24-00141-00-RS
- Let date
- Friday, February 27, 2026
- Contract
- 61L87 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- HMA resurfacing of School Street from W 144th Street to W. 138th Street in the Village of Riverdale. Additionally includes curb and gutter, sidewalk and other required work.
- Classification
- ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gallagher Asphalt Corporation Low bidder | $902,962 | ||
| 2 | K-Five Construction Corporation | $942,000 | +4.3% | |
| 3 | D. Construction, Inc. | $952,844 | +5.5% | |
| 4 | M & J Underground Inc. | $1,044,265 | +15.6% | |
| 5 | Everlast Blacktop Inc. | $1,138,920 | +26.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gallagher Aspha… | #2 K-Five Construc… | #3 D. Construction… | #4 M & J Undergrou… | #5 Everlast Blackt… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | LR443200 | STRIP REF CR CON TR | 4,643 | FOOT | $0.0100 | $0.0100 | $3.27 | $4.02 | $4.00 | |
| 2 | XX005206 | EXPLOR EXCAVATION | 5 | FOOT | $37.00 | $100.00 | $0.0100 | $548.20 | $250.00 | |
| 3 | XX006448 | PVC CS PIPE REPL 10" | 30 | FOOT | $130.00 | $225.00 | $500.00 | $167.64 | $185.00 | |
| 4 | XX006821 | CONC TRUCK WASHOUT | 1 | L SUM | $1,200.00 | $500.00 | $2,500.00 | $600.00 | $1,500.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 17,450 | SQ YD | $2.90 | $4.00 | $3.00 | $6.03 | $3.79 | |
| 6 | X4404400 | PAVT REMOVAL SPL | 50 | SQ YD | $27.30 | $50.00 | $0.0100 | $22.10 | $25.00 | |
| 7 | X6020399 | CONNECT EX MANHOLE | 1 | EACH | $400.00 | $1,232.00 | $3,500.00 | $2,286.07 | $4,500.00 | |
| 8 | X6030310 | FR & LIDS ADJUST SPL | 10 | EACH | $725.00 | $1,250.00 | $900.00 | $1,627.85 | $1,250.00 | |
| 9 | X7200061 | TEMP INFO SIGNING | 52 | SQ FT | $16.40 | $15.00 | $30.00 | $36.02 | $35.00 | |
| 10 | X8860105 | DET LOOP REPL | 75 | FOOT | $79.00 | $70.00 | $79.44 | $74.33 | $30.00 | |
| 11 | X8900104 | TEMP TR SIGNAL TIMING | 1 | EACH | $1,750.00 | $1,600.00 | $1,765.50 | $1,440.90 | $6,500.00 | |
| 12 | Z0017400 | DRAIN UTIL STR ADJ | 18 | EACH | $340.00 | $850.00 | $1,000.00 | $458.56 | $950.00 | |
| 13 | 20101100 | TREE TRUNK PROTECTION | 4 | EACH | $760.00 | $135.00 | $330.00 | $126.83 | $770.00 | |
| 14 | 20101200 | TREE ROOT PRUNING | 4 | EACH | $760.00 | $150.00 | $330.00 | $218.28 | $770.00 | |
| 15 | 20200100 | EARTH EXCAVATION | 50 | CU YD | $90.00 | $50.00 | $100.00 | $79.54 | $80.00 | |
| 16 | 20800150 | TRENCH BACKFILL | 6 | CU YD | $90.00 | $23.00 | $150.00 | $88.96 | $100.00 | |
| 17 | 21101615 | TOPSOIL F & P 4 | 1,210 | SQ YD | $13.60 | $9.00 | $13.86 | $3.09 | $6.00 | |
