ODOT Bid Results

Aug 2019 · 14 let jobs Sign up free
14Let jobs
$44,773,624Total low bids
$34,309,958Total estimates
+30.5%Low bids vs estimates

Aug 2019 results

Bid tabs (Excel) ExcelCSV
Let dateContractCounty / DistrictProject EstimateLow bidLow bidder% vs est.Bidders
Aug 22, 2019 190238NHPP-017N(254)PM Blaine
Division 5
GRADE, DRAIN, AND SURFACE SH -3: FROM 1.0 MILE EAST OF THE US -270 JUNCTION, EXTEND EAST IN WATONGA . PROJECT LENGTH = 4.109 MILES · $8,512,045 $9,866,476 THE CUMMINS CONSTRUCTION CO., INC. +15.9% 3
Aug 22, 2019 190262STP-272B(258)IG Tulsa
Division 8
GRADE, DRAIN, AND SURFACE CITY STREET (NORTH GARNETT ROAD ): FROM EAST 96TH STREET NORTH , EXTEND NORTH IN THE CITY OF OWASSO . PROJECT LENGTH = 0.870 MILE · — $8,897,000 BECCO CONTRACTORS, INC. 5
Aug 22, 2019 190257STP-268C(056)CI Sequoyah
Division 1
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (DWIGHT MISSION /SEQUOYAH LANDING ROAD): FROM I-40, EXTEND NORTH NEAR SALLISAW . PROJECT LENGTH = 5.555 MILES · $8,253,255 $8,848,046 JOB CONSTRUCTION CO., INC. +7.2% 2
Aug 22, 2019 190271STP-172B(484)IG Tulsa
Division 8
GRADE, DRAIN, AND SURFACE CITY STREET (MAIN STREET): FROM SH-97 (WILSON AVENUE ), EXTEND EAST THEN NORTH IN THE CITY OF SAND SPRINGS . PROJECT LENGTH = 1.230 MILES · $7,479,992 $7,755,557 Paragon Contractors, LLC +3.7% 5
Aug 22, 2019 190243STP-219B(071)PM Creek
Division 8
PAVEMENT REHABILITATION (ASPHALT ) SH-48: FROM 2.0 MILES NORTH OF THE SH -33 JUNCTION, EXTEND NORTH NEAR MANNFORD . PROJECT LENGTH = 6.318 MILES · $3,676,464 $3,329,000 BECCO CONTRACTORS, INC. -9.5% 6
Aug 22, 2019 190259SSP-272F(268)SS Tulsa
Division 8
BRIDGE PAINTING I -44/US-75 NB/CITY STREETS (YALE AVE/PITTSBURG AVE /HARVARD AVE/MEMORIAL RD ): AT MULTIPLE LOCATIONS IN DIVISION VIII. PROJECT LENGTH = 0.00 MILE · $1,889,027 $1,489,640 JK INDUSTRIES, INC. -21.1% 9
Aug 22, 2019 190254CIRB-261C(089)RB Pittsburg
Division 2
RESURFACE (ASPHALT ) COUNTY ROAD (ASHLAND ROAD): FROM THE SH -31 JUNCTION, EXTEND EAST IN ASHLAND . PROJECT LENGTH = 4.000 MILES · $1,519,318 $1,297,565 Rosscon, LLC -14.6% 4
Aug 22, 2019 190245STP-223C(019)CI Ellis
Division 6
BRIDGE AND APPROACHES COUNTY ROAD (EW-36): OVER DRY PRONG CREEK , 2.5 MILES EAST OF THE TEXAS STATE LINE NEAR CATESBY. PROJECT LENGTH = 0.189 MILE · $648,429 $842,048 Wyatt Contracting +29.9% 7
Aug 22, 2019 190244STP-220C(067)CI Custer
Division 5
BRIDGE AND APPROACHES COUNTY ROAD (EW-099): OVER BARNITZ CREEK, 4.5 MILES WEST OF THE US-183 JUNCTION NEAR ARAPAHO . PROJECT LENGTH = 0.161 MILE · $770,264 $821,182 SEWELL BROS., INC. +6.6% 5
Aug 22, 2019 190261SSP-272F(269)SS Washington
Division 8
JOINT SEAL /REPAIR US -75: OVER CANEY RIVER O 'FLOW, NORTH AND SOUTH FORK DOUBLE CREEK, AND SK &O RAILROAD IN DIVISIONS VIII. PROJECT LENGTH - 0.00 MILE · $440,315 $509,147 PBX Corporation +15.6% 3
Aug 22, 2019 190250STP-255D(499)CO Oklahoma
Division 4
BRIDGE AND APPROACHES COUNTY ROAD (BRITTON ROAD ): OVER TRIBUTARY OF NORTH CANADIAN RIVER, 11.3 MILES EAST OF I -35 IN JONES. PROJECT LENGTH = 0.133 MILE · $616,751 $508,497 Wyatt Contracting -17.6% 9
Aug 22, 2019 190258STP-271D(065)CI Tillman
Division 5
BRIDGE AND APPROACHES COUNTY ROAD (EW-190): OVER BOTTLE CREEK, 0.2 MILES EAST OF THE US-183 JUNCTION NEAR DAVIDSON . PROJECT LENGTH = 0.121 MILE · $362,313 $368,794 Wyatt Contracting +1.8% 7
Aug 22, 2019 190260SSP-272F(267)SS Creek, Ottawa, Pawnee, Rogers, Tulsa
BRIDGE WATER PROOF SEAL US -64/US-75/US-412EB/SH-10/SH-11/SH-51/HARVARD AVE /PITTSBURG AVE/YALE AVE: AT MULTIPLE LOCATIONS IN DIVISION VIII. PROJECT LENGTH = 0.00 MILES · $141,785 $136,505 LOGOS CONSTRUCTION CO., LLC -3.7% 2
Aug 22, 2019 190246SSP-011N(106)RW Grady
Division 7
RIGHT-OF-WAY CLEARANCE PROPOSED US-81 REALIGNMENT: FROM 1.0 MILE NORTH OF THE US-277 JUNCTION, EXTEND NORTH IN CHICKASHA . PROJECT LENGTH = 8.310 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTED · — $104,168 M & M WRECKING, INC. 2
1–14 of 14

Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.