RIGHT-OF-WAY CLEARANCE SH-20: FROM THE SH -99 JUNCTION, EXTEND SOUTHEAST NEAR HOMINY. PROJECT LENGTH = 5.016 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Let date
- Thursday, September 19, 2019
- Contract
- 190296
- J/P numbers
- 24268(08)
- District
- Division 8
- County
- Osage
- Highway
- Limits
- RIGHT-OF-WAY CLEARANCE SH-20: FROM THE SH -99 JUNCTION, EXTEND SOUTHEAST NEAR HOMINY. PROJECT LENGTH = 5.016 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED .
- Project number
- STP-257C(076)RW
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Robin Hausner Demolition, LLC Low bidder | $157,600 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Robin Hausner D… |
|---|---|---|---|---|---|---|
| 1 | 233(A) 2817 | VEGETATIVE MULCHING | 1 | AC | $5,000.00 | $100.00 |
| 2 | 619(G) 0094 | RIGHT-OF-WAY CLEARANCE | 1 | LSUM | $173,384.00 | $155,500.00 |
| 3 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $2,500.00 | $1,500.00 |
| 4 | 641 1552 | MOBILIZATION | 1 | LSUM | $7,000.00 | $500.00 |