: FROM 0.8 MILES NORTHWEST OF THE US -70 JUNCTION, EXTEND WEST IN HUGO . PROJECT LENGTH = 0.399 MILE · | $528,987 | $656,226 | HUB Construction, Inc. | +24.1% | 2 |
| Sep 19, 2019 | 190299STP-269F(060)3B | Stephens Division 7 |
JOINT SEAL /REPAIR US -81/SH-7 EB: US-81, OVER CLARIDY CREEK 5.9 MI N OF SH-53.SH-7 EB, OVER US-81 0.8 MI S OF SH-7A IN DUNCAN. PROJECT LENGTH = 0.00 MILE · | $569,020 | $642,011 | LOGOS CONSTRUCTION CO., LLC | +12.8% | 2 |
| Sep 19, 2019 | 190337E-SAP-4400(060)ES | Tulsa Division 8 |
BRIDGE REPAIR US -169: REPAIR VEHICLE IMPACT DAMAGE OVER I-44, 2.7 MILES EAST OF THE SH-51 JUNCTION IN TULSA . PROJECT LENGTH = 0.000 MILE · | $283,714 | $587,000 | BECCO CONTRACTORS, INC. | +106.9% | 2 |
| Sep 19, 2019 | 190224STP-255C(487)CO | Oklahoma Division 4 |
BRIDGE AND APPROACHES COUNTY ROAD (WATERLOO RD ): OVER TRIBUTARY TO BLOODY RUSH CREEK, 0.5 MILES WEST OF THE SH -74 JUNCTION NEAR EDMOND. PROJECT LENGTH = 0.123 MILE · | $612,550 | $577,710 | Silver Star Construction Company, Inc. | -5.7% | 10 |
| Sep 19, 2019 | 190291STP-244F(067)3B | Cleveland, Coal, Garvin, Lincoln, Mcclain, Pontotoc, Pottawa |
JOINT SEAL /REPAIR US -75/US-377/SH-19/SH-24/SH-31/SH-39/SH-56/SH-59/SH-74B/ SH-99/SH-102: AT MULTIPLE LOCATIONS IN DIVISION III. PROJECT LENGTH = 0.00 MILE · | $498,221 | $435,366 | B & B CONSTRUCTION SERVICE J.T., INC. | -12.6% | 5 |
| Sep 19, 2019 | 180071HSIPG-272F(180)TR | Tulsa Division 8 |
TRAFFIC SIGNING INTERSTATES /US HWYS/STATE HWYS /CITY STREETS : AT MULTIPLE LOCATIONS IN THE CITY OF TULSA. PROJECT LENGTH = 0.00 MILE · | — | $383,769 | ACTION SAFETY SUPPLY CO., LLC | 3 | |
| Sep 19, 2019 | 190292NHPP-NBIP(530)3B | Mcintosh Division 1 |
BRIDGE PAINTING COUNTY ROADS (E1080 ROAD/E1090 ROAD/ONAPA ROAD ): OVER US-69, 0.7 MI, 1.7 MI, AND 3.8 MI SOUTH OF THE I -40 JUNCTION. PROJECT LENGTH = 0.00 MILE · | $476,810 | $383,630 | POSEIDON CONSTRUCTION, INC. | -19.5% | 10 |
| Sep 19, 2019 | 190298HSIPG-269N(050)AD | Stephens Division 7 |
PEDESTRIAN IMPROVEMENTS (SIDEWALKS ) US-81 (BROADWAY STREET ): FROM CHICKASAW AVENUE , EXTEND NORTH IN MARLOW . PROJECT LENGTH = 0.372 MILE · | $238,910 | $320,729 | TOM HUDSON PAVING, INC. | +34.2% | 2 |
| Sep 19, 2019 | 190276STP-NBIP(531)3B | Cleveland, Lincoln, Pottawatomie |
BRIDGE PAINTING US -270 SB/US-377/SH-99/CITY STREET (ROBINSON STREET): AT MULTIPLE LOCATIONS IN DIVISION III. PROJECT LENGTH = 0.00 MILE · | $237,746 | $242,005 | POSEIDON CONSTRUCTION, INC. | +1.8% | 7 |
| Sep 19, 2019 | 190296STP-257C(076)RW | Osage Division 8 |
RIGHT-OF-WAY CLEARANCE SH-20: FROM THE SH -99 JUNCTION, EXTEND SOUTHEAST NEAR HOMINY. PROJECT LENGTH = 5.016 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED . · | — | $157,600 | Robin Hausner Demolition, LLC | 1 | |
| Sep 19, 2019 | 190306STP-276F(036)3B | Major, Woods |
JOINT SEAL /REPAIR US -281/US-412: AT MULTIPLE LOCATIONS IN DIVISION VI. PROJECT LENGTH - 0.00 MILE · | $191,090 | $151,953 | RESTEK, INC. | -20.5% | 5 |