17-00110-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $1,291,558 | ||
| 2 | Keller Construction, Inc. | $1,656,607 | +28.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Keller Construc… |
|---|---|---|---|---|---|---|---|
| 1 | X0323389 | STORM SEW CONNECTION | 5 | EACH | $250.00 | $277.00 | |
| 2 | X1200108 | INLET BOX SPL | 3 | EACH | $2,345.00 | $2,900.00 | |
| 3 | X1500004 | BIT SURF TREATMNT A1 | 47 | SQ YD | $60.00 | $42.55 | |
| 4 | X1700128 | STAMPED CLRDPCCPVT8J | 229 | SQ YD | $175.00 | $362.00 | |
| 5 | X2600012 | REM & REL SN P&P ASSY | 5 | EACH | $250.00 | $500.00 | |
| 6 | X4401198 | HMA SURF REM VAR DP | 4,075 | SQ YD | $7.20 | $6.11 | |
| 7 | X6010302 | TRENCH DRAIN | 35 | FOOT | $545.00 | $712.00 | |
| 8 | X6026634 | METER VAULTS ADJ | 7 | EACH | $250.00 | $776.75 | |
| 9 | X6061005 | CONC CURB TB SPL | 2,969 | FOOT | $38.00 | $46.45 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $9,750.00 | $58,550.00 | |
| 11 | X7240300 | SIGN REMOVAL | 30 | EACH | $155.00 | $266.00 | |
| 12 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $13,000.00 | $15,454.00 | |
| 13 | Z0056668 | SS 2 WAT MN 12 | 152 | FOOT | $121.00 | $127.50 | |
| 14 | Z0056669 | SS 2 WAT MN 15 | 52 | FOOT | $232.00 | $244.50 | |
| 15 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 17 | 20100110 | TREE REMOV 6-15 | 14 | UNIT | $56.00 | $258.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 520 | CU YD | $135.00 | $266.15 | |
| 19 | 20800150 | TRENCH BACKFILL | 358 | CU YD | $43.50 | $63.30 | |
| 20 | 21101610 | TOPSOIL F & P 3 | 1,237 | SQ YD | $10.00 | $9.30 | |
| 21 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $14.45 | $13.50 | |
| 22 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $14.45 | $13.50 | |
| 23 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $14.45 | $13.50 | |
| 24 | 25200100 | SODDING | 1,237 | SQ YD | $19.85 | $18.55 | |
| 25 | 25200200 | SUPPLE WATERING | 55 | UNIT | $400.00 | $375.00 | |
| 26 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $6.00 | $5.00 | |
| 27 | 28000500 | INLET & PIPE PROTECT | 18 | EACH | $75.00 | $197.00 | |
| 28 | 31100100 | SUB GRAN MAT A | 701 | TON | $40.30 | $74.55 | |
| 29 | 35100300 | AGG BASE CSE A 4 | 518 | SQ YD | $21.00 | $40.25 | |
| 30 | 40201000 | AGGREGATE-TEMP ACCESS | 121 | TON | $45.00 | $114.20 | |
| 31 | 40600275 | BIT MATLS PR CT | 2,862 | POUND | $1.30 | $2.62 | |
| 32 | 40600290 | BIT MATLS TACK CT | 3,017 | POUND | $1.50 | $2.62 | |
| 33 | 40600370 | LONG JOINT SEALANT | 1,874 | FOOT | $6.35 | $5.77 | |
| 34 | 40600982 | HMA SURF REM BUTT JT | 67 | SQ YD | $14.70 | $6.11 | |
| 35 | 40600990 | TEMPORARY RAMP | 164 | SQ YD | $27.00 | $0.0100 | |
| 36 | 40602970 | HMA BC IL-9.5FG N70 | 6 | TON | $590.00 | $421.05 | |
| 37 | 40603085 | HMA BC IL-19.0 N70 | 408 | TON | $150.00 | $144.18 | |
| 38 | 40604052 | HMA SC IL-9.5 C N70 | 938 | TON | $155.00 | $144.18 | |
| 39 | 42001300 | PROTECTIVE COAT | 229 | SQ YD | $3.00 | $0.0100 | |
| 40 | 42300200 | PCC DRIVEWAY PAVT 6 | 518 | SQ YD | $122.00 | $97.85 | |
| 41 | 42400100 | PC CONC SIDEWALK 4 | 14,974 | SQ FT | $9.10 | $7.55 | |
| 42 | 42400800 | DETECTABLE WARNINGS | 255 | SQ FT | $32.00 | $77.45 | |
| 43 | 44000100 | PAVEMENT REM | 1,557 | SQ YD | $16.15 | $25.15 | |