| 18 | 25000110 | SEEDING CL 1A | 0.25 | ACRE | $1,960.00 | $10,440.00 | $8,250.00 | $2,490.69 | $5,000.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 20 | POUND | $27.00 | $4.00 | $3.30 | $3.09 | $3.00 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 20 | POUND | $27.00 | $4.00 | $3.30 | $3.09 | $3.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 20 | POUND | $27.00 | $4.00 | $3.30 | $3.09 | $3.00 | |
| 22 | 25100630 | EROSION CONTR BLANKET | 1,210 | SQ YD | $13.60 | $1.00 | $2.15 | $25.73 | $2.00 | |
| 23 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $19.60 | $4.00 | $11.00 | $51.46 | $5.00 | |
| 24 | 28000510 | INLET FILTERS | 25 | EACH | $150.00 | $200.00 | $319.00 | $210.18 | $160.00 | |
| 25 | 35800100 | PREPARATION OF BASE | 17,450 | SQ YD | $0.0100 | $0.9000 | $1.75 | $1.61 | $2.00 | |
| 26 | 35800200 | AGG BASE REPAIR | 40 | TON | $60.00 | $40.00 | $40.00 | $42.18 | $60.00 | |
| 27 | 40600290 | BIT MATLS TACK CT | 8,100 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 28 | 40600370 | LONG JOINT SEALANT | 5,000 | FOOT | $3.90 | $4.50 | $4.22 | $4.92 | $3.75 | |
| 29 | 40600400 | MIX CR JTS FLANGEWYS | 20 | TON | $200.00 | $50.00 | $0.0100 | $0.0100 | $250.00 | |
| 30 | 40600982 | HMA SURF REM BUTT JT | 190 | SQ YD | $60.00 | $30.00 | $0.0100 | $0.0100 | $25.00 | |
| 31 | 40602978 | HMA BC IL-9.5 N50 | 1,550 | TON | $86.00 | $93.00 | $74.50 | $94.41 | $90.61 | |
| 32 | 40604060 | HMA SC IL-9.5 D N50 | 1,825 | TON | $86.00 | $93.00 | $78.50 | $98.43 | $93.17 | |
| 33 | 40800050 | INCIDENTAL HMA SURF | 7 | TON | $250.00 | $1,500.00 | $150.00 | $502.18 | $150.00 | |
| 34 | 42000300 | PCC PVT 8 | 120 | SQ YD | $90.00 | $110.00 | $90.00 | $130.66 | $145.00 | |
| 35 | 42101300 | PROTECTIVE COAT | 1,730 | SQ YD | $0.0100 | $1.00 | $1.00 | $1.10 | $3.00 | |
| 36 | 42300300 | PCC DRIVEWAY PAVT 7 | 210 | SQ YD | $90.00 | $80.00 | $85.00 | $113.73 | $130.00 | |
| 37 | 42400200 | PC CONC SIDEWALK 5 | 8,580 | SQ FT | $7.00 | $9.50 | $10.00 | $7.70 | $12.50 | |
| 38 | 42400800 | DETECTABLE WARNINGS | 550 | SQ FT | $20.00 | $20.00 | $35.00 | $24.09 | $45.00 | |
| 39 | 44000100 | PAVEMENT REM | 120 | SQ YD | $28.00 | $22.00 | $25.00 | $50.19 | $5.00 | |
| 40 | 44000161 | HMA SURF REM 3 | 45 | SQ YD | $38.00 | $4.25 | $10.00 | $22.10 | $5.00 | |
| 41 | 44000200 | DRIVE PAVEMENT REM | 255 | SQ YD | $28.00 | $20.00 | $12.00 | $30.51 | $18.00 | |
| 42 | 44000500 | COMB CURB GUTTER REM | 2,220 | FOOT | $17.00 | $10.00 | $10.00 | $13.10 | $12.00 | |
| 43 | 44000600 | SIDEWALK REM | 8,580 | SQ FT | $3.00 | $1.50 | $2.00 | $2.82 | $2.50 | |
| 44 | 44201705 | CL D PATCH T2 5 | 500 | SQ YD | $45.00 | $17.00 | $55.00 | $35.15 | $64.00 | |
| 45 | 44201709 | CL D PATCH T3 5 | 500 | SQ YD | $35.00 | $17.00 | $50.00 | $35.15 | $66.00 | |
| 46 | 44201711 | CL D PATCH T4 5 | 500 | SQ YD | $25.00 | $34.00 | $50.00 | $35.15 | $68.00 | |
| 47 | 56500600 | DOM WAT SER BOX ADJ | 2 | EACH | $250.00 | $350.00 | $400.00 | $237.30 | $850.00 | |
