26Let jobs
$29,395,920Total low bids
$26,873,278Total estimates
+9.4%Low bids vs estimates
Oct 2017 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Oct 19, 2017 | 170322CIRB-143C(091)RB | Love Division 7 |
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (OSWALT ROAD /EW-206): FROM SH-76, EXTEND EAST NEAR ARDMORE . PROJECT LENGTH = 6.025 MILES · | $7,732,098 | $6,583,798 | OVERLAND CORPORATION | -14.9% | 4 |
| Oct 19, 2017 | 170328HSIPIG-3500(044)TR | Cleveland, Oklahoma |
TRAFFIC SIGNING I-35: FROM ROBINSON AVENUE , EXTEND NORTH IN NORMAN , MOORE, OKLAHOMA CITY AND EDMOND . · | — | $3,100,572 | ACTION SAFETY SUPPLY CO., LLC | 2 | |
| Oct 19, 2017 | 170295ACNHPP-272N(200)SS | Tulsa Division 8 |
BRIDGE REHABILITATION US -64: OVER 97TH W. AVENUE (ADAMS ROAD), 0.8 MILES EAST OF THE SH-97 JUNCTION IN SAND SPRINGS. PROJECT LENGTH = 0.082 MILE · | $3,272,542 | $3,067,000 | BECCO CONTRACTORS, INC. | -6.3% | 5 |
| Oct 19, 2017 | 170313STP-214C(080)AG | Cleveland Division 3 |
GRADE, DRAIN, AND SURFACE CITY STREET (12TH AVENUE SE ): FROM 0.4 MILES SOUTH OF SH-9, EXTEND NORTH IN THE CITY OF NORMAN . PROJECT LENGTH = 0.530 MILE · | $2,811,557 | $2,794,654 | Allen Contracting, Inc. | -0.6% | 4 |
| Oct 19, 2017 | 170338SBR-272N(230)SB | Tulsa Division 8 |
BRIDGE REHABILITATION SH -51 NORTHBOUND : OVER ARKANSAS RIVER , 0.4 MILES NORTH OF THE SH-97 JUNCTION IN SAND SPRINGS. · | $2,995,135 | $2,307,462 | PBX Corporation | -23.0% | 3 |
| Oct 19, 2017 | 170341SEC1934-272C(223)TI | Tulsa Division 8 |
TRAFFIC SIGNALS CITY STREETS: AT MULTIPLE LOCATIONS IN THE CITY OF TULSA. · | $1,779,772 | $1,974,263 | TRAFFIC & LIGHTING SYSTEMS, LLC | +10.9% | 3 |
| Oct 19, 2017 | 170334HSIPG-260B(031)AD | Stpy-260b(035)3p |
PAYNE PEDESTRIAN IMPROVEMENTS (SIDEWALKS ) AND RESURFACE (ASPHALT ) US-177: FROM 1.0 MILE SOUTH OF SH-33, EXTEND NORTH IN PERKINS . PROJECT LENGTH = 0.500 MILE · | $1,495,640 | $1,458,200 | CROSSLAND HEAVY CONTRACTORS INC. | -2.5% | 4 |
| Oct 19, 2017 | 170307HSIPG-013N(165)TR | Bryan, Pittsburg |
TRAFFIC SIGNING US-69: AT MULTIPLE LOCATIONS IN DIVISION II. · | — | $940,073 | ACTION SAFETY SUPPLY CO., LLC | 4 | |
| Oct 19, 2017 | 170312STP-114E(258)EH | Cleveland Division 3 |
ENHANCEMENT (TRAIL CONSTRUCTION ) SH-9: FROM 24TH AVENUE , EXTEND EAST IN THE CITY OF NORMAN. PROJECT LENGTH = 1.100 MILES · | — | $649,900 | RDNJ, INC. DBA A-TECH PAVING | 6 | |
| Oct 19, 2017 | 170337STP-172E(538)EH | Tulsa Division 8 |
ENHANCEMENT (TRAIL CONSTRUCTION ) CITY STREET (PARK ROAD TRAIL): FROM NORTH ADAMS ROAD, EXTEND EAST IN SAND SPRINGS . PROJECT LENGTH = 0.950 MILE · | $613,662 | $619,575 | Keystone Services, Inc. | +1.0% | 3 |
| Oct 19, 2017 | 170310HSIPG-211F(031)TR | Hsipg-215f(027)tr |
33295(04) HSIPG-260B(034)TR CHEROKEE, COAL, PAYNE SAFETY IMPROVEMENT (RUMBLE STRIP AND PAVEMENT MARKING ) AT MULTIPLE LOCATIONS IN DIVISIONS I, III, AND IV. · | $1,147,872 | $585,597 | ACTION SAFETY SUPPLY CO., LLC | -49.0% | 4 |
| Oct 19, 2017 | 170329HSIPG-255F(449)TR | Canadian, Oklahoma |
STRIPING AND PAVEMENT MARKING I -40/I-235/I-240/US-77/SH-152: AT MULTIPLE LOCATIONS IN OKLAHOMA AND CANADIAN COUNTIES . · | — | $563,477 | ACTION SAFETY SUPPLY CO., LLC | 1 | |
| Oct 19, 2017 | 170332STP-157E(189)EH | Stpg-257e(235)ig |
OSAGE ENHANCEMENT (TRAIL CONSTRUCTION AND TRAFFIC SIGNALS ) OSAGE PRAIRIE TRAIL : FROM WEST ROGERS BOULEVARD , EXTEND NORTH IN THE CITY OF SKIATOOK . PROJECT LENGTH = 1.750 MILES · | — | $530,240 | BRIGHT LIGHTING, INC. DBA BL TOWER CONSTRUCTION | 2 | |
| Oct 19, 2017 | 170336HSIPG-265B(020)TR | Hsipg-277n(042)tr |
