20Let jobs
$135,239,698Total low bids
—Total estimates
—Low bids vs estimates
Dec 2024 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Dec 13, 2024 | 78798 | Williamson District 9 |
(X1-8,X1-7-1,X1-7,X1-6-1)R-2 · | — | $41,665,230 | Samron Midwest Contracting, Inc. | 2 | |
| Dec 13, 2024 | 64N05 | Henry District 2 |
5.795 miles of pavement patching, HMA resurfacing, HMA surface removal, the removal and replacement of concrete bridge decks for SNs 037-0023 and 037-0024 over Cleveland Road, deck replacements and deck repairs for SN-s 037-0021 and 037-0022 over the Rock · | — | $24,521,613 | Civil Constructors d/b/a Helm Civil and Phoenix Corporation of the Quad Cities | 3 | |
| Dec 13, 2024 | 72M81 | Sangamon District 6 |
84-5-1(BRR,RS-2) · | — | $17,664,190 | Illinois Valley Paving, a div of UCM, Inc. | 1 | |
| Dec 13, 2024 | 78633 | Williamson District 9 |
113R-1 · | — | $16,365,141 | E. T. Simonds Construction Company | 2 | |
| Dec 13, 2024 | 72122 | Sangamon District 6 |
28(R-2,RS-8) · | — | $5,572,391 | Illinois Valley Paving, a div of UCM, Inc. | 3 | |
| Dec 13, 2024 | 70D76 | Champaign District 5 |
(14HB)BR,(14B)BR-1 · | — | $4,119,981 | Stark Excavating, Inc. | 2 | |
| Dec 13, 2024 | 78A67 | Gallatin District 9 |
(10,11,11-1)RS-2 · | — | $3,871,637 | E. T. Simonds Construction Company | 2 | |
| Dec 13, 2024 | 76U07 | Madison District 8 |
60-7BJR-BDR · | — | $2,833,156 | Keeley & Sons, Inc. | 2 | |
| Dec 13, 2024 | 72426 | Christian District 6 |
(11-12)N · | — | $2,733,196 | Truman L. Flatt & Sons Co., Inc. | 2 | |
| Dec 13, 2024 | 70H01 | Douglas District 5 |
(21-27B-2)BR · | — | $2,185,889 | Sangamo Construction Company | 1 | |
| Dec 13, 2024 | 78A71 | Union District 9 |
106RS-6 · | — | $2,148,210 | Samron Midwest Contracting, Inc. | 2 | |
| Dec 13, 2024 | 62T17 | Dupage District 1 |
FAP 0347 22 BJ3 · | — | $1,972,826 | D. Construction, Inc. | 8 | |
| Dec 13, 2024 | 70E63 | Vermillion District 5 |
L-BR-1 · | — | $1,957,706 | Sangamo Construction Company | 3 | |
| Dec 13, 2024 | 74B41 | Cumberland District 7 |
D7 BRIDGE REPAIRS 2024-12 · | — | $1,564,297 | Samron Midwest Contracting, Inc. | 2 | |
| Dec 13, 2024 | 62T30 | Dupage District 1 |
FAP 0870 22 BJ · | — | $1,491,736 | Martam Construction Incorporated | 8 | |
| Dec 13, 2024 | 62T04 | Will District 1 |
FAP 0330 22 BJ2 · Bridge deck overlay, reconstruction of abutment deck joint, approach slab repairs and substructure repairs of | — | $1,407,207 | D. Construction, Inc. | 4 | |
| Dec 13, 2024 | 78A82 | Perry District 9 |
(111,X,566)RS-3 · | — | $974,236 | Samron Midwest Contracting, Inc. | 2 | |
| Dec 13, 2024 | 78A27 | Perry District 9 |
(8-1B,8-1B-1)BRR-1 · | — | $888,874 | E. T. Simonds Construction Company | 2 | |
| Dec 13, 2024 | 78A70 | Johnson District 9 |
113RS-4 · | — | $659,172 | Samron Midwest Contracting, Inc. | 2 | |
| Dec 13, 2024 | 78A65 | Williamson District 9 |
6RS-3 · | — | $643,012 | Samron Midwest Contracting, Inc. | 2 |
1–20 of 20
Source: IDOT Transportation Bulletin "Unit Price Tabulation of Bids" for each letting. Totals are as read; IDOT does not publish an engineer's estimate there, so estimate columns stay blank. Bid Potato backfills the last two years. Confirm against IDOT's As Accepted tabulation.