60B-1
- Let date
- Friday, July 15, 2022
- Contract
- 76J90
- District
- District 8
- County
- Madison
- Highway
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Walsh Construction Company II, LLC Low bidder | $496,247,509 | ||
| 2 | Massman Construction Co. and Traylor Bros., Inc. Joint Venture | $576,380,935 | +16.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Walsh Construct… | #2 Massman Constru… |
|---|---|---|---|---|---|---|---|
| 1 | X0301847 | WATER TRANSPORT- ENGR | 40 | CAL MO | $0.0100 | $2,175.00 | |
| 2 | X0320023 | CCTV DOME CAMERA HD | 3 | EACH | $4,692.00 | $4,690.00 | |
| 3 | X0320051 | CROS SONIC LOG A DUCT | 11,868 | FOOT | $85.98 | $240.00 | |
| 4 | X0320052 | CROS SONIC LOG TEST | 150 | EACH | $1,521.97 | $7,500.00 | |
| 5 | X0322916 | PRO SS CONN TO EX SS | 1 | EACH | $1,075.00 | $1,075.00 | |
| 6 | X0322936 | REMOV EX FLAR END SEC | 18 | EACH | $330.00 | $330.00 | |
| 7 | X0324256 | FIB OPTIC C SPLICE | 1 | EACH | $5,335.00 | $5,335.00 | |
| 8 | X0324597 | CCTV CABINET | 3 | EACH | $4,695.00 | $4,695.00 | |
| 9 | X0325077 | FIB OPT UTILIT MARKER | 24 | EACH | $148.00 | $148.00 | |
| 10 | X0325464 | OSS BUTFLY TY II-F-A | 20.5 | FOOT | $3,610.00 | $4,610.00 | |
| 11 | X0326812 | CAT 5 ETHERNET CABLE | 155 | FOOT | $3.70 | $3.70 | |
| 12 | X0327121 | CAMERA POLE 55 FT | 2 | EACH | $9,384.00 | $9,384.00 | |
| 13 | X0327357 | CONSTRN VBRN MONITRNG | 1 | L SUM | $240,000.00 | $705,000.00 | |
| 14 | X0900020 | THML INTGRTY PROF TST | 16 | EACH | $8,406.48 | $1,191.00 | |
| 15 | X0900044 | THML NTGRTY PROF DATA | 11,868 | FOOT | $74.51 | $255.00 | |
| 16 | X1400308 | REM CCTV CAMERA | 2 | EACH | $589.56 | $590.00 | |
| 17 | X1500006 | BIT SURF TREATMNT A3 | 1,528 | SQ YD | $21.65 | $21.65 | |
| 18 | X1700063 | CONCRETE HEADWALL SPL | 35 | EACH | $2,948.71 | $2,950.00 | |
| 19 | X2080250 | TRENCH BACKFILL SPL | 7,310 | CU YD | $15.30 | $15.30 | |
| 20 | X4400110 | TEMP PAVT REMOVAL | 23,544 | SQ YD | $27.50 | $27.50 | |
| 21 | X5030250 | BR DECK GROOVING LONG | 46,030 | SQ YD | $3.59 | $5.50 | |
| 22 | X5051401 | F&E STRUCT STL BR N1 | 1 | L SUM | $90,209,081.42 | $44,500,000.00 | |
| 23 | X5051402 | F&E STRUCT STL BR N2 | 1 | L SUM | $72,250,000.00 | $40,870,000.00 | |
| 24 | X5210235 | HLMR BRG GUID EX 850 | 48 | EACH | $23,224.57 | $24,000.00 | |
| 25 | X5210240 | HLMR BRG GUID EXP 900 | 26 | EACH | $23,292.24 | $21,000.00 | |
