| 1 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 223 | CY |
$50.00 |
$100.00 |
$62.00 |
$88.98 |
| 2 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 1,245 | TON |
$22.00 |
$25.00 |
$29.50 |
$30.06 |
| 3 | 407(B) 0250 |
TACK COAT | 16,439 | GAL |
$2.75 |
$2.50 |
$4.00 |
$2.76 |
| 4 | 411(C) 5955 |
SUPERPAVE, TYPE S4(PG 70-28 OK) | 13,757 | TON |
$75.00 |
$79.50 |
$82.00 |
$90.51 |
| 5 | 411(D) 5970 |
SUPERPAVE, TYPE S5(PG 70-28 OK) | 5,242 | TON |
$75.00 |
$79.50 |
$85.80 |
$85.52 |
| 6 | 411(H) 6210 |
SUPERPAVE, TYPE S3(PATCH)(PG64-22OK) | 185 | TON |
$200.00 |
$150.00 |
$125.00 |
$142.87 |
| 7 | 412 5267 |
COLD MILLING PAVEMENT | 88,903 | SY |
$2.00 |
$0.9500 |
$1.75 |
$1.72 |
| 8 | 413(B) 4863 |
RUMBLE STRIP-METHOD HMA-CYC | 52,280 | LF |
$0.1500 |
$0.3500 |
$0.1000 |
$0.1700 |
| 9 | 504(E) 1381 |
CONCRETE PARAPET | 20 | LF |
$200.00 |
$200.00 |
$325.00 |
$502.53 |
| 10 | 612(A) 0641 |
MANHOLES ADJUST TO GRADE | 2 | EA |
$908.00 |
$1,200.00 |
$1,775.00 |
$1,303.63 |
| 11 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 1,610 | LF |
$3.50 |
$3.50 |
$3.50 |
$3.32 |
| 12 | 619(B) 6252 |
REMOVAL OF EXISTING PARAPET | 20 | LF |
$200.00 |
$100.00 |
$85.00 |
$380.48 |
| 13 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 1,350 | LF |
$17.00 |
$14.00 |
$14.00 |
$14.36 |
| 14 | 623(G) 8590 |
GUARDRAIL END TREATMENT (31") | 4 | EA |
$2,300.00 |
$2,400.00 |
$2,500.00 |
$2,456.76 |
| 15 | 623(I) 8700 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 4 | EA |
$1,800.00 |
$2,200.00 |
$2,300.00 |
$2,235.63 |
| 16 | 853 9069 |
GUARDRAIL DELINEATORS(TYPE 2, CODE 1) | 56 | EA |
$12.00 |
$7.00 |
$8.00 |
$7.30 |
| 17 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 102,300 | LF |
$0.6000 |
$0.4000 |
$0.5000 |
$0.4000 |
| 18 | 856(A) 8540 |
TRAFFIC STRIPE(MULTI-POLY.)(8" WIDE) | 22 | LF |
$3.00 |
$2.00 |
$2.00 |
$1.99 |
| 19 | 856(A) 8555 |
TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 398 | LF |
$10.00 |
$5.50 |
$6.00 |
$5.53 |
| 20 | 856(B) 8525 |
TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | 2 | EA |
$175.00 |
$450.00 |
$500.00 |
$442.26 |
| 21 | 856(B) 8860 |
TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) | 2 | EA |
$150.00 |
$250.00 |
$250.00 |
$221.14 |
| 22 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$10,000.00 |
$15,000.00 |
$9,000.00 |
$35,000.00 |
| 23 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$20,000.00 |
$123,450.00 |
$16,250.00 |
$33,000.00 |