33298(04) HSIPG-208F(059)TR CADDO, CARTER, COMANCHE, GRADY, LOVE, ROGER MILLS, WOODWARD SAFETY IMPROVEMENT (RUMBLE STRIPS AND PAVEMENT MARKING ) US HIGHWAYS /STATE HIGHWAY : AT MULTIPLE LOCATIONS IN DIVISIONS V, VI, AND VII. · | $1,025,910 | $529,000 | Direct Traffic Control, Inc. | -48.4% | 4 |
| Oct 19, 2017 | 170327TAP-255D(328)AG | Oklahoma Division 4 |
ENHANCEMENT (TRAIL CONSTRUCTION ) RAILROAD CORRIDOR WITH TRAIL : FROM S.E.15TH STREET, EXTEND NORTHWEST IN THE CITY OF MIDWEST CITY . PROJECT LENGTH = 1.030 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL B · | $641,067 | $525,980 | CROSSLAND HEAVY CONTRACTORS INC. | -18.0% | 8 |
| Oct 19, 2017 | 170305CIRB-203C(033)RB | Atoka Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-4005): OVER DOYAL CREEK , 0.1 MILES NORTH OF WESLEY ROAD NEAR STRINGTOWN . PROJECT LENGTH = 0.171 MILE · | $569,929 | $490,122 | L & N BRIDGE, LLC | -14.0% | 6 |
| Oct 19, 2017 | 170321STP-240F(058)3B | Latimer, Leflore |
JOINT SEAL/REPAIR US-59/US-270/US-271/SH-2/SH-63: AT MULTIPLE LOCATIONS IN DIVISION II. · | $476,553 | $466,375 | PBX Corporation | -2.1% | 6 |
| Oct 19, 2017 | 170324HSIPG-250C(016)AD | Murray Division 7 |
PEDESTRIAN IMPROVEMENTS (SIDEWALKS ) SH-7/CITY STREET : FROM 0.1 MILES SOUTH OF SH-7. EXTEND NORTH ON C . F. COOPER MEMORIAL RD THEN EAST ON SH -7 IN SULPHUR. PROJECT LENGTH = 0.58 MILE · | $484,218 | $448,690 | C3 Construction, Inc. | -7.3% | 5 |
| Oct 19, 2017 | 170319STP-239D(032)CI | Latimer Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-1470/SW LIMESTONE ROAD ): OVER LIMESTONE CREEK, 3.6 MILES SW OF THE US -270 JUNCTION NEAR WILBURTON . PROJECT LENGTH = 0.113 MILE · | $465,992 | $414,308 | BRIDGECO CONTRACTORS, INC. | -11.1% | 6 |
| Oct 19, 2017 | 170318STP-233D(035)CI | Jackson Division 5 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-155): OVER TRIBUTARY OF BITTER CREEK , 1.3 MILES WEST OF THE US -283 INTERSECTION NEAR ALTUS . PROJECT LENGTH = 0.152 MILE · | $478,650 | $405,646 | KLAVER CONSTRUCTION COMPANY, INC. | -15.3% | 7 |
| Oct 19, 2017 | 170330STP-273F(043)3B | Adair, Mcintosh, Sequoyah, Wagoner |
JOINT SEAL/REPAIR US-59/US-69/SH-10/SH-16/SH-51E: AT MULTIPLE LOCATIONS IN DIVISION I. · | $282,105 | $226,697 | PBX Corporation | -19.6% | 7 |
| Oct 19, 2017 | 170320STP-NBIP(519)3B | Latimer Division 2 |
BRIDGE PAINTING SH -2: OVER FOURCHE MALINE CREEK, 2.4 MILES NORTHWEST OF THE US -270 JUNCTION IN WILBURTON . · | $239,351 | $209,518 | JK INDUSTRIES, INC. | -12.5% | 5 |
| Oct 19, 2017 | 170323RRCS-245B(050)CS | Mccurtain Division 2 |
SAFETY IMPROVEMENT (RAILROAD CROSSING AND SIGNALS ) US-70B: AT THE INTERSECTION OF N.W. TEXAS AVENUE , IN THE CITY OF IDABEL. · | $255,311 | $198,522 | Midstate Traffic Control, Inc. | -22.2% | 2 |
| Oct 19, 2017 | 170333HSIP-258N(036)TR | Ottawa Division 8 |
TRAFFIC SIGNALS CITY STREET (MAIN STREET): AT THE INTERSECTION OF OWENS BOULEVARD IN THE CITY OF MIAMI. · | — | $166,890 | Midstate Traffic Control, Inc. | 3 | |
| Oct 19, 2017 | 170331STP-NBIP(521)3B | Okmulgee Division 1 |
BRIDGE PAINTING COUNTY ROAD (MISSION ROAD): OVER US-62, 2.4 MILES SOUTH OF THE SH -56 LOOP IN THE CITY OF OKMULGEE . · | $85,435 | $116,283 | JK INDUSTRIES, INC. | +36.1% | 5 |
| Oct 19, 2017 | 170335HSIP-262C(044)TR | Pontotoc |
SAFETY IMPROVEMENT (SCHOOL SIGNS ) SH-1: FROM 1.0 MILE EAST OF THE HICKORY STREET INTERSECTION, EXTEND EAST IN THE CITY OF ROFF . PROJECT LENGTH = 0.320 MILE · | $20,477 | $23,079 | TRAFFIC SIGNALS, INC. | +12.7% | 2 |
1–26 of 26
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.