| 26 | X5210345 | HLMR BRNG FIXED 550K | 28 | EACH | $8,446.92 | $12,000.00 | |
| 27 | X5210375 | HLMR BRNG FIXED 850K | 108 | EACH | $14,619.22 | $22,000.00 | |
| 28 | X5210380 | HLMR BRNG FIXED 900K | 49 | EACH | $14,793.21 | $25,000.00 | |
| 29 | X5509900 | ABANDON FILL SS | 1,609 | FOOT | $29.50 | $29.50 | |
| 30 | X6015000 | REM CONC HDWL P DRNS | 35 | EACH | $197.80 | $198.00 | |
| 31 | X6024503 | INLET ADJ NEW F&G SPL | 4 | EACH | $2,390.00 | $2,390.00 | |
| 32 | X6650202 | WOV W FENCE REMOV | 4,256 | FOOT | $8.25 | $8.25 | |
| 33 | X6660117 | REM RE-E ROW MARKERS | 1 | EACH | $1,870.00 | $1,870.00 | |
| 34 | X6700410 | ENGR FLD OFF A SPL | 48 | CAL MO | $8,898.12 | $11,400.00 | |
| 35 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $798,040.00 | $800,000.00 | |
| 36 | X7030040 | WET REF TEM TAPE T3 6 | 231,283 | FOOT | $1.94 | $2.00 | |
| 37 | X8710075 | FO CAB C 72 SM FO | 11,170 | FOOT | $3.83 | $3.80 | |
| 38 | Z0004552 | APPROACH SLAB REM | 219 | SQ YD | $110.00 | $110.00 | |
| 39 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $9,800.00 | $9,800.00 | |
| 40 | Z0010615 | CLEAN EX INLETS | 8 | EACH | $3,360.00 | $3,360.00 | |
| 41 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,286,800.01 | $550,000.00 | |
| 42 | Z0016200 | DECK SLAB REP (PART) | 3,240 | SQ YD | $515.45 | $516.00 | |
| 43 | Z0018002 | DRAINAGE SCUPPR DS-11 | 166 | EACH | $2,402.96 | $2,600.00 | |
| 44 | Z0021500 | EXPANSION JOINT 3 | 74 | FOOT | $187.15 | $188.00 | |
| 45 | Z0029090 | DIAMOND GRIND BR SEC | 66,537 | SQ YD | $6.20 | $8.00 | |
| 46 | Z0033052 | COMMUNICATIONS VAULT | 1 | EACH | $3,315.00 | $3,315.00 | |
| 47 | Z0034396 | MODULAR EXPAN JT 12 | 132 | FOOT | $2,585.11 | $2,520.00 | |
| 48 | Z0034500 | MODULAR EXPAN JT 18 | 116 | FOOT | $3,344.84 | $3,335.00 | |
| 49 | Z0034706 | MODULAR EXPAN JT 27 | 232 | FOOT | $5,642.27 | $7,480.00 | |
| 50 | Z0040530 | PIPE UNDERDRAIN REMOV | 21,977 | FOOT | $1.95 | $1.95 | |
| 51 | Z0062456 | TEMP PAVEMENT | 25,821 | SQ YD | $128.52 | $129.00 | |
| 52 | Z0076600 | TRAINEES | 3,000 | HOUR | $0.8000 | $0.8000 | |
| 53 | Z0076604 | TRAINEES TPG | 3,000 | HOUR | $15.00 | $15.00 | |
| 54 | Z0076870 | UNDR CONNECT TO STR | 39 | EACH | $621.10 | $622.00 | |
| 55 | 20100500 | TREE REMOV ACRES | 3.25 | ACRE | $26,650.00 | $27,000.00 | |
| 56 | 20200100 | EARTH EXCAVATION | 159,310 | CU YD | $22.61 | $25.00 | |
| 57 | 20400800 | FURNISHED EXCAVATION | 27,325 | CU YD | $7.65 | $7.65 | |
