15-00044-00-FP
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Geneva Construction Company Low bidder | $645,500 | ||
| 2 | Triggi Construction, Inc. | $646,579 | +0.2% | |
| 3 | D. Construction, Inc. | $693,533 | +7.4% | |
| 4 | Alliance Contractors, Inc. | $719,988 | +11.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Geneva Construc… | #2 Triggi Construc… | #3 D. Construction… | #4 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 178 | SQ FT | $16.00 | $16.00 | $13.20 | $16.00 | |
| 2 | X4021000 | TEMP ACCESS- PRIV ENT | 27 | EACH | $146.00 | $50.00 | $250.00 | $100.00 | |
| 3 | X4401198 | HMA SURF REM VAR DP | 6,965 | SQ YD | $3.40 | $2.00 | $2.00 | $3.20 | |
| 4 | X6023840 | REMOVE & REL INLETS | 15 | EACH | $1,925.00 | $2,000.00 | $2,500.00 | $3,145.00 | |
| 5 | X7030005 | TEMP PAVT MKING REMOV | 1,500 | SQ FT | $1.50 | $1.50 | $2.00 | $1.50 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,200.00 | $5,000.00 | $15,000.00 | $8,500.00 | |
| 7 | Z0030850 | TEMP INFO SIGNING | 200 | SQ FT | $20.00 | $20.00 | $25.00 | $20.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 641 | CU YD | $50.60 | $35.00 | $35.00 | $20.00 | |
| 9 | 20800150 | TRENCH BACKFILL | 10 | CU YD | $51.25 | $95.00 | $80.00 | $150.00 | |
| 10 | 21101615 | TOPSOIL F & P 4 | 1,204 | SQ YD | $5.15 | $5.00 | $9.00 | $6.25 | |
| 11 | 25000110 | SEEDING CL 1A | 0.3 | ACRE | $4,250.00 | $5,000.00 | $4,950.00 | $3,500.00 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 27 | POUND | $2.50 | $5.00 | $74.25 | $3.00 | |
| 13 | 25000500 | PHOSPHORUS FERT NUTR | 27 | POUND | $2.50 | $5.00 | $74.25 | $3.00 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 27 | POUND | $2.50 | $5.00 | $74.25 | $3.00 | |
| 15 | 25100630 | EROSION CONTR BLANKET | 1,204 | SQ YD | $2.05 | $2.50 | $2.37 | $2.00 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $3.00 | $1.00 | $3.30 | $2.00 | |
| 17 | 28000510 | INLET FILTERS | 17 | EACH | $175.00 | $150.00 | $192.50 | $25.00 | |
| 18 | 31101200 | SUB GRAN MAT B 4 | 2,135 | SQ YD | $3.75 | $7.50 | $7.00 | $2.00 | |
| 19 | 31101810 | SUB GRAN MAT B 12 | 805 | SQ YD | $31.35 | $15.00 | $20.00 | $7.00 | |
| 20 | 40600290 | BIT MATLS TACK CT | 4,701 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.7500 | |
| 21 | 40600827 | P LB MM IL-4.75 N50 | 439 | TON | $98.00 | $96.00 | $90.00 | $96.85 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 837 | SQ YD | $3.40 | $13.00 | $0.0100 | $3.20 | |
| 23 | 40600990 | TEMPORARY RAMP | 288 | SQ YD | $14.00 | $24.55 | $0.0100 | $33.50 | |
| 24 | 40604050 | HMA SC IL-9.5 C N50 | 585 | TON | $80.00 | $92.50 | $70.00 | $80.00 | |
| 25 | 42300200 | PCC DRIVEWAY PAVT 6 | 441 | SQ YD | $70.00 | $55.00 | $62.50 | $85.00 | |
| 26 | 42400200 | PC CONC SIDEWALK 5 | 15,240 | SQ FT | $6.25 | $5.50 | $6.50 | $7.00 | |
| 27 | 42400800 | DETECTABLE WARNINGS | 638 | SQ FT | $23.00 | $30.00 | $27.50 | $28.00 | |
| 28 | 44000100 | PAVEMENT REM | 292 | SQ YD | $5.00 | $15.00 | $15.00 | $81.00 | |
| 29 | 44000200 | DRIVE PAVEMENT REM | 441 | SQ YD | $4.95 | $20.00 | $12.00 | $27.00 | |
| 30 | 44000500 | COMB CURB GUTTER REM | 4,559 | FOOT | $6.00 | $5.50 | $8.00 | $12.00 | |
| 31 | 44000600 | SIDEWALK REM | 15,071 | SQ FT | $1.15 | $1.50 | $2.00 | $3.50 | |
| 32 | 44201713 | CL D PATCH T1 6 | 75 | SQ YD | $70.00 | $115.00 | $50.00 | $68.00 | |
| 33 | 550A0050 | STORM SEW CL A 1 12 | 100 | FOOT | $36.25 | $125.00 | $60.00 | $50.00 | |
| 34 | 56109210 | WATER VALVES ADJUST | 3 | EACH | $180.00 | $475.00 | $400.00 | $450.00 | |
| 35 | 60236800 | INLETS TA T11F&G | 5 | EACH | $1,910.00 | $2,200.00 | $1,800.00 | $3,145.00 | |
| 36 | 60255500 | MAN ADJUST | 33 | EACH | $1,000.00 | $700.00 | $550.00 | $450.00 | |
| 37 | 60404805 | FR & GRATES T11V | 13 | EACH | $420.00 | $700.00 | $450.00 | $400.00 | |
| 38 | 60406200 | FR & LIDS T5 OL | 2 | EACH | $610.00 | $600.00 | $550.00 | $600.00 | |
| 39 | 60608562 | COMB CC&G TM4.12 | 4,559 | FOOT | $16.00 | $20.00 | $20.00 | $21.00 | |
| 40 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $4,500.00 | $3,000.00 | $4,000.00 | $500.00 | |
| 41 | 67100100 | MOBILIZATION | 1 | L SUM | $38,500.00 | $30,000.00 | $41,500.00 | $21,065.00 | |
| 42 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $8,674.14 | $10,000.00 | $31,091.85 | $8,650.00 | |
| 43 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $100.00 | $0.0100 | $100.00 | |
| 44 | 70300100 | SHORT TERM PAVT MKING | 925 | FOOT | $1.87 | $1.50 | $0.0100 | $1.00 | |
| 45 | 70300150 | SHRT TRM PAVT MK REM | 308 | SQ FT | $3.10 | $2.50 | $0.0100 | $1.00 | |
| 46 | 70300220 | TEMP PVT MK LINE 4 | 1,250 | FOOT | $0.4500 | $0.4500 | $0.0100 | $0.4500 | |
| 47 | 70300280 | TEMP PVT MK LINE 24 | 336 | FOOT | $2.70 | $2.70 | $0.0100 | $2.70 | |
| 48 | 78000400 | THPL PVT MK LINE 6 | 2,138 | FOOT | $1.90 | $1.55 | $1.43 | $1.90 | |
| 49 | 78000650 | THPL PVT MK LINE 24 | 336 | FOOT | $3.85 | $7.95 | $6.60 | $3.85 |