Bid tab 170107

Let Feb 16, 2017 · Division 8 · Tulsa Sign up free

‹ Feb 2017 results

BRIDGE REHABILITATION SH -11: OVER US-75, 3.5 MILES NORTH OF THE I -244 INTERCHANGE IN THE CITY OF TULSA . PROJECT LENGTH = 0.161 MILE

Let date
Thursday, February 16, 2017
Contract
170107
J/P numbers
30594(04)
District
Division 8
County
Tulsa
Highway
Limits
BRIDGE REHABILITATION SH -11: OVER US-75, 3.5 MILES NORTH OF THE I -244 INTERCHANGE IN THE CITY OF TULSA . PROJECT LENGTH = 0.161 MILE
Project number
SBR-272N(186)SB

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,676,068
1 SHERWOOD CONSTRUCTION CO., INC. Low bidder $1,750,485 +4.4%
2 BECCO CONTRACTORS, INC. $2,079,000 +24.0% +18.8%
3 OBC, INC. $2,362,122 +40.9% +34.9%

Bid tab: unit prices 87 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SHERWOOD CONSTR…#2 BECCO CONTRACTO…#3 OBC, INC.
1202(H) 0185 EARTHWORK1LSUM $50,000.00 $16,101.58 $35,000.00 $11,330.47
2205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $7,500.00 $14,297.21 $10,000.00 $4,777.49
3221(C) 2801 TEMPORARY SILT FENCE1,100LF $3.00 $5.24 $1.50 $1.53
4221(F) 0100 TEMPORARY SILT DIKE75LF $15.00 $8.39 $12.00 $12.73
5221(H) 0450 (PL)TEMPORARY INLET SEDIMENT FILTER4EA $200.00 $165.27 $285.00 $303.53
6221(K) 0600 TEMPORARY FIBER LOG300LF $2.25 $2.99 $3.00 $3.14
7230(A) 2806 SOLID SLAB SODDING5,300SY $3.50 $1.54 $2.00 $1.43
8303(A) 2100 AGGREGATE BASE TYPE A780CY $90.00 $29.72 $40.00 $58.97
9325 5271 SEPARATOR FABRIC2,065SY $3.00 $1.68 $1.50 $1.98
10408 5774 PRIME COAT1,021GAL $7.00 $8.02 $1.10 $5.33
11411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)90TON $125.00 $74.64 $65.00 $276.90
12414(B) 5725 DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT )2,110SY $45.00 $28.92 $55.00 $21.59
13414(G) 5275 P.C. CONCRETE FOR PAVEMENT528CY $180.00 $122.33 $125.00 $117.40
14609(A) 0380 CONCRETE CURB (8" BARRIER-INTEGRAL)1,310LF $10.00 $3.00 $10.00 $17.78
15610(A) 0602 4" CONCRETE SIDEWALK500SY $70.00 $33.36 $65.00 $36.50
16613(J) 5915 EDGE DRAIN CONDUIT-PERFORATED655LF $16.00 $6.48 $10.00 $9.16
17613(K) 5916 EDGE DRAIN OUTLET LATERAL-NONPERFORATED60LF $22.00 $11.15 $10.00 $9.23
18613(Q) 5946 OUTLET LATERAL HEADWALL4EA $650.00 $281.92 $1,000.00 $1,441.23
19619(B) 4727 REMOVAL OF CONCRETE PAVEMENT2,540SY $15.00 $6.55 $10.00 $6.11
20619(B) 4780 REMOVAL OF GUARDRAIL1,395LF $5.00 $2.29 $2.20 $3.51
21623(A) 1418 BEAM GUARDRAIL W-BEAM SINGLE868.75LF $30.00 $18.34 $17.60 $17.04
22623(F) 8300 GUARDRAIL TRAIL END TURNDOWN (31")2EA $1,000.00 $687.79 $660.00 $639.00
23623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $2,200.00 $2,407.28 $2,200.00 $2,236.50