| 58 | 20800150 | TRENCH BACKFILL | 2,659 | CU YD | $55.00 | $55.00 | |
| 59 | 25000305 | SEEDING CL 3A | 24.75 | ACRE | $2,220.00 | $2,220.00 | |
| 60 | 25000400 | NITROGEN FERT NUTR | 2,226 | POUND | $7.14 | $7.15 | |
| 61 | 25000500 | PHOSPHORUS FERT NUTR | 2,226 | POUND | $7.14 | $7.15 | |
| 62 | 25000600 | POTASSIUM FERT NUTR | 2,226 | POUND | $7.14 | $7.15 | |
| 63 | 25000700 | AGR GROUND LIMESTONE | 49.5 | TON | $204.00 | $204.00 | |
| 64 | 25100127 | MULCH METHOD 3A | 49.5 | ACRE | $2,014.50 | $2,015.00 | |
| 65 | 25100635 | HD EROS CONTR BLANKET | 23,906 | SQ YD | $4.08 | $4.00 | |
| 66 | 28000250 | TEMP EROS CONTR SEED | 8,157 | POUND | $4.08 | $4.00 | |
| 67 | 28000305 | TEMP DITCH CHECKS | 620 | FOOT | $18.50 | $18.50 | |
| 68 | 28000400 | PERIMETER EROS BAR | 21,313 | FOOT | $2.90 | $2.90 | |
| 69 | 28000510 | INLET FILTERS | 95 | EACH | $297.00 | $297.00 | |
| 70 | 28100107 | STONE RIPRAP CL A4 | 14,645 | SQ YD | $43.52 | $44.00 | |
| 71 | 28100111 | STONE RIPRAP CL A6 | 17,095 | SQ YD | $108.58 | $83.00 | |
| 72 | 28200200 | FILTER FABRIC | 31,740 | SQ YD | $3.00 | $3.00 | |
| 73 | 31100910 | SUB GRAN MAT A 12 | 71,194 | SQ YD | $27.65 | $27.65 | |
| 74 | 31200100 | STAB SUBBASE 4 | 71,194 | SQ YD | $33.00 | $33.00 | |
| 75 | 35100700 | AGG BASE CSE A 8 | 1,528 | SQ YD | $14.45 | $14.45 | |
| 76 | 42100340 | CONT REINF PCC PVT 12 | 39,642 | SQ YD | $96.00 | $96.00 | |
| 77 | 42100615 | PAVT REINFORCEMENT | 39,642 | SQ YD | $48.25 | $48.25 | |
| 78 | 42100990 | WF BM TERM JT COMP 12 | 2 | EACH | $51,000.00 | $51,000.00 | |
| 79 | 42101030 | WF BM TERM JT COMP 36 | 2 | EACH | $151,980.00 | $152,000.00 | |
| 80 | 42101300 | PROTECTIVE COAT | 81,229 | SQ YD | $1.84 | $1.85 | |
| 81 | 44000100 | PAVEMENT REM | 22,269 | SQ YD | $27.00 | $27.00 | |
| 82 | 44001980 | CONC BARRIER REMOV | 2,652 | FOOT | $16.50 | $16.50 | |
| 83 | 44004250 | PAVED SHLD REMOVAL | 26,828 | SQ YD | $17.50 | $17.50 | |
| 84 | 44200050 | WELDED WIRE REINF | 181 | SQ YD | $9.15 | $9.15 | |
| 85 | 44201031 | CL B PATCH T2 15 | 236 | SQ YD | $287.90 | $288.00 | |
| 86 | 44201035 | CL B PATCH T3 15 | 100 | SQ YD | $287.90 | $288.00 | |
| 87 | 44201037 | CL B PATCH T4 15 | 81 | SQ YD | $287.90 | $288.00 | |
| 88 | 44201299 | DOWEL BARS 1 1/2 | 600 | EACH | $33.90 | $34.00 | |
| 89 | 44213200 | SAW CUTS | 9,907 | FOOT | $7.14 | $7.15 | |
