Bid code 616(D) 7078

VALVE BOX EXTENSION · per EA Sign up free

‹ All bid codes

$112.75Avg low bid / EA
$158.01Avg of all bids
$167.41Avg engineer's estimate
17Jobs · 158 EA

Average low bid by year

YearJobsQuantityAvg lowAvg all
202114$500.00$325.00
2020545$154.66$165.02
2019752$99.26$195.98
2018457$64.80$72.62

Recent low bids

ExcelCSV
Let dateContractCounty / DistrictQuantityUnit priceLow bidder
Nov 18, 2021210347 DelawareDivision 84 EA $500.00C-GAWF CONSTRUCTION, INC.
Sep 17, 2020200294 SequoyahDivision 16 EA $120.00Rosscon, LLC
Sep 17, 2020200088 TulsaDivision 810 EA $55.00CROSSLAND HEAVY CONTRACTORS INC.
Aug 20, 2020200270 Nhppi-4400(077)pm17 EA $191.15SHERWOOD CONSTRUCTION CO., INC.
May 14, 2020200126 TulsaDivision 87 EA $198.77SHERWOOD CONSTRUCTION CO., INC.
Mar 19, 2020200133 HaskellDivision 15 EA $209.76C3 Construction, Inc.
Nov 14, 2019190389 TulsaDivision 89 EA $22.75CROSSLAND HEAVY CONTRACTORS INC.
Oct 17, 2019190331 TulsaDivision 83 EA $180.33SHERWOOD CONSTRUCTION CO., INC.
Aug 22, 2019190262 TulsaDivision 81 EA $100.00BECCO CONTRACTORS, INC.
Aug 22, 2019190271 TulsaDivision 828 EA $106.00Paragon Contractors, LLC
May 16, 2019190139 WagonerDivision 12 EA $300.00Paragon Contractors, LLC
Mar 14, 2019190133 RogersDivision 82 EA $163.88SHERWOOD CONSTRUCTION CO., INC.
Jan 17, 2019190051 Ssp-250n(018)pm7 EA $60.00Pavers, Inc.
Sep 20, 2018180280 CraigDivision 810 EA $63.00CROSSLAND HEAVY CONTRACTORS INC.
May 17, 2018180193 CreekDivision 82 EA $160.00Cimarron Construction Company, LLC
Mar 15, 2018180122 Acstp-277d(044)ur20 EA $51.90THE CUMMINS CONSTRUCTION CO., INC.
Mar 15, 2018180122 Acstp-277d(044)ur17 EA $51.90THE CUMMINS CONSTRUCTION CO., INC.
Mar 15, 2018180148 TulsaDivision 88 EA $102.92SHERWOOD CONSTRUCTION CO., INC.