17-00101-00-BT
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | A Lamp Concrete Contractors, Inc. Low bidder | $379,874 | ||
| 2 | Copenhaver Construction, Inc. | $393,449 | +3.6% | |
| 3 | Alliance Contractors, Inc. | $478,567 | +26.0% | |
| 4 | Sumit Construction Co., Inc. | $481,696 | +26.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 A Lamp Concrete… | #2 Copenhaver Cons… | #3 Alliance Contra… | #4 Sumit Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | A2004621 | T-GLED TR-I IMP 3 | 5 | EACH | $1,050.00 | $900.00 | $693.00 | $770.00 | |
| 2 | A2007122 | T-QUERCUS RUBRA 3 | 6 | EACH | $1,050.00 | $950.00 | $736.00 | $770.00 | |
| 3 | X0325839 | SIGNAL TIMING | 1 | L SUM | $605.00 | $1,000.00 | $550.00 | $600.00 | |
| 4 | X0327980 | PAVMT MRKG REM WTR BL | 93 | SQ FT | $1.00 | $35.00 | $15.00 | $40.00 | |
| 5 | X1700019 | SEG BLK WALL REM/REPL | 56 | SQ FT | $110.00 | $45.00 | $75.00 | $40.00 | |
| 6 | X4240800 | DETECTABLE WARN SPL | 170 | SQ FT | $45.00 | $35.00 | $30.00 | $35.00 | |
| 7 | X7240505 | RELOC SIGN PANEL&POST | 5 | EACH | $350.00 | $350.00 | $150.00 | $150.00 | |
| 8 | Z0013797 | STAB CONSTR ENTRANCE | 50 | SQ YD | $15.00 | $25.00 | $90.00 | $45.00 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $9,000.00 | $21,000.00 | $6,935.00 | $5,000.00 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $25.00 | $20.00 | $10.00 | $18.00 | |
| 11 | 20100110 | TREE REMOV 6-15 | 96 | UNIT | $25.00 | $40.00 | $22.00 | $25.00 | |
| 12 | 20101000 | TEMPORARY FENCE | 560 | FOOT | $1.00 | $3.00 | $3.00 | $6.00 | |
| 13 | 20101200 | TREE ROOT PRUNING | 7 | EACH | $200.00 | $10.00 | $180.00 | $10.00 | |
| 14 | 20101300 | TREE PRUN 1-10 | 9 | EACH | $35.00 | $50.00 | $30.00 | $150.00 | |
| 15 | 20101350 | TREE PRUN OVER 10 | 5 | EACH | $90.00 | $60.00 | $80.00 | $250.00 | |
| 16 | 20200100 | EARTH EXCAVATION | 353 | CU YD | $30.00 | $32.00 | $50.00 | $42.00 | |
| 17 | 20201200 | REM & DISP UNS MATL | 50 | CU YD | $10.00 | $33.00 | $200.00 | $70.00 | |
| 18 | 20400800 | FURNISHED EXCAVATION | 576 | CU YD | $1.00 | $5.00 | $1.00 | $45.00 | |
| 19 | 21001000 | GEOTECH FAB F/GR STAB | 300 | SQ YD | $2.00 | $2.00 | $2.50 | $5.00 | |
| 20 | 21101505 | TOPSOIL EXC & PLAC | 1,090 | CU YD | $5.00 | $15.00 | $56.55 | $70.00 | |
| 21 | 21101615 | TOPSOIL F & P 4 | 600 | SQ YD | $8.00 | $5.00 | $8.00 | $5.25 | |
| 22 | 25000100 | SEEDING CL 1 | 0.5 | ACRE | $3,100.00 | $5,000.00 | $2,567.00 | $2,500.00 | |
| 23 | 25000400 | NITROGEN FERT NUTR | 82 | POUND | $5.50 | $1.00 | $3.00 | $5.00 | |