24623(I) 8690 GUARDRAIL BRIDGE CONN-TRAIL END (31")2EA $650.00 $859.75 $900.00 $798.75
25623(I) 8700 GUARDRAIL BRIDGE CONN-THRIE BEAM (31")4EA $2,000.00 $1,719.49 $1,650.00 $1,597.50
26501(G) 6309 CLSM BACKFILL90CY $160.00 $206.87 $100.00 $136.60
27502 6116 (PL)FALSEWORK JACKING1LSUM $20,000.00 $250,992.66 $90,000.00 $30,150.15
28504(A) 1304 APPROACH SLAB249.4SY $180.00 $152.54 $165.00 $190.94
29504(B) 1305 SAW-CUT GROOVING801SY $5.20 $4.13 $4.00 $3.83
30504(C) 6250 SEALED EXPANSION JOINT33.2LF $260.00 $232.17 $235.00 $264.85
31504(E) 1381 CONCRETE PARAPET538LF $80.00 $65.31 $115.00 $80.98
32504(G) 6390 RAPID CURE JOINT SEALANT50LF $30.00 $77.92 $35.00 $26.63
33507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY10EA $1,000.00 $1,071.06 $3,000.00 $2,108.70
34507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY10EA $1,150.00 $1,071.06 $3,000.00 $2,108.70
35509 6152 SPECIAL CONCRETE FINISH100.9SY $32.00 $15.48 $90.00 $77.74
36509(A) 1326 CLASS AA CONCRETE233.7CY $550.00 $624.37 $750.00 $753.50
37511(B) 6010 EPOXY COATED REINFORCING STEEL56,850LB $1.20 $0.9500 $1.00 $1.12
38515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)560SY $4.60 $3.44 $3.30 $3.20
39520(A) 6058 PREPARATION OF CRACKS, ABOVE WATER50LF $36.00 $35.86 $30.00 $31.95
40520(C) 6060 EPOXY RESIN, ABOVE WATER4GAL $90.00 $128.08 $110.00 $42.60
41521(A) 6210 PNEUMATICALLY PLACED MORTAR14.9SY $500.00 $909.34 $750.00 $1,043.70
42524(A) 6610 (SP)CARBON FIBER-REINFORCED POLYMER175SF $80.00 $76.85 $65.00 $78.81
43535 6130 (SP)CORROSION INHIBITOR(SURFACE APPLIED)19.4SY $45.00 $56.35 $45.00 $44.73
44542 4610 (PL)INSTALLATION OF BRIDGE ITEMS(TYPE A)1LSUM $1,200.00 $2,605.07 $2,500.00 $4,073.63
45542 4620 (PL)INSTALLATION OF BRIDGE ITEMS(TYPE B)1LSUM $1,000.00 $2,605.07 $2,500.00 $3,633.78
46619(B) 2510 REMOVAL OF BRIDGE ITEM (TYPE A)1LSUM $15,000.00 $2,295.47 $25,000.00 $50,000.00
47619(B) 2520 REMOVAL OF BRIDGE ITEM (TYPE B)1LSUM $50,000.00 $23,943.90 $150,000.00 $400,000.00
48501(G) 6309 CLSM BACKFILL90CY $160.00 $206.87 $100.00 $136.60
49502 6116 (PL)FALSEWORK JACKING1LSUM $20,000.00 $250,992.66 $90,000.00 $30,150.15
50504(A) 1304 APPROACH SLAB249.4SY $180.00 $152.54 $165.00 $191.21
51504(B) 1305 SAW-CUT GROOVING801SY $5.35 $4.13 $4.00 $3.83
52504(C) 6250 SEALED EXPANSION JOINT33.2LF $260.00 $232.17 $235.00 $264.85
53504(E) 1381 CONCRETE PARAPET538LF $80.00 $65.31 $115.00 $80.98
54504(G) 6390 RAPID CURE JOINT SEALANT50LF $30.00 $77.92 $35.00 $26.63
55507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY10EA $1,000.00 $1,071.06 $3,000.00 $2,108.70
56507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY10EA $1,150.00 $1,071.06 $3,000.00 $2,108.70
