| 1 | 202(G) 0185 |
EARTHWORK | 1 | LSUM |
$30,000.00 |
$72,000.00 |
$100,000.00 |
$119,000.00 |
| 2 | 223 2801 |
TEMPORARY SILT FENCE | 3,000 | LF |
$2.00 |
$1.20 |
$1.26 |
$1.20 |
| 3 | 230(A) 2806 |
SOLID SLAB SODDING | 17,660 | SY |
$2.50 |
$1.50 |
$1.58 |
$1.50 |
| 4 | 233(A) 2817 |
VEGETATIVE MULCHING | 3.65 | AC |
$500.00 |
$900.00 |
$948.54 |
$900.00 |
| 5 | 303 5912 |
AGGREGATE BASE | 23,902.05 | TON |
$28.00 |
$25.00 |
$30.00 |
$33.00 |
| 6 | 311(D) 0154 |
PROCESSING EXISTING BASE & SURFACE, METHOD D | 319.57 | STA |
$550.00 |
$550.00 |
$165.13 |
$675.00 |
| 7 | 403(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 7,086 | TON |
$50.00 |
$30.00 |
$31.75 |
$38.00 |
| 8 | 407 0250 |
TACK COAT | 6,305 | GAL |
$3.00 |
$2.20 |
$4.00 |
$2.00 |
| 9 | 411(S3) 5945 |
(SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | 7,953 | TON |
$75.00 |
$76.00 |
$71.50 |
$72.00 |
| 10 | 411(S4) 5960 |
(SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 11,379 | TON |
$70.00 |
$85.00 |
$74.50 |
$78.00 |
| 11 | 613(D) 0690 |
24" CORR. GALV. STEEL PIPE | 44 | LF |
$40.00 |
$62.00 |
$45.37 |
$62.00 |
| 12 | 613(M) 5730 |
24" PREFAB. CULVERT END SECTION, ROUND | 2 | EA |
$900.00 |
$450.00 |
$276.15 |
$600.00 |
| 13 | 623(A) 0932 |
BEAM GUARD RAIL-W-BEAM-SINGLE | 1,400 | LF |
$15.00 |
$13.95 |
$14.76 |
$14.00 |
| 14 | 623(F) 4447 |
GUARD RAIL ANCHOR UNIT (TYPE B) | 2 | EA |
$800.00 |
$650.00 |
$579.67 |
$550.00 |
| 15 | 629(A) 4958 |
MAILBOX INSTALLATION-SINGLE | 1 | EA |
$100.00 |
$75.00 |
$79.05 |
$100.00 |
| 16 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 76.04 | SF |
$20.00 |
$12.00 |
$12.65 |
$12.00 |
| 17 | 851(D) 8597 |
FLANGE CHANNEL POSTS(4 LB/FT) | 252 | LF |
$10.00 |
$9.00 |
$9.49 |
$9.00 |
| 18 | 853 9033 |
DELINEATORS(TYPE 2, CODE 1) | 25 | EA |
$20.00 |
$18.00 |
$18.97 |
$18.00 |
| 19 | 853 9039 |
DELINEATORS(TYPE 2, CODE 3) | 30 | EA |
$20.00 |
$18.00 |
$18.97 |
$18.00 |
| 20 | 854(A) 8800 |
TRAFFIC STRIPE(PAINT)(4" WIDE) | 20,922 | LF |
$0.6000 |
$0.2100 |
$0.2200 |
$0.2100 |
| 21 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$9,000.00 |
$5,500.00 |
$5,796.65 |
$50,000.00 |
| 22 | 202(A) 1301 |
UNCLASSIFIED EXCAVATION | 200 | CY |
$15.00 |
$10.00 |
$5.27 |
$5.00 |
| 23 | 501(A) 1306 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 50 | CY |
$15.00 |
$15.00 |
$5.27 |
$5.00 |
| 24 | 508(A) 6335 |
REMOVAL OF CULVERT END | 2 | EA |
$2,000.00 |
$1,000.00 |
$1,264.73 |
$1,200.00 |
| 25 | 509(B) 1328 |
CLASS A CONCRETE | 120 | CY |
$550.00 |
$390.00 |
$544.89 |
$517.00 |
| 26 | 511(A) 1332 |
REINFORCING STEEL | 14,160 | LB |
$1.00 |
$0.8000 |
$0.7400 |
$0.7000 |
| 27 | 642 0098 |
STAKING | 1 | LSUM |
$8,000.00 |
$6,200.00 |
$31,618.10 |
$10,000.00 |
| 28 | 220 2800 |
(SP)SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$7,500.00 |
$5,000.00 |
$3,701.53 |
$20,000.00 |
| 29 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$45,000.00 |
$97,000.00 |
$250,000.00 |
$105,000.00 |