ENHANCEMENT (SIDEWALK IMPROVEMENT ) CITY STREET (GRAND BOULEVARD ): FROM GRAYSTONE AVE TO NICHOLS RD IN THE CITY OF NICHOLS HILLS. PROJECT LENGTH = 0.648 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED , HOWEVER BIDDERS WILL BE REQUIRED TO PROVIDE
- Let date
- Thursday, June 20, 2013
- Contract
- 130261
- J/P numbers
- 28693(04)
- District
- Division 4
- County
- Oklahoma
- Highway
- Limits
- ENHANCEMENT (SIDEWALK IMPROVEMENT ) CITY STREET (GRAND BOULEVARD ): FROM GRAYSTONE AVE TO NICHOLS RD IN THE CITY OF NICHOLS HILLS. PROJECT LENGTH = 0.648 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED , HOWEVER BIDDERS WILL BE REQUIRED TO PROVIDE
- Project number
- STP-155C(899)AG
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $137,392 | ||
| 1 | Olivas Construction Company, Inc. Low bidder | $122,209 | -11.1% | |
| 2 | SAC Services, Inc. | $126,588 | -7.9% | +3.6% |
| 3 | PARATHON CONSTRUCTION, LLC | $141,498 | +3.0% | +15.8% |
| 4 | CONNELLY PAVING CO. | $148,211 | +7.9% | +21.3% |
| 5 | RUDY CONSTRUCTION CO. | $199,766 | +45.4% | +63.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Olivas Construc… | #2 SAC Services, I… | #3 PARATHON CONSTR… | #4 CONNELLY PAVING… | #5 RUDY CONSTRUCTI… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 202(A) 0183 | UNCLASSIFIED EXCAVATION | 752 | CY | $6.00 | $11.00 | $9.50 | $12.00 | $17.00 | $20.00 |
| 2 | 205(A) 4229 | TYPE A-SALVAGED TOPSOIL | 1 | LSUM | $5,000.00 | $4,500.00 | $7,100.00 | $2,500.00 | $3,400.00 | $5,000.00 |
| 3 | 221(C) 2801 | TEMPORARY SILT FENCE | 2,710 | LF | $5.00 | $1.65 | $1.95 | $2.25 | $2.50 | $1.00 |
| 4 | 221(K) 0600 | TEMPORARY FIBER LOG | 186 | LF | $5.00 | $2.50 | $6.50 | $5.25 | $12.00 | $6.00 |
| 5 | 230(A) 2806 | SOLID SLAB SODDING | 3,000 | SY | $4.00 | $2.50 | $3.75 | $4.60 | $3.00 | $5.00 |
| 6 | 610(A) 0602 | 4" CONCRETE SIDEWALK | 1,960 | SY | $40.00 | $35.00 | $42.50 | $42.50 | $50.00 | $65.00 |
| 7 | 610(I) 4610 | TACTILE WARNING DEVICE-NEW | 140 | SF | $50.00 | $50.00 | $20.00 | $40.00 | $30.00 | $25.00 |
| 8 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $3,000.00 | $3,000.00 | $3,000.00 | $2,000.00 | $2,000.00 | $10,000.00 |
| 9 | 642(B) 0096 | CONSTRUCTION STAKING LEVEL II | 1 | LSUM | $3,000.00 | $4,300.00 | $3,000.00 | $4,000.00 | $6,820.00 | $5,000.00 |
| 10 | 641 1552 | MOBILIZATION | 1 | LSUM | $10,000.00 | $14,100.00 | $2,500.00 | $14,200.00 | $3,000.00 | $15,000.00 |