23-00099-00-SW
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D'Land Construction, LLC Low bidder | $246,136 | ||
| 2 | Triggi Construction, Inc. | $268,695 | +9.2% | |
| 3 | Alliance Contractors, Inc. | $275,504 | +11.9% | |
| 4 | Sjostrom & Sons, Inc. | $309,229 | +25.6% | |
| 5 | Copenhaver Construction, Inc. | $335,918 | +36.5% | |
| 6 | Landmark Contractors, Inc. | $339,715 | +38.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D'Land Construc… | #2 Triggi Construc… | #3 Alliance Contra… | #4 Sjostrom & Sons… | #5 Copenhaver Cons… | #6 Landmark Contra… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4240800 | DETECTABLE WARN SPL | 340 | SQ FT | $40.00 | $35.00 | $40.00 | $25.00 | $50.00 | $37.50 | |
| 2 | X6060074 | COMB CC&G TM SPL AEP | 353 | FOOT | $55.00 | $45.00 | $84.85 | $65.00 | $39.00 | $106.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,100.00 | $9,750.00 | $6,500.00 | $8,800.00 | $15,000.00 | $6,500.00 | |
| 4 | Z0017400 | DRAIN UTIL STR ADJ | 4 | EACH | $550.00 | $500.00 | $250.00 | $325.00 | $600.00 | $410.65 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 155 | SQ FT | $22.00 | $20.00 | $12.00 | $15.15 | $15.00 | $12.00 | |
| 6 | Z0051500 | REM & RESET ST SIGNS | 6 | EACH | $420.00 | $500.00 | $400.00 | $315.00 | $300.00 | $250.00 | |
| 7 | 20101100 | TREE TRUNK PROTECTION | 17 | EACH | $100.00 | $200.00 | $185.00 | $346.20 | $100.00 | $185.00 | |
| 8 | 20101200 | TREE ROOT PRUNING | 17 | EACH | $121.00 | $200.00 | $110.00 | $200.00 | $10.00 | $175.00 | |
| 9 | 20101300 | TREE PRUN 1-10 | 5 | EACH | $104.50 | $100.00 | $95.00 | $220.31 | $20.00 | $150.00 | |
| 10 | 20101350 | TREE PRUN OVER 10 | 12 | EACH | $231.00 | $200.00 | $210.00 | $260.00 | $30.00 | $180.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 178 | CU YD | $55.00 | $100.00 | $20.00 | $126.00 | $79.00 | $114.55 | |
| 12 | 21101615 | TOPSOIL F & P 4 | 1,023 | SQ YD | $8.25 | $0.1000 | $7.50 | $0.1500 | $6.00 | $7.50 | |
| 13 | 25000110 | SEEDING CL 1A | 0.25 | ACRE | $5,500.00 | $40,000.00 | $5,000.00 | $48,775.00 | $5,000.00 | $5,000.00 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $3.00 | $1.00 | $3.00 | $1.26 | $1.00 | $3.00 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $3.00 | $1.00 | $3.00 | $1.26 | $1.00 | $3.00 | |
| 16 | 25100630 | EROSION CONTR BLANKET | 1,023 | SQ YD | $2.00 | $3.00 | $1.75 | $4.00 | $3.00 | $1.75 | |
| 17 | 28000510 | INLET FILTERS | 36 | EACH | $180.00 | $200.00 | $50.00 | $275.00 | $200.00 | $280.00 | |
| 18 | 35101600 | AGG BASE CSE B 4 | 714 | SQ YD | $8.00 | $15.00 | $7.25 | $37.00 | $10.00 | $27.45 | |
| 19 | 40600290 | BIT MATLS TACK CT | 55 | POUND | $50.00 | $1.00 | $0.0100 | $6.00 | $60.00 | $0.0100 | |
| 20 | 40604060 | HMA SC IL-9.5 D N50 | 5 | TON | $800.00 | $750.00 | $1,000.00 | $882.00 | $700.00 | $2,750.00 | |
| 21 | 40800050 | INCIDENTAL HMA SURF | 5 | TON | $800.00 | $750.00 | $1,000.00 | $882.00 | $700.00 | $2,750.00 | |
| 22 | 42400200 | PC CONC SIDEWALK 5 | 6,425 | SQ FT | $13.50 | $13.50 | $16.30 | $13.00 | $16.00 | $14.25 | |
| 23 | 44000100 | PAVEMENT REM | 39 | SQ YD | $35.00 | $25.00 | $20.00 | $27.00 | $40.00 | $91.15 | |
| 24 | 44000155 | HMA SURF REM 1 1/2 | 44 | SQ YD | $140.00 | $55.00 | $100.00 | $175.00 | $137.00 | $151.70 | |
| 25 | 44000500 | COMB CURB GUTTER REM | 353 | FOOT | $10.00 | $20.00 | $15.00 | $25.00 | $15.00 | $32.60 | |
| 26 | 44000600 | SIDEWALK REM | 2,278 | SQ FT | $2.00 | $5.00 | $2.00 | $4.65 | $5.00 | $4.15 | |
| 27 | 60260300 | INLETS ADJ NEW T1F OL | 2 | EACH | $800.00 | $1,000.00 | $725.00 | $315.00 | $790.00 | $810.40 | |
| 28 | 60266600 | VALVE BOX ADJ | 2 | EACH | $250.00 | $250.00 | $100.00 | $315.00 | $200.00 | $253.65 | |
| 29 | 66900200 | NON SPL WASTE DISPOSL | 35 | CU YD | $85.00 | $100.00 | $89.80 | $165.00 | $170.00 | $150.00 | |
| 30 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,760.00 | $1,500.00 | $1,500.00 | $2,014.25 | $3,000.00 | $1,500.00 | |
| 31 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,850.00 | $3,500.00 | $2,900.00 | $4,406.00 | $5,000.00 | $2,900.00 | |
| 32 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $880.00 | $500.00 | $900.00 | $1,008.00 | $2,000.00 | $900.00 | |
| 33 | 66901006 | REG SUB MON | 1 | CAL DA | $1,210.00 | $700.00 | $750.00 | $1,384.00 | $800.00 | $750.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $14,000.00 | $5,000.00 | $17,000.00 | $17,900.00 | $21,000.00 | $27,820.00 | |
| 35 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $6,250.00 | $20,500.00 | $22,487.60 | $7,082.00 | $49,000.00 | $5,625.00 | |
| 36 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $2,750.00 | $100.00 | $1.00 | $1.25 | $500.00 | $1.00 | |
| 37 | 72000100 | SIGN PANEL T1 | 23 | SQ FT | $33.00 | $25.00 | $25.00 | $3.00 | $30.00 | $26.00 | |
| 38 | 72900200 | METAL POST TY B | 45 | FOOT | $20.00 | $15.00 | $22.00 | $23.00 | $22.00 | $18.00 | |
| 39 | 78000400 | THPL PVT MK LINE 6 | 875 | FOOT | $2.20 | $1.75 | $1.72 | $2.25 | $4.00 | $1.72 | |
| 40 | 78000600 | THPL PVT MK LINE 12 | 880 | FOOT | $4.40 | $4.25 | $4.25 | $5.35 | $6.00 | $4.25 | |
| 41 | 78000650 | THPL PVT MK LINE 24 | 89 | FOOT | $11.00 | $8.75 | $8.65 | $11.00 | $12.00 | $8.65 | |
| 42 | 78300202 | PVT MKG REM WTR BLAST | 71 | SQ FT | $50.00 | $45.00 | $44.00 | $60.00 | $60.00 | $50.00 |