| 90 | 48300700 | PCC SHOULDERS 12 | 33,313 | SQ YD | $96.00 | $96.00 | |
| 91 | 50100100 | REM EXIST STRUCT | 1 | EACH | $53,947,280.35 | $7,000,000.00 | |
| 92 | 50200100 | STRUCTURE EXCAVATION | 1,295 | CU YD | $26.45 | $41.75 | |
| 93 | 50300100 | FLOOR DRAINS | 24 | EACH | $985.21 | $1,000.00 | |
| 94 | 50300225 | CONC STRUCT | 25,481.4 | CU YD | $1,285.94 | $3,800.00 | |
| 95 | 50300255 | CONC SUP-STR | 21,840.2 | CU YD | $1,678.10 | $4,100.00 | |
| 96 | 50300280 | CONCRETE ENCASEMENT | 29.4 | CU YD | $1,090.15 | $1,100.00 | |
| 97 | 50300300 | PROTECTIVE COAT | 80,565 | SQ YD | $0.6300 | $3.00 | |
| 98 | 50301350 | CONC SUPSTR APP SLAB | 347 | CU YD | $357.80 | $357.00 | |
| 99 | 50500505 | STUD SHEAR CONNECTORS | 195,364 | EACH | $5.82 | $5.00 | |
| 100 | 50800205 | REINF BARS, EPOXY CTD | 22,647,000 | POUND | $1.73 | $2.20 | |
| 101 | 50800530 | MECHANICAL SPLICERS | 14,948 | EACH | $264.13 | $250.00 | |
| 102 | 51201610 | FUR STL PILE HP12X63 | 4,197 | FOOT | $93.15 | $95.00 | |
| 103 | 51201710 | FUR STL PILE HP12X84 | 2,260 | FOOT | $113.15 | $116.00 | |
| 104 | 51202305 | DRIVING PILES | 6,457 | FOOT | $0.0200 | $0.0200 | |
| 105 | 51203610 | TEST PILE ST HP12X63 | 2 | EACH | $10,890.00 | $10,900.00 | |
| 106 | 51203710 | TEST PILE ST HP12X84 | 4 | EACH | $11,415.00 | $11,500.00 | |
| 107 | 51204650 | PILE SHOES | 84 | EACH | $155.00 | $155.00 | |
| 108 | 51500100 | NAME PLATES | 2 | EACH | $797.80 | $800.00 | |
| 109 | 51602000 | PERMANENT CASING | 8,854 | FOOT | $2,873.06 | $1,100.00 | |
| 110 | 51603000 | DRILLED SHAFT IN SOIL | 20,137 | CU YD | $1,289.87 | $5,000.00 | |
| 111 | 51604000 | DRILLED SHAFT IN ROCK | 7,000 | CU YD | $4,534.93 | $5,500.00 | |
| 112 | 52000110 | PREF JT STRIP SEAL | 255 | FOOT | $337.80 | $533.00 | |
| 113 | 52100010 | ELAST BEARING ASSY T1 | 52 | EACH | $3,779.50 | $4,000.00 | |
| 114 | 52100030 | ELAST BEARING ASSY T3 | 74 | EACH | $7,424.51 | $16,000.00 | |
| 115 | 52100530 | ANCHOR BOLTS 1 1/4 | 820 | EACH | $144.64 | $350.00 | |
| 116 | 52100540 | ANCHOR BOLTS 1 1/2 | 168 | EACH | $179.11 | $375.00 | |
| 117 | 52100560 | ANCHOR BOLTS 2 | 312 | EACH | $287.37 | $750.00 | |
| 118 | 52200010 | TEMP SHT PILING | 7,485 | SQ FT | $29.85 | $30.00 | |
| 119 | 54213663 | PRC FLAR END SEC 18 | 1 | EACH | $1,070.00 | $1,070.00 | |
| 120 | 54213669 | PRC FLAR END SEC 24 | 5 | EACH | $1,350.00 | $1,350.00 | |
| 121 | 550A0360 | STORM SEW CL A 2 15 | 1,327 | FOOT | $64.00 | $64.00 | |