| 44 | 44000155 | HMA SURF REM 1 1/2 | 1,505 | SQ YD | $3.00 | $6.11 | |
| 45 | 44000200 | DRIVE PAVEMENT REM | 240 | SQ YD | $23.60 | $15.90 | |
| 46 | 44000300 | CURB REM | 3,147 | FOOT | $13.20 | $5.50 | |
| 47 | 44000500 | COMB CURB GUTTER REM | 488 | FOOT | $18.00 | $14.10 | |
| 48 | 44000600 | SIDEWALK REM | 13,310 | SQ FT | $1.50 | $1.25 | |
| 49 | 44201749 | CL D PATCH T1 9 | 75 | SQ YD | $180.00 | $138.92 | |
| 50 | 44201753 | CL D PATCH T2 9 | 75 | SQ YD | $155.00 | $138.92 | |
| 51 | 44201757 | CL D PATCH T3 9 | 75 | SQ YD | $140.00 | $138.92 | |
| 52 | 44201759 | CL D PATCH T4 9 | 75 | SQ YD | $120.00 | $138.92 | |
| 53 | 54216185 | R C PIPE TEE 15P 12R | 1 | EACH | $1,800.00 | $2,600.00 | |
| 54 | 54248510 | CONCRETE COLLAR | 1.2 | CU YD | $1,125.00 | $4,900.00 | |
| 55 | 550A0340 | STORM SEW CL A 2 12 | 116 | FOOT | $101.00 | $110.00 | |
| 56 | 550A0380 | STORM SEW CL A 2 18 | 5 | FOOT | $247.50 | $240.50 | |
| 57 | 55100500 | STORM SEWER REM 12 | 161 | FOOT | $29.75 | $38.25 | |
| 58 | 55100700 | STORM SEWER REM 15 | 52 | FOOT | $45.25 | $41.40 | |
| 59 | 55100900 | STORM SEWER REM 18 | 2 | FOOT | $65.00 | $171.20 | |
| 60 | 60218400 | MAN TA 4 DIA T1F CL | 1 | EACH | $2,920.00 | $3,012.00 | |
| 61 | 60218500 | MAN TA 4 DIA T3F&G | 2 | EACH | $2,920.00 | $3,012.00 | |
| 62 | 60224030 | MAN TA 6 DIA T15F&L | 1 | EACH | $4,650.00 | $4,670.00 | |
| 63 | 60235700 | INLETS TA T3F&G | 1 | EACH | $1,955.00 | $2,054.00 | |
| 64 | 60237000 | INLETS TA T15F&L | 4 | EACH | $1,915.00 | $2,054.00 | |
| 65 | 60237470 | INLETS TA T24F&G | 1 | EACH | $1,955.00 | $2,054.00 | |
| 66 | 60240210 | INLETS TB T1F OL | 1 | EACH | $2,420.00 | $2,392.00 | |
| 67 | 60240215 | INLETS TB T1F CL | 1 | EACH | $2,095.00 | $2,392.00 | |
| 68 | 60240320 | INLETS TB T15F&L | 1 | EACH | $2,420.00 | $2,392.00 | |
| 69 | 60255500 | MAN ADJUST | 4 | EACH | $400.00 | $2,168.00 | |
| 70 | 60265700 | VV ADJUST | 21 | EACH | $285.00 | $1,275.50 | |
| 71 | 60500040 | REMOV MANHOLES | 1 | EACH | $250.00 | $614.00 | |
| 72 | 60500060 | REMOV INLETS | 9 | EACH | $175.00 | $410.00 | |
| 73 | 60600605 | CONC CURB TB | 740 | FOOT | $59.40 | $54.50 | |
| 74 | 60605000 | COMB CC&G TB6.24 | 256 | FOOT | $83.50 | $63.05 | |
| 75 | 67100100 | MOBILIZATION | 1 | L SUM | $50,000.00 | $188,242.00 | |
| 76 | 70300100 | SHORT TERM PAVT MKING | 212 | FOOT | $4.00 | $5.00 | |
| 77 | 70300150 | SHRT TRM PAVT MK REM | 73 | SQ FT | $8.00 | $7.15 | |
| 78 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 4,567 | FOOT | $0.5000 | $0.0100 | |
| 79 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 688 | FOOT | $8.80 | $0.0100 | |
| 80 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 110 | FOOT | $16.50 | $0.0100 | |
| 81 | 72000100 | SIGN PANEL T1 | 105 | SQ FT | $41.30 | $66.05 | |
| 82 | 72400100 | REMOV SIN PAN ASSY TA | 8 | EACH | $75.00 | $250.00 | |
| 83 | 72800100 | TELES STL SIN SUPPORT | 295 | FOOT | $17.00 | $46.50 | |
| 84 | 78000200 | THPL PVT MK LINE 4 | 4,567 | FOOT | $1.45 | $1.47 | |
| 85 | 78000600 | THPL PVT MK LINE 12 | 688 | FOOT | $11.25 | $7.04 | |
| 86 | 78000650 | THPL PVT MK LINE 24 | 110 | FOOT | $20.00 | $17.15 | |
| 87 | 78300201 | PAVMT MRKG REM GRIND | 2,430 | SQ FT | $2.25 | $1.98 |