$234.58Avg low bid / EACH
$299.07Avg of all bids
—Avg engineer's estimate
6Jobs · 108 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 3 | 39 | $198.98 | $377.88 |
| 2025 | 3 | 69 | $254.70 | $272.80 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 27, 2026 | 62R23 | WillDistrict 1 | 2 EACH | $3,000.00 | D. Construction, Inc. & Kraemer North America, LLC JV |
| Jan 16, 2026 | 76E84 | Madison, St.clairDistrict 8 | 35 EACH | $0.0100 | The Kilian Corporation & Christ Brothers Asphalt & Keeley & Sons, Inc. tri-venture |
| Jan 16, 2026 | 62F94 | WillDistrict 1 | 2 EACH | $880.00 | D. Construction, Inc. |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 4 EACH | $715.00 | D. Construction, Inc. |
| Jun 13, 2025 | 76K74 | St.clairDistrict 8 | 32 EACH | $290.70 | Keeley & Sons, Inc. Keller Construction Inc. |
| Mar 7, 2025 | 76R99 | St. ClairDistrict 8 | 33 EACH | $164.00 | The Kilian Corporation and Christ Brothers Asphalt |