| 122 | 550A0380 | STORM SEW CL A 2 18 | 1,349 | FOOT | $71.50 | $71.50 | |
| 123 | 550A0410 | STORM SEW CL A 2 24 | 2,300 | FOOT | $113.00 | $113.00 | |
| 124 | 550B0070 | STORM SEW CL B 1 15 | 224 | FOOT | $59.75 | $60.00 | |
| 125 | 55100700 | STORM SEWER REM 15 | 142 | FOOT | $22.00 | $22.00 | |
| 126 | 55101200 | STORM SEWER REM 24 | 31 | FOOT | $23.00 | $23.00 | |
| 127 | 55200600 | STORM SEWERS JKD 18 | 80 | FOOT | $0.0100 | $1,137.00 | |
| 128 | 55200900 | STORM SEWERS JKD 24 | 91 | FOOT | $0.0100 | $1,392.00 | |
| 129 | 58600101 | GRANULAR BACKFILL STR | 675 | CU YD | $46.90 | $50.00 | |
| 130 | 58700300 | CONCRETE SEALER | 52,617 | SQ FT | $2.50 | $2.00 | |
| 131 | 59100100 | GEOCOMPOSITE WALL DR | 378 | SQ YD | $43.15 | $45.00 | |
| 132 | 60108106 | PIPE UNDERDR T 1 6 | 21,977 | FOOT | $15.90 | $16.00 | |
| 133 | 60108300 | PIPE UNDERDRAIN 8 SP | 700 | FOOT | $45.50 | $46.00 | |
| 134 | 60146304 | P UNDR FOR STRUCT 4 | 350 | FOOT | $29.80 | $30.00 | |
| 135 | 60218400 | MAN TA 4 DIA T1F CL | 1 | EACH | $3,545.00 | $3,500.00 | |
| 136 | 60270050 | DR STR T4 W/2 T20F&G | 28 | EACH | $7,785.00 | $7,785.00 | |
| 137 | 60270055 | DR STR T5 W/2 T22F&G | 6 | EACH | $11,045.00 | $11,000.00 | |
| 138 | 60500040 | REMOV MANHOLES | 3 | EACH | $845.00 | $845.00 | |
| 139 | 60500050 | REMOV CATCH BAS | 2 | EACH | $845.00 | $845.00 | |
| 140 | 60500060 | REMOV INLETS | 8 | EACH | $330.00 | $330.00 | |
| 141 | 63000001 | SPBGR TY A 6FT POSTS | 13,990 | FOOT | $34.17 | $34.00 | |
| 142 | 63100070 | TRAF BAR TERM T5 | 2 | EACH | $1,364.00 | $1,364.00 | |
| 143 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $4,284.00 | $4,284.00 | |
| 144 | 63200310 | GUARDRAIL REMOV | 23,073 | FOOT | $4.41 | $4.40 | |
| 145 | 63500105 | DELINEATORS | 58 | EACH | $55.85 | $55.85 | |
| 146 | 63700280 | CONC BAR 2F 44HT | 5,737 | FOOT | $127.15 | $127.00 | |
| 147 | 63700380 | CONC BAR VX 44HT | 1,253 | FOOT | $131.65 | $132.00 | |
| 148 | 63700805 | CONC BAR TRANS | 46 | FOOT | $387.90 | $388.00 | |
| 149 | 63700900 | CONC BARRIER BASE | 7,035 | FOOT | $26.80 | $26.00 | |
| 150 | 64200116 | SHOULDER RUM STRIP 16 | 24,250 | FOOT | $0.2600 | $0.2600 | |
| 151 | 64300770 | IMP ATTEN SU NAR TL3 | 2 | EACH | $35,598.00 | $35,000.00 | |
| 152 | 66400205 | CH LK FENCE 5 | 150 | FOOT | $55.59 | $55.00 | |
| 153 | 66406500 | CH LK GATES 5X8 DBL | 1 | EACH | $734.40 | $735.00 | |