57509 6152 SPECIAL CONCRETE FINISH100.2SY $32.00 $15.48 $90.00 $77.75
58509(A) 1326 CLASS AA CONCRETE235.1CY $650.00 $624.37 $750.00 $762.00
59511(B) 6010 EPOXY COATED REINFORCING STEEL56,970LB $1.16 $0.9500 $1.00 $1.12
60513(B) 6019 CLASS B BRIDGE DECK REPAIR30SY $350.00 $416.48 $400.00 $426.00
61513(C) 6020 CLASS C BRIDGE DECK REPAIR30SY $530.00 $533.26 $500.00 $489.90
62515(A) 6013 WATER REPELLENT (VISUALLY INSPECTED)558SY $4.60 $3.44 $3.30 $3.20
63520(A) 6058 PREPARATION OF CRACKS, ABOVE WATER50LF $36.00 $35.86 $30.00 $31.95
64520(C) 6060 EPOXY RESIN, ABOVE WATER4GAL $90.00 $128.08 $110.00 $42.60
65521(A) 6210 PNEUMATICALLY PLACED MORTAR10.8SY $500.00 $909.34 $750.00 $1,043.70
66524(A) 6610 (SP)CARBON FIBER-REINFORCED POLYMER170.5SF $80.00 $76.85 $65.00 $78.81
67535 6130 (SP)CORROSION INHIBITOR(SURFACE APPLIED)18.9SY $45.00 $56.35 $45.00 $44.73
68542 4610 (PL)INSTALLATION OF BRIDGE ITEMS(TYPE A)1LSUM $1,200.00 $2,605.07 $2,500.00 $3,953.28
69542 4620 (PL)INSTALLATION OF BRIDGE ITEMS(TYPE B)1LSUM $1,000.00 $2,605.07 $2,500.00 $3,533.67
70619(B) 2510 REMOVAL OF BRIDGE ITEM (TYPE A)1LSUM $15,000.00 $2,295.47 $25,000.00 $50,000.00
71619(B) 2520 REMOVAL OF BRIDGE ITEM (TYPE B)1LSUM $50,000.00 $23,943.90 $150,000.00 $400,000.00
72805(D) 8756 (PL)REMOVE & RESET EXISTING SIGNS3EA $240.00 $136.29 $110.00 $106.50
73856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)10,880LF $0.7600 $0.7100 $0.6000 $0.5500
74857(C) 8851 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE)21,600LF $0.8200 $0.3400 $0.3000 $0.2700
75857(E) 8887 (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-11,200EA $1.00 $0.6800 $0.5500 $0.5300
76857(F) 8006 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE)8,000LF $0.7500 $0.3400 $0.3000 $0.2700
77880(A) 8812 ARROW DISPLAY(TYPE C)450SD $5.00 $1.36 $1.10 $1.07
78880(B) 8818 CONSTRUCTION SIGNS 0 TO 6.25 SF8,775SD $0.5000 $0.3400 $0.3000 $0.2700
79880(B) 8821 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF6,075SD $0.6000 $0.3400 $0.3000 $0.2700
80880(B) 8824 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF7,200SD $1.20 $2.04 $1.65 $1.60
81880(C) 8842 CONSTRUCTION BARRICADES(TYPE III)5,515SD $0.5000 $0.3400 $0.3000 $0.2700
82880(C) 8848 WING BARRICADES900SD $3.00 $1.36 $1.10 $1.07
83880(E) 8860 WARNING LIGHTS(TYPE A)12,825SD $0.5000 $0.1400 $0.1100 $0.1100
84880(F) 8878 DRUMS31,165SD $0.5000 $0.1400 $0.1500 $0.1100
85882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN450SD $15.00 $20.44 $17.00 $15.98
86642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $10,000.00 $12,827.40 $30,754.00 $10,969.50
87641 1399 MOBILIZATION1LSUM $107,627.00 $70,018.00 $125,000.00 $100,000.00