| 48 | 60200105 | CB TA 4 DIA T1F OL | 1 | EACH | $4,500.00 | $8,950.00 | $4,500.00 | $3,220.12 | $8,000.00 | |
| 49 | 60234200 | INLETS TA T1F OL | 1 | EACH | $240.00 | $3,685.00 | $2,200.00 | $2,137.19 | $6,800.00 | |
| 50 | 60406000 | FR & LIDS T1 OL | 11 | EACH | $360.00 | $485.00 | $600.00 | $364.81 | $1,150.00 | |
| 51 | 60406100 | FR & LIDS T1 CL | 6 | EACH | $360.00 | $485.00 | $600.00 | $364.81 | $1,250.00 | |
| 52 | 60604100 | COMB CC&G TB6.12 MOD | 2,220 | FOOT | $30.00 | $30.00 | $32.00 | $47.89 | $40.00 | |
| 53 | 66900200 | NON SPL WASTE DISPOSL | 12 | CU YD | $175.00 | $125.00 | $200.00 | $104.19 | $80.00 | |
| 54 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,580.00 | $1,450.00 | $1,595.00 | $2,032.69 | $2,200.00 | |
| 55 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,378.00 | $3,100.00 | $3,410.00 | $2,367.19 | $2,500.00 | |
| 56 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,308.00 | $1,200.00 | $1,320.00 | $2,161.35 | $2,300.00 | |
| 57 | 66901006 | REG SUB MON | 15 | CAL DA | $740.00 | $680.00 | $750.00 | $1,024.07 | $1,100.00 | |
| 58 | 67100100 | MOBILIZATION | 1 | L SUM | $54,000.00 | $59,044.32 | $57,170.00 | $33,561.94 | $53,501.62 | |
| 59 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $40,000.00 | $40,000.00 | $33,680.00 | $6,689.88 | $12,050.00 | |
| 60 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $2,350.00 | $1.00 | $0.0100 | $514.61 | $1.00 | |
| 61 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $2,350.00 | $1.00 | $0.0100 | $514.61 | $11,500.00 | |
| 62 | 70300100 | SHORT TERM PAVT MKING | 1,700 | FOOT | $0.0100 | $3.00 | $0.0100 | $1.51 | $1.50 | |
| 63 | 70300150 | SHRT TRM PAVT MK REM | 575 | SQ FT | $0.0100 | $4.00 | $0.0100 | $1.52 | $3.00 | |
| 64 | 72000100 | SIGN PANEL T1 | 28 | SQ FT | $41.00 | $37.50 | $27.50 | $36.02 | $45.00 | |
| 65 | 72900100 | METAL POST TY A | 28 | FOOT | $27.00 | $25.00 | $14.30 | $15.44 | $18.00 | |
| 66 | 78000100 | THPL PVT MK LTR & SYM | 190 | SQ FT | $6.50 | $6.00 | $6.60 | $6.18 | $18.00 | |
| 67 | 78000200 | THPL PVT MK LINE 4 | 8,230 | FOOT | $0.5000 | $0.5000 | $0.5500 | $0.5100 | $1.10 | |
| 68 | 78000400 | THPL PVT MK LINE 6 | 1,280 | FOOT | $1.10 | $1.00 | $1.10 | $1.03 | $2.20 | |
| 69 | 78000600 | THPL PVT MK LINE 12 | 910 | FOOT | $3.25 | $3.00 | $3.30 | $3.09 | $6.00 | |
| 70 | 78000650 | THPL PVT MK LINE 24 | 420 | FOOT | $6.55 | $6.00 | $6.60 | $6.18 | $7.00 | |
| 71 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $3,815.00 | $3,500.00 | $3,850.00 | $1,651.89 | $3,000.00 | |
| 72 | 87301305 | ELCBL C LEAD 14 1PR | 25 | FOOT | $3.75 | $3.00 | $3.77 | $3.53 | $50.00 | |
| 73 | 89502300 | REM ELCBL FR CON | 25 | FOOT | $1.20 | $1.00 | $1.21 | $1.13 | $50.00 |