| 24 | 25000600 | POTASSIUM FERT NUTR | 82 | POUND | $5.50 | $1.00 | $3.00 | $5.00 | |
| 25 | 25100630 | EROSION CONTR BLANKET | 2,420 | SQ YD | $2.20 | $2.00 | $0.9000 | $1.50 | |
| 26 | 25200110 | SODDING SALT TOLERANT | 1,739 | SQ YD | $14.00 | $7.00 | $8.00 | $10.00 | |
| 27 | 28000250 | TEMP EROS CONTR SEED | 10 | POUND | $22.00 | $0.0100 | $2.00 | $12.00 | |
| 28 | 28000400 | PERIMETER EROS BAR | 4,092 | FOOT | $1.00 | $2.00 | $2.10 | $2.20 | |
| 29 | 28000510 | INLET FILTERS | 20 | EACH | $15.00 | $50.00 | $100.00 | $200.00 | |
| 30 | 28001100 | TEMP EROS CONTR BLANK | 358 | SQ YD | $2.20 | $0.0100 | $0.8000 | $2.00 | |
| 31 | 30300001 | AGG SUBGRADE IMPROVE | 50 | CU YD | $10.00 | $37.00 | $100.00 | $48.00 | |
| 32 | 30300112 | AGG SUBGRADE IMPR 12 | 43 | SQ YD | $25.00 | $17.00 | $18.75 | $14.00 | |
| 33 | 35101600 | AGG BASE CSE B 4 | 128 | SQ YD | $5.50 | $11.00 | $6.00 | $6.00 | |
| 34 | 35102200 | AGG BASE CSE B 10 | 2,684 | SQ YD | $13.00 | $14.00 | $33.50 | $12.00 | |
| 35 | 40600275 | BIT MATLS PR CT | 6,038 | POUND | $0.0100 | $0.5000 | $0.4500 | $3.00 | |
| 36 | 40600990 | TEMPORARY RAMP | 45 | SQ YD | $5.00 | $50.00 | $100.00 | $25.00 | |
| 37 | 40603080 | HMA BC IL-19.0 N50 | 350 | TON | $87.00 | $85.00 | $75.16 | $200.00 | |
| 38 | 40603335 | HMA SC "D" N50 | 233 | TON | $98.00 | $103.00 | $86.16 | $220.00 | |
| 39 | 40700100 | BIT MATLS TACK CT | 604 | POUND | $0.0100 | $2.00 | $1.24 | $3.00 | |
| 40 | 42400410 | PC CONC SIDEWALK 8 | 1,146 | SQ FT | $9.00 | $10.00 | $14.00 | $8.00 | |
| 41 | 44000100 | PAVEMENT REM | 23 | SQ YD | $20.00 | $23.00 | $30.00 | $25.00 | |
| 42 | 44000165 | HMA SURF REM 4 | 80 | SQ YD | $20.00 | $20.00 | $20.00 | $18.00 | |
| 43 | 44000500 | COMB CURB GUTTER REM | 129 | FOOT | $8.00 | $9.00 | $10.00 | $10.00 | |
| 44 | 550A0050 | STORM SEW CL A 1 12 | 10 | FOOT | $125.00 | $120.00 | $100.00 | $100.00 | |
| 45 | 550A0340 | STORM SEW CL A 2 12 | 12 | FOOT | $135.00 | $140.00 | $100.00 | $1,200.00 | |
| 46 | 60200805 | CB TA 4 DIA T8G | 1 | EACH | $4,500.00 | $3,700.00 | $6,000.00 | $4,500.00 | |
| 47 | 60207605 | CB TC T8G | 1 | EACH | $2,000.00 | $3,800.00 | $2,480.00 | $3,500.00 | |
| 48 | 60255500 | MAN ADJUST | 6 | EACH | $400.00 | $800.00 | $400.00 | $350.00 | |
| 49 | 60500050 | REMOV CATCH BAS | 2 | EACH | $400.00 | $700.00 | $100.00 | $700.00 | |
| 50 | 60604400 | COMB CC&G TB6.18 | 129 | FOOT | $36.00 | $33.00 | $43.00 | $35.00 | |
| 51 | 67100100 | MOBILIZATION | 1 | L SUM | $22,000.00 | $23,000.00 | $51,708.23 | $10,000.00 | |
| 52 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $91,000.00 | $69,000.00 | $1.00 | $100.00 | |