| 154 | 66500105 | WOV W FENCE 4 | 4,769 | FOOT | $12.75 | $13.00 | |
| 155 | 66501200 | WOV W GATES 4X8 DBL | 1 | EACH | $714.00 | $715.00 | |
| 156 | 66600105 | FUR ERECT ROW MARKERS | 21 | EACH | $695.00 | $695.00 | |
| 157 | 66700205 | PERM SURV MKRS T1 | 14 | EACH | $987.15 | $987.00 | |
| 158 | 66900200 | NON SPL WASTE DISPOSL | 2,000 | CU YD | $66.54 | $67.00 | |
| 159 | 66900400 | SPL WAST GRD WAT DISP | 200 | GALLON | $19.74 | $20.00 | |
| 160 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,244.94 | $1,500.00 | |
| 161 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,192.14 | $4,000.00 | |
| 162 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $3,319.82 | $4,000.00 | |
| 163 | 66901006 | REG SUB MON | 115 | CAL DA | $1,053.41 | $1,100.00 | |
| 164 | 67000600 | ENGR FIELD LAB | 48 | CAL MO | $1,672.60 | $1,600.00 | |
| 165 | 67100100 | MOBILIZATION | 1 | L SUM | $29,700,000.00 | $34,700,000.00 | |
| 166 | 70107025 | CHANGEABLE MESSAGE SN | 6,080 | CAL DA | $27.54 | $28.00 | |
| 167 | 70400100 | TEMP CONC BARRIER | 43,274 | FOOT | $20.00 | $20.00 | |
| 168 | 70400200 | REL TEMP CONC BARRIER | 60,207 | FOOT | $12.45 | $12.50 | |
| 169 | 70600250 | IMP ATTN TEMP NRD TL3 | 3 | EACH | $2,790.30 | $2,800.00 | |
| 170 | 70600350 | IMP ATTN REL NRD TL3 | 8 | EACH | $1,570.00 | $1,570.00 | |
| 171 | 72000200 | SIGN PANEL T2 | 82.5 | SQ FT | $27.77 | $27.00 | |
| 172 | 72000300 | SIGN PANEL T3 | 2,518.75 | SQ FT | $28.31 | $28.00 | |
| 173 | 72400310 | REMOV SIGN PANEL T1 | 165 | SQ FT | $8.61 | $8.50 | |
| 174 | 72400320 | REMOV SIGN PANEL T2 | 66.5 | SQ FT | $8.61 | $8.50 | |
| 175 | 72400330 | REMOV SIGN PANEL T3 | 1,312.75 | SQ FT | $4.31 | $4.30 | |
| 176 | 72400710 | RELOC SIGN PANEL T1 | 18 | SQ FT | $24.20 | $24.00 | |
| 177 | 72400720 | RELOC SIGN PANEL T2 | 20 | SQ FT | $24.20 | $24.00 | |
| 178 | 72400730 | RELOC SIGN PANEL T3 | 360 | SQ FT | $12.71 | $13.00 | |
| 179 | 72600100 | MILEPOST MKR ASSEMBLY | 22 | EACH | $1,120.80 | $1,120.00 | |
| 180 | 72700100 | STR STL SIN SUP BA | 9,818.5 | POUND | $1.16 | $1.16 | |
| 181 | 73000100 | WOOD SIN SUPPORT | 52 | FOOT | $41.90 | $41.00 | |
| 182 | 73301810 | OSS WALKWAY TY A | 20.5 | FOOT | $662.92 | $663.00 | |
| 183 | 73400100 | CONC FOUNDATION | 24.28 | CU YD | $1,902.61 | $1,903.00 | |
| 184 | 73700200 | REM CONC FDN-GR MT | 26 | EACH | $430.00 | $430.00 | |
