19-00091-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | J. A. Johnson Paving Company Low bidder | $871,468 | ||
| 2 | Peter Baker & Son Co. | $990,778 | +13.7% | |
| 3 | Payne & Dolan, Inc. | $1,148,985 | +31.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J. A. Johnson P… | #2 Peter Baker & S… | #3 Payne & Dolan, … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0325714 | FL BEACON P MTD SP IN | 4 | EACH | $7,000.00 | $7,000.00 | $7,000.00 | |
| 2 | X4240430 | PC CONC SIDEWALK 5 SP | 6,820 | SQ FT | $7.50 | $7.50 | $7.50 | |
| 3 | Z0004526 | HMA DRIVEWAY PAVT 7 | 100 | SQ YD | $73.00 | $110.00 | $105.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $0.0100 | $7,200.00 | $1.00 | |
| 5 | Z0018100 | DRAINAGE STR ADJ SPL | 6 | EACH | $2,350.00 | $2,350.00 | $1,500.00 | |
| 6 | Z0018400 | DRAINAGE STR ADJ | 20 | EACH | $465.00 | $465.00 | $450.00 | |
| 7 | Z0030850 | TEMP INFO SIGNING | 500 | SQ FT | $20.00 | $20.00 | $20.00 | |
| 8 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 10 | 20201200 | REM & DISP UNS MATL | 330 | CU YD | $0.0100 | $20.00 | $80.00 | |
| 11 | 21001000 | GEOTECH FAB F/GR STAB | 1,900 | SQ YD | $0.0100 | $1.00 | $1.00 | |
| 12 | 21101625 | TOPSOIL F & P 6 | 765 | SQ YD | $4.00 | $7.00 | $0.1000 | |
| 13 | 25200110 | SODDING SALT TOLERANT | 765 | SQ YD | $18.50 | $8.50 | $24.50 | |
| 14 | 28000510 | INLET FILTERS | 35 | EACH | $190.00 | $190.00 | $145.00 | |
| 15 | 30300001 | AGG SUBGRADE IMPROVE | 330 | CU YD | $0.0100 | $20.00 | $100.00 | |
| 16 | 35800100 | PREPARATION OF BASE | 18,963 | SQ YD | $0.0100 | $0.1000 | $0.0100 | |
| 17 | 35800200 | AGG BASE REPAIR | 1,100 | TON | $0.0100 | $10.00 | $27.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 13,440 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 19 | 40602965 | HMA BC IL-9.5FG N50 | 1,370 | TON | $101.00 | $108.00 | $105.00 | |
| 20 | 40604060 | HMA SC IL-9.5 D N50 | 2,180 | TON | $101.00 | $110.00 | $98.00 | |
| 21 | 42300300 | PCC DRIVEWAY PAVT 7 | 100 | SQ YD | $65.00 | $65.00 | $65.00 | |
| 22 | 42400800 | DETECTABLE WARNINGS | 820 | SQ FT | $36.00 | $40.00 | $40.00 | |
| 23 | 44000161 | HMA SURF REM 3 | 18,963 | SQ YD | $3.10 | $6.40 | $4.50 | |
| 24 | 44000200 | DRIVE PAVEMENT REM | 200 | SQ YD | $18.00 | $9.00 | $35.00 | |
| 25 | 44000500 | COMB CURB GUTTER REM | 1,600 | FOOT | $9.00 | $9.00 | $9.00 | |
| 26 | 44000600 | SIDEWALK REM | 6,820 | SQ FT | $2.35 | $2.50 | $3.00 | |
| 27 | 44201713 | CL D PATCH T1 6 | 490 | SQ YD | $15.00 | $40.00 | $96.00 | |
| 28 | 44201717 | CL D PATCH T2 6 | 490 | SQ YD | $15.00 | $40.00 | $70.00 | |
| 29 | 44201721 | CL D PATCH T3 6 | 490 | SQ YD | $15.00 | $40.00 | $58.00 | |
| 30 | 44201723 | CL D PATCH T4 6 | 490 | SQ YD | $15.00 | $40.00 | $49.00 | |
| 31 | 60404300 | FR & GRATES T3 | 5 | EACH | $825.00 | $825.00 | $700.00 | |
| 32 | 60406000 | FR & LIDS T1 OL | 5 | EACH | $525.00 | $525.00 | $700.00 | |
| 33 | 60406100 | FR & LIDS T1 CL | 5 | EACH | $525.00 | $525.00 | $700.00 | |
| 34 | 60603800 | COMB CC&G TB6.12 | 1,600 | FOOT | $28.00 | $28.00 | $28.00 | |
| 35 | 66900200 | NON SPL WASTE DISPOSL | 50 | CU YD | $125.00 | $85.00 | $100.00 | |
| 36 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,450.00 | $1,450.00 | $1,450.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $52,000.00 | $55,520.00 | $170,000.00 | |
| 38 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $80,467.82 | $19,881.37 | $7,400.00 | |
| 39 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $100.00 | $100.00 | |
| 40 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $100.00 | $100.00 | |
| 41 | 78000400 | THPL PVT MK LINE 6 | 1,400 | FOOT | $1.25 | $1.75 | $2.65 | |
| 42 | 78000600 | THPL PVT MK LINE 12 | 1,350 | FOOT | $3.00 | $3.50 | $3.45 | |
| 43 | 78000650 | THPL PVT MK LINE 24 | 395 | FOOT | $6.00 | $7.00 | $6.95 |