| 53 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $1.00 | $200.00 | $38,420.00 | $100.00 | |
| 54 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $200.00 | $1.00 | $100.00 | |
| 55 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $200.00 | $1.00 | $8,000.00 | |
| 56 | 72000100 | SIGN PANEL T1 | 30 | SQ FT | $25.00 | $40.00 | $22.00 | $40.00 | |
| 57 | 72900100 | METAL POST TY A | 77 | FOOT | $15.00 | $20.00 | $15.00 | $12.00 | |
| 58 | 78000400 | THPL PVT MK LINE 6 | 248 | FOOT | $4.00 | $4.00 | $3.50 | $4.00 | |
| 59 | 78000600 | THPL PVT MK LINE 12 | 329 | FOOT | $8.00 | $9.00 | $7.00 | $8.00 | |
| 60 | 78000650 | THPL PVT MK LINE 24 | 49 | FOOT | $16.00 | $18.00 | $14.00 | $16.00 | |
| 61 | 81028220 | UNDRGRD C GALVS 3 | 18 | FOOT | $45.00 | $45.00 | $40.40 | $43.00 | |
| 62 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $1,950.00 | $2,100.00 | $1,760.00 | $1,850.00 | |
| 63 | 87301215 | ELCBL C SIGNAL 14 2C | 346 | FOOT | $1.10 | $2.00 | $1.00 | $1.20 | |
| 64 | 87301225 | ELCBL C SIGNAL 14 3C | 469 | FOOT | $1.35 | $2.00 | $1.20 | $1.40 | |
| 65 | 87301245 | ELCBL C SIGNAL 14 5C | 319 | FOOT | $1.55 | $2.00 | $1.40 | $1.60 | |
| 66 | 87301255 | ELCBL C SIGNAL 14 7C | 198 | FOOT | $1.90 | $2.00 | $1.70 | $2.00 | |
| 67 | 87301900 | ELCBL C EGRDC 6 1C | 54 | FOOT | $1.80 | $2.00 | $1.60 | $1.80 | |
| 68 | 87800100 | CONC FDN TY A | 8 | FOOT | $285.00 | $300.00 | $257.00 | $280.00 | |
| 69 | 87900200 | DRILL EX HANDHOLE | 2 | EACH | $385.00 | $380.00 | $347.00 | $370.00 | |
| 70 | 88102717 | PED SH LED 1F BM CDT | 8 | EACH | $685.00 | $670.00 | $621.00 | $650.00 | |
| 71 | 88600100 | DET LOOP T1 | 158 | FOOT | $21.50 | $22.00 | $19.50 | $22.00 | |
| 72 | 88800100 | PED PUSH-BUTTON | 7 | EACH | $613.00 | $600.00 | $557.00 | $600.00 | |
| 73 | 89500100 | RELOC EX SIG HEAD | 3 | EACH | $745.00 | $750.00 | $677.00 | $700.00 | |
| 74 | 89501150 | RELOC EX TS POST | 2 | EACH | $565.00 | $700.00 | $512.00 | $550.00 | |
| 75 | 89502200 | MOD EX CONTR | 1 | EACH | $1,950.00 | $1,900.00 | $1,751.00 | $1,850.00 | |
| 76 | 89502210 | MOD EX CONTR CAB | 1 | EACH | $1,950.00 | $1,900.00 | $1,751.00 | $1,850.00 | |
| 77 | 89502300 | REM ELCBL FR CON | 522 | FOOT | $0.5000 | $1.00 | $0.4000 | $0.5000 | |
| 78 | 89502375 | REMOV EX TS EQUIP | 1 | EACH | $485.00 | $500.00 | $440.00 | $500.00 | |
| 79 | 89502376 | REBUILD EX HANDHOLE | 2 | EACH | $2,600.00 | $2,800.00 | $2,347.00 | $2,500.00 | |
| 80 | 89502385 | REMOV EX CONC FDN | 2 | EACH | $500.00 | $500.00 | $440.00 | $500.00 |