| 185 | 78003101 | PREF PL PM TB STNRD LTR-SYM | 172 | SQ FT | $40.80 | $40.00 | |
| 186 | 78004600 | PREF PL PM TD LTR/SYM | 124.5 | SQ FT | $55.59 | $55.00 | |
| 187 | 78004630 | PREF PL PM TD L 6 | 50,078 | FOOT | $5.56 | $5.50 | |
| 188 | 78004645 | PREF PL PM TD L 9 | 12,520 | FOOT | $10.56 | $10.50 | |
| 189 | 78004655 | PREF PL PM TD L 11 | 312 | FOOT | $17.09 | $17.00 | |
| 190 | 78011035 | GRV RCSD PVT MRKG 7 | 50,078 | FOOT | $0.3600 | $0.3600 | |
| 191 | 78011050 | GRV RCSD PVT MRKG 10 | 12,520 | FOOT | $1.28 | $1.28 | |
| 192 | 78011060 | GRV RCSD PVT MRKG 12 | 312 | FOOT | $1.30 | $1.30 | |
| 193 | 78100100 | RAISED REFL PAVT MKR | 706 | EACH | $46.41 | $46.00 | |
| 194 | 78200005 | GRDRAIL REF TYPE A | 60 | EACH | $15.30 | $15.00 | |
| 195 | 78200011 | BARR WALL REF TYPE C | 120 | EACH | $15.30 | $15.00 | |
| 196 | 78300200 | RAISED REF PVT MK REM | 190 | EACH | $10.20 | $10.00 | |
| 197 | 81028240 | UNDRGRD C GALVS 4 | 320 | FOOT | $51.00 | $51.00 | |
| 198 | 81028390 | UNDRGRD C PVC 4 | 560 | FOOT | $23.00 | $23.00 | |
| 199 | 81100500 | CON AT ST 1 1/2 GALVS | 280 | FOOT | $37.00 | $37.00 | |
| 200 | 81100600 | CON AT ST 2 GALVS | 80 | FOOT | $46.00 | $46.00 | |
| 201 | 81200230 | CON EMB STR 2 PVC | 21,600 | FOOT | $8.20 | $8.00 | |
| 202 | 81300550 | JUN BX SS AS 12X12X6 | 2 | EACH | $1,122.00 | $1,100.00 | |
| 203 | 81300730 | JUN BX SS AS 16X14X6 | 8 | EACH | $1,377.00 | $1,370.00 | |
| 204 | 81400700 | HANDHOLE PCC | 14 | EACH | $1,224.00 | $1,224.00 | |
| 205 | 81603112 | UD2#6#8G XLPUSE 1.25P | 14,125 | FOOT | $8.20 | $8.00 | |
| 206 | 81702120 | EC C XLP USE 1C 8 | 12,050 | FOOT | $1.65 | $1.65 | |
| 207 | 81702130 | EC C XLP USE 1C 6 | 40,804 | FOOT | $1.95 | $1.95 | |
| 208 | 82110007 | LUM LED RDWY G | 146 | EACH | $729.30 | $729.00 | |
| 209 | 83060450 | LT P GS 45MH 15MA | 59 | EACH | $6,528.00 | $6,528.00 | |
| 210 | 83060550 | LT P GS 50MH 15MA | 71 | EACH | $6,222.00 | $6,222.00 | |
| 211 | 83600300 | LIGHT POLE FDN 30D | 511 | FOOT | $235.00 | $235.00 | |
| 212 | 83800205 | BKWY DEV TR B 15BC | 1 | EACH | $653.00 | $653.00 | |
| 213 | 84200500 | REM LT UNIT SALV | 52 | EACH | $408.00 | $408.00 | |
| 214 | 84200600 | REM LT U NO SALV | 45 | EACH | $408.00 | $408.00 | |
| 215 | 84200804 | REM POLE FDN | 54 | EACH | $310.00 | $310.00 | |
| 216 | 87300925 | ELCBL C TRACER 14 1C | 11,170 | FOOT | $5.75 | $5.75 | |
| 217 | 89502210 | MOD EX CONTR CAB | 2 | EACH | $612.00